W912P820B0019-0002.pdf

PDF 400 KB Posted

Attached to
W912P820B0019 - WSLP STOCKPILE 1
Solicitation number
W912P820B0019
Issued by

About this file

This document provides an amendment to a solicitation for a federal construction contract. The solicitation is for excavating, processing, and stockpiling clay materials within the Bonnet Carre Spillway in Louisiana, with an option to stockpile at an alternate site up to 6 miles away. The work includes clearing, grubbing, and reconstructing an asphalt ramp. The magnitude of the acquisition is estimated between $25 million to $100 million. Bidders must submit a bid bond and the awardee will be required to provide payment and performance bonds within three days of award. The amendment provides responses to industry questions, revises estimated quantities, and makes changes to specifications regarding overburden removal, permitted work hours, and stockpile locations and measurements.

View the file

Other files

File Type Posted
W912P820B0019 Abstract signed.pdf PDF
W912P820B0019-0012.pdf PDF
W912P820B0019-0010.pdf PDF
W912P820B0019-0009.pdf PDF
W912P820B0019-0008.pdf PDF
W912P820B0019-0007.pdf PDF
W912P820B0019-0005 .pdf PDF
W912P820B0019-0004.pdf PDF
W912P820C0019-P00003.pdf PDF
20B0019-0001.pdf PDF
A21_20B0019_Solicitation rev.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912P820B0019

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of Amendment 0002 is to complete the follow ing:

To provide the Government responses to the Industry questions and to amend sections of the solicitation. Please see continuation sheet.

1. CONTRACT ID CODE PAGE OF PAGES

1 7

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Dec-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P820B0019

X 9B. DATED (SEE ITEM 11)

14-Nov-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Dec-2019

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

CONTINUATION PAGE

Industry Questions and Government Responses for Bonnet Carre Stockpile Contract 1:

1. In the event that overburden is deposited in the borrow pits thru the life of the contract by water seeping thru the spillway structure, will the contractor be compensated for the removal of this additional overburden?

Government Response: No.

2. In the event that overburden is deposited in the borrow pits thru the life of the contract by opening of the spillway structure, will the contractor be compensated for the removal of this additional overburden?

Government Response: Yes.

3. Please provide the Government’s estimated quantities for “Job” items.

Government Response: Borrow Pit 1: 23 acres clearing 4,200 LF perimeter dike Borrow Pit 2:

27 acres clearing 4,250 LF perimeter dike Borrow Pit 3; 25 acres clearing 4,200 LF perimeter dike.

Clearing Stockpile Area 1: 25 acres Clearing Stockpile Area 2: 20 acres

Ramp reconstruction:

Asphalt Wearing Course: 346.6 SY Asphalt Binder Course: 346.6 SY Base Course: 86.7 CY Embankment: 105 CY

4. The Government’s estimated quantity of overburden was provided prior to bid time on the Bonnet Carre Stockpile Contract 2, Solicitation W912P8200020. Please provide the Government’s estimated quantity of overburden for this solicitation.

Government Response: Sand Overburden of Borrow Areas: 170,000 CY

5. Since this is only a stockpile job, with third party testing, can the Superintendent be the Quality Control Manager provided he has the proper training?

Government Response: No.

6. With over triple the quantities of sand overburden to remove compared to Stockpile Contract 2, would the Corps consider increasing the base bid days, which are the same quantity of 370 Calendar Days for both jobs?

Government Response: The Government will verify the existing overburden. At this time, the duration will not be changed.

7. Note 7 provides that 240 Calendar Days will be added for both CLIN 0006 and 0007: is this concurrent if both Optional Work Items are exercised? Or is it consecutive, meaning 240 days added for each, or a total of 480 days? Only 240 calendar days less the weather days that must be allowed, would require moving, processing, and stockpiling 1,000,000 cy in approximately 190 - 200 days.

Government Response: Time extensions for exercise of Optional Work Bid Items 0006 and 0007 are not additive. An amendment will be issued to stipulate Optional Work Items 0006 and 007 will not be exercised concurrently. One or the other will be exercised, not both.

