W912P726RA020 Richmond Inner Harbor_FY26_Dredging Specs_(Solicitation)_15Jul26.pdf
PDF 36 MB Posted
- Solicitation number
- W912P726RA020
About this file
This Request for Proposal (RFP) solicits bids for the Richmond Inner Harbor FY26 Maintenance Dredging Project in Contra Costa County, California. The U.S. Army Corps of Engineers, San Francisco District, seeks a single contractor to perform maintenance dredging of Richmond Inner Harbor to -37 feet (MLLW) plus 1 foot of paid overdepth across 14 reaches, with an estimated total volume of 301,700 cubic yards. Dredged material from Reaches 1-14 must be transported to the Government-furnished Montezuma Wetlands Site for placement. The contract will be awarded on a Lowest Price Technically Acceptable (LPTA) basis as a firm fixed price (FFP) agreement. The estimated cost range is $10,000,000 to $25,000,000. Offers are due August 14, 2026, at 11:30 AM Pacific Daylight Time. The period of performance for the base contract is 114 calendar days from Notice to Proceed.
This full and open competition RFP requires offerors to submit technical and price volumes separately through the Procurement Integrated Enterprise Environment (PIEE) website. The technical proposal must address past performance on dredging projects completed within the last three years and equipment availability to complete work within 114 calendar days. Offerors must furnish a bid guarantee of 20 percent of the proposed price, not to exceed $3 million, and performance and payment bonds equal to 100 percent of the contract price. Upon award, the contractor must submit a Small Business Subcontracting Plan with recommended goals of 20 percent small business, 10 percent small disadvantaged business, 5 percent women-owned small business, 2 percent HUBZone, and 1.3 percent service-disabled veteran-owned small business. The procurement falls under NAICS code 237990 with a $37 million small business size standard. All inquiries must be submitted to Contract Specialist Lisa Ip at Lisa.I.Ip@usace.army.mil no later than 14 calendar days before the proposal due date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL (RFP)
FULL AND OPEN COMPETITION
RICHMOND INNER HARBOR FY26
MAINTENANCE DREDGING PROJECT
CONTRA COSTA COUNTY, CALIFORNIA
SOLICITATION NO. W912P726RA020
r.P'ril
US ARMY CORPS OF ENGINEERS
San Francisco District
SO
LI
C
IT
AT
IO
N
SECTION
SOLICITATION
00 10 00
00 21 00
00 45 00
00 70 00
00 72 00
ATTACHMENTS
TABLE OF CONTENTS
COVER SHEET
TABLE OF CONTENTS
TITLE
SOLICITATION, OFFER AND AWARD (STANDARD FORM 1442)
(CONTINUATION STANDARD FROM 1442)
PRICING SCHEDULE
INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS/ OFFERORS AND
EVALUATION CRITERIA FOR AWARD
SUPPLEMENTARY INSTRUCTIONS
REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF BIDDERS/
OFFERORS
CONDITIONS OF THE CONTRACT
CONTRACTING DEFINITIONS
GENERAL CONDITIONS
SPECIAL CONTRACT REQUIREMENT
GENERAL WAGE DETERMINATION
PREAWARD SURVEY
TECHNICAL SPECIFICATIONS
01 00 00
35 00 00
NOTE:
General Requirements
SPECIFICATIONS (SEPARATE PACKAGE)
Waterway and Marine Construction
DRAWINGS (SEPARATE PACKAGE)
SECTIONS 00 21 00 AND 00 22 00 ARE INCLUDED FOR SOLICITATION
PURPOSES ONLY. THESE SECTIONS WILL BE REMOVED, MAINTAINED IN
THE CONTRACT FILE AND NOT MADE PART OF THE CONTRACT.
SECTION 00 45 00, AS COMPLETED BY AWARDEE, IS INCORPORATED
INTO ANY RESULTANT CONTRACT BY REFERENCE.
AMENDMENTS ARE INCORPORATED INTO THE RESULTANT CONTRACT.
SUBCONTRACTING PLAN (IF REQUIRED) BECOMES AN ATTACHMENT TO AND
A MATERIAL PART OF THE CONTRACT.