8. Section 9. PERMISSIBLE HOURS OF WORK provides only daylight hours can be worked within the spillway. Can the contractor work multiple shifts with proper lighting?

Government Response: Work is limited to daylight hours for safety concerns and consideration for adjacent residents.

9. The sand overburden is reportedly fifteen feet deep along the tree line in Borrow Pits 1 and 2:

is there a maximum amount of overburden removal that must be completed for the Job price? Is there a depth where exploration may cease?

Government Response: All overburden must be removed to the depth of suitable materials as shown on the plans.

10. Could the Corps provide their anticipated quantities as with the Stockpile 2 job?

Government Response: Quantities for "Job" bid items will be forthcoming.

11. Is the anticipated maximum cumulative volume of clay to be removed from the three pits 1,500,000 cy? Or is it until the pits are exhausted? If the quantity is extended how will the time be adjusted?

Government Response: The stockpile quantity is 1,000,000 CY maximum if Optional Work Items are exercised. Pits shall be excavated until such stockpile fill is obtained.

12. Will there be an Office Trailer requirement for this project that the USACE will share with the contractor? There are no utilities in the spillway that I am aware of so it would be difficult to put one in there. If there is a requirement for this is there an alternate location preferred by the

USACE?

Government Response: No to all questions.

13. Can the Safety Officer and Superintendent be the same person for this project?

Government Response: No.

14. Can clearing and grubbing be burned within the spillway?

Government Response: Yes, provided all local, state and federal requirements are met for such burning.

15. Where is the alternate location for stockpile in the optional work on the bid form. Is this the same location on HWY 61 that was in the previous solicitation. The drawings for that location are not in the new solicitation.

Government Response: Alternate site is located as described in the plans and specs, which is approximately 12 miles away from the borrow areas.

16. The contract is in basic award and option award. If we were awarded this contract, our bonding company would provide a payment and performance bond for the base work. Once the optional work is awarded, a separate payment and performance bond would be provided. Is this acceptable?

Government Response: Yes

SECTION 00010

Pages 7 and 8 of 434. Delete these pages in their entirety and substitute the attached revised pages 00010-7 and 8 therefore.

SECTION 00700

Page 57 of 403. Provision 52.236-4 PHYSICAL DATA, subparagraph (e). Delete this subparagraph in its entirety and substitute the following therefore:

“(e) Estimates of quantities involved in certain items of work for which bids are being solicited on a job basis have been made for the use of the Government. Copies of these quantity estimates may be viewed/obtained by contacting the Contract Specialists for this contract. It is expressly understood that the accuracy of these estimates is in no way warranted and that the furnishing of this information to a bidder will not relieve him of his responsibility to estimate the quantities involved.”

SECTION 31 23 00.00 12

Page 4, paragraph 3.1.3. Delete this paragraph in its entirety and substitute the following therefore:

“3.1.3 Use of Bonnet Carre Floodway Borrow Area

Government-furnished borrow and stockpile areas for the exclusive use in the performance of this contract work have been established in the Bonnet Carre Floodway at the location and within the respective limits shown on the drawings.

Borrow and stockpiling from this source shall be performed in accordance with applicable notations on the drawings and as provided in these specifications. This Government-furnished source of borrow material may be overlain by alluvial sand and silt, deposited by the river, of varying thicknesses as a result of Floodway operation and the removal of sand under the terms of annually issued and renewable Federally granted sand hauling permits for specific tracts. Permit tracts may overlay portions of the designated borrow and stockpile area. The permits for this tract, as well as other tracts, grant a permittee 20 calendar days in which to vacate the tract, remove its equipment and any stockpiled sand from its tract after it receives notice from the Government to vacate the tract. Therefore, the Contractor must give written notice to the Contracting Officer that will allow at least 30 calendar days for notification to the affected sand hauler. This notice will allow the sand hauler adequate time to terminate its operations and grant unobstructed occupancy of the borrow and stockpile areas to the contractor. River water may seep through the Bonnet Carre' Spillway structure when the river stage at Bonnet Carre' is at or above elevation 15.0 feet N.G.V.D. Delays to the Contractor's borrow, stockpiling, and hauling operation from water flowing through the unopened structure when the floodway is not being operated will be subject to the provisions of Section 00700 Contract Clause entitled "DEFAULT (FIXED- PRICE CONSTRUCTION) (FAR 52.249-10)". The Government may need to operate the