00 71 00
00 22 00
00 73 00
SO
LI
C
IT
AT
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
PAGE OF PAGES
W912P726RA020
3. DATE ISSUED
15 JUL 2026
W075 ENDIST SAN FRAN
KO CONTRACTING DIVISION, 450 GOLDEN GATE AVENUE
SAN FRANCISCO, CA 94102-3406
UNITED STATES
LISA IP, EMAIL: LISA.I.IP@USACE.ARMY.MIL TELEPHONE: 415-503-6877
W912P7
LISA IP 415-503-6877
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
PROJECT TITLE: RICHMOND INNER HARBOR FY26 MAINTENANCE DREDGING
PROJECT LOCATION: CONTRA COSTA COUNTY, CA
WORK INCLUDES ANNUAL MAINTENANCE DREDGING OF THE RICHMOND INNER HARBOR TO -37-FT (MLLW) PLUS 1 FOOT OF PAID OVERDEPTH AND TRANSPORTING OF THE DREDGED MATERIAL PER THE REQUIREMENTS IN SPECIFICATION. MATERIAL TO BE DREDGED FROM REACHES 1 THROUGH 14 IS SUITABLE AND SHALL BE TAKEN FOR PLACEMENT AT MONTEZUMA WETLANDS SITE. CONTRACTOR SHALL REFER TO THE DMMO SUITABILITY DETERMINATION ATTACHED AT THE END OF THE SPECIFICATIONS PACKAGE. SAMPLE AREAS 1 THROUGH 4 CORRESPOND TO REACHES 1 THROUGH 10 WHILE SAMPLE AREAS 5
AND 6 CORRESPOND TO REACHES 11 THROUGH 14.
ESTIMATED COST RANGE IS BETWEEN $10,000,000 AND $25,000,000.
QUESTIONS RELATING TO THIS SOLICITATION AND TECHNICAL INQUIRIES WILL BE SUBMITTED VIA EMAIL TO THE ASSIGNED CONTRACT SPECIALIST. INQUIRIES
MUST BE RECEIVED NO LATER THAN 14 CALENDAR DAYS PRIOR TO PROPOSAL DUE DATE.
1 114 section 00 73 00
11:30 AM
14 AUG 2026
SO
LI
C
IT
AT
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
SO
LI
C
IT
AT
CONTINUATION OF STANDARD FORM 1442
BLOCK 20D:
(1) IF THE OFFEROR IS A JOINT VENTURE, EACH PARTICIPANT IN THE JOINT VENTURE
MUST COMPLETE THE FOLLOWING:
Company Name Signature Title
Company Name Signature Title
Company Name Signature Title
NOTE: If a corporation is participating as a member of a Joint Venture, the certificate below must also be completed and signed.
CORPORATION AUTHORIZATION TO PARTICIPATE IN JOINT VENTURE CERTIFICATE
I, ______________________(insert name), certify that I am the Secretary of the corporation named as a participant in a Joint Venture on this offer; that _____________________(insert name), who signed said offer on behalf of the corporation,was then ______________________(insert title) of said corporation; that the signature thereto is genuine; that said contract was duly signed, sealed and attested for and in behalf of said corporation by authority of its governing body; and that the corporation is authorized to participate in the Joint Venture on this offer.
(Name of Corporation)
(Secretary)
(2) IF THE OFFEROR IS A PARTNERSHIP, LIST FULL NAME OF ALL PARTNERS BELOW.
SIGNATURES BY ALL PARTNERS HERE SIGNIFY THAT THE INDIVIDUAL WHO SIGNED THE
OFFER IN BLOCK 20B HAS THE AUTHORITY TO BIND THE PARTNERSHIP.
Name
Name
Signature
Signature
Name Signature
(3) IF THE OFFEROR IS A CORPORATION, THE OFFER SHALL BE SIGNED IN THE
CORPORATE NAME FOLLOWED BY THE WORD "BY" AND THE SIGNATURE OF THE PERSON
AUTHORIZED TO SIGN THE OFFER IN BLOCK 20B. PROVIDE PROOF THAT THE PERSON
SIGNING FOR THE CORPORATION HAS THE AUTHORITY TO BIND THE CORPORATION BY
COMPLETING THE FOLLOWING CERTIFICATE:
SO
LI
C
IT
AT
CONTINUATION OF STANDARD FORM 1442
CORPORATION AUTHORIZATION CERTIFICATE
I, _______________________________(insert name), certify that I am the
Secretary of the corporation named as offeror in the within offer; that
______________________(insert name), who signed said offer on behalf of the corporation, was then ______________________________(insert title) of said corporation, that the signature thereto is genuine; that said contract was duly signed, sealed and attested for in behalf of said corporation by authority of its governing body.
(Name of Corporation)
(Secretary)
(4) IF THE OFFEROR IS AN INDIVIDUAL DOING BUSINESS AS A FIRM, THE OFFER
SHALL BE SIGNED BY THAT INDIVIDUAL IN BLOCK 20B FOLLOWED BY THE WORDS "AN
INDIVIDUAL DOING BUSINESS AS _____________________________________ (INSERT
NAME OF FIRM).
(5) WHEN AN AGENT SIGNS THE OFFER, PROVIDE PROOF OF THE AGENT'S AUTHORITY TO
BIND THE PRINCIPAL.