Bonnet Carre Floodway, which may adversely affect the availability of borrow. The operation of the floodway will only occur after the President of the Mississippi River Commission has determined that the river has reached a stage or flow that threatens the Federal flood control system downstream of the Spillway. The Government will, in all anticipatory circumstances, give written notice to the Contractor of the potential need or intent to operate the floodway, granting 10 calendar days to cease borrow operations and remove equipment. This notice shall not relieve the Contractor from taking whatever steps necessary to protect its equipment and operations from rising river stages. The Contractor shall cooperate and coordinate its use of mutual haul roads with others. Any changes or delays to the Contractor's operations due to opening the Bonnet Carre Floodway will be made pursuant to Contract Clause in Section 00700, entitled "CHANGES (FAR 52.243-4)".”

SECTION 31 24 00.00 12

1. Page 5, paragraph 1.4.1. Delete this paragraph in its entirety and substitute the following therefore:

“1.4.1 Clay Stockpile within Bonnet Carre Spillway

Payment for all fill material placed and including additional material placed by reason of foundation settlement during construction, will be made at the contract unit price per cubic yard for "Clay Processing/Stockpiling at Bonnet Carre". Price and payment shall constitute full compensation for furnishing all plant, labor, control testing, surveying, employment of professional engineering services, equipment and material, settlement gages, and performing all operations necessary for excavation, all testing, hauling, foundation preparation, material processing for moisture control and blending, placing and compacting the material and all other incidental work required to complete the stockpiling operations at the Bonnet Carre stockpile area 1. The Government reserves the right to remove and utilize partially stockpiled material at any time after a measurement and acceptance of the partial stockpile. During this removal operation, the Government may occupy not more than four acres of the stockpile area during removal operations.”

2. Page 5, after paragraph 1.4.1, add the following new paragraphs as:

“1.4.2 Clay Stockpile within Bonnet Carre Spillway (Optional Work)

Payment for all fill material placed and including additional material placed by reason of foundation settlement during construction, will be made at the contract unit price per cubic yard for "Additional Clay Processing/Stockpiling at Bonnet Carre - OW", if Optional Work is exercised. Price and payment shall constitute full compensation for furnishing all plant, labor, control testing, surveying, employment of professional engineering services, equipment and material, settlement gages, and performing all operations necessary for excavation, all testing, hauling, foundation preparation, material processing for moisture control and blending, placing and compacting the material and all other incidental work required to complete the stockpiling operations at the Bonnet Carre Stockpile area locations. The Government reserves the right to remove and utilize partially stockpiled material at any time after a measurement and acceptance of the partial stockpile. During this removal operation, the Government may occupy not more than four acres of the stockpile area during removal operations.

1.4.3 Clay Stockpile at Alternate Site (Optional Work)

Payment for all fill material placed and including additional material placed by reason of foundation settlement during construction, will be made at the contract unit price per cubic yard for "Clay Processing/Stockpiling at Alternate Site - OW", if Optional Work is exercised. Price and payment shall constitute full compensation for furnishing all plant, labor, control testing, surveying, employment of professional engineering services, equipment and material, settlement gages, and performing all operations necessary for excavation, all testing, hauling, foundation preparation, material processing for moisture control and blending, placing and compacting the material and all other incidental work required to complete the stockpiling operations at an alternate site located outside of the Bonne Carre Spillway. The Government reserves the right to remove and utilize partially stockpiled material at any time after a measurement and acceptance of the partial stockpile. During this removal operation, the Government may occupy not more than four acres of the stockpile area during removal operations.”

3. Renumber existing paragraphs 1.4.2, 1.4.3, and 1.4.4 accordingly.

DRAWINGS

SHEET IDENTIFICATION No. C-02. Delete this drawing in its entirety and substitute the attached revised SHEET IDENTIFICATION No. C-02.

(End of Summary of Changes)