SO
LI
C
IT
AT
Contract Line Item No.(CLIN)
Description of Supplies and Services
*Quantity Unit Unit
Price($) Amount($)
0001 Mobilization and Demobilization 1 Job
(JA)
Dredging Reach 1 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 34,100
CUBIC
YARD
(CY)
Dredging Reach 2 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 33,400
CUBIC
YARD
(CY)
Dredging Reach 3 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 21,000
CUBIC
YARD
(CY)
Dredging Reach 4 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 29,300
CUBIC
YARD
(CY)
Dredging Reach 5 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 35,800
CUBIC
YARD
(CY)
Dredging Reach 6 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 34,600
CUBIC
YARD
(CY)
SECTION 00 10 00
PRICING SCHEDULE
RICHMOND INNER HARBOR FY26 MAINTENANCE DREDGING
SO
LI
C
IT
AT
Dredging Reach 7 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 29,100
CUBIC
YARD
(CY)
Dredging Reach 8 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 18,900
CUBIC
YARD
(CY)
Dredging Reach 9 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 19,000
CUBIC
YARD
(CY)
Dredging Reach 10 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 8,000
CUBIC
YARD
(CY)
Dredging Reach 11 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 13,600
CUBIC
YARD
(CY)
Dredging Reach 12 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 4,800
CUBIC
YARD
(CY)
SO
LI
C
IT
AT
Dredging Reach 13 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader. Includes light monitoring associated with eelgrass 15,900
CUBIC
YARD
(CY)
Dredging Reach 14 to -37-ft MLLW plus 1-foot of paid Over-depth with delivery to the Government furnished Montezuma Wetland Offloader 4,200
CUBIC
YARD
(CY)
Total (Item 0001 through 0015)
1 .
2 .
3 .
4 .
5 .
End of Document
Dredge material placement shall meet the requirements in specification Section 01
11 00 SUMMARY OF WORK.
* - ALL QUANTITIES ARE ESTIMATES. SEE Variation in Estimated Quantity, SECTION 00 73 00
(GENERAL CONDITION) OF THE CONTRACT.
IMPORTANT NOTES:
The term "Job", which appears on the Pricing Schedule (Section 00 01 00) under “Unit” for Proposal Item No. 0001 shall be considered as a Lump Sum. The Variation in Estimated Quantities contract clause, FAR 52.211-18, shall not apply to Proposal Item No. 0001.
BASIS of AWARD: The contract will be awarded in accordance with subsection 2 of section 00 22 00 “Supplementary Conditions”.
The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site in accordance with the Change Clause FAR 52.243-4.
The Contractor shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.
301,700 CY + 1 Job
SO
LI
C
IT
AT
Richmond Inner Harbor FY26 Maintenance Dredging
DREDGING PLANT AND EQUIPMENT SCHEDULE
Available Plant to be Used
Age and Overall No. Type Capacity Manufacturer Condition Location Dimensions
Dredges:
Scows:
Tugboats:
Quantity Measurement Equipment:
Quality Control:
DDLS:
1. In preparing the above tabulation the bidder shall insert the following information under the appropriate heading, using a separate line for each major item and an additional page if necessary.
Dredging Plant & Equipment Schedule Section 00 10 00
SO
LI
C
IT
AT
a. Number. For dredges give identifying number or name.
b. Type. Under this heading give description as follows: For clamshell dredge show bucket capacity in in-situ cubic yards, for clamshell and/or pipe-line dredges show inside diameter of intake and discharge pipe, horsepower of pump engine, and type of power; for hopper dredges show capacity at overflow, number of dredge pumps, suction pipe size, propulsion type and horsepower, dredge length O/A and beam O/A.
c. Capacity. Under this heading, state the estimated capacity of the plant in cubic yards per month when working materials similar to those which it is anticipated will be encountered in the performance of the work for clamshell, hopper, pipeline, and scow.
d. Overall Dimensions. State overall length and beam.
e. DDLS. List the DDLS equipment and number of each that will be used in accordance with Appendix 5 of the specifications.
2. List two dredging projects with location, dates of completion, and name of project owner:
(a)
(b)
Section 00 10 00
SO
LI
C
IT
AT
Section 00 21 00
SECTION 00 21 00
INSTRUCTIONS, CONDITIONS AND NOTICES TO
OFFERORS AND EVALUATION CRITERIA FOR AWARD
1 .1 GENERAL
The work includes maintenance dredging of the Richmond Inner Harbor to -37-ft (MLLW) plus 1 foot of paid overdepth and transporting of the dredged material per the requirements in specification Section 00 10 00 PRICING SCHEDULE and 01 11 00 SUMMARY OF WORK. Material to be dredged from Reaches 1 through 14 is suitable and shall be taken for placement at Montezuma Wetlands site. Contractor shall refer to the DMMO Suitability Determination attached at the end of the specifications package. Sample areas 1 through 4 correspond to Reaches 1 through 10 while sample areas 5 and 6 correspond to Reaches 11 through 14.
This requirement is for full and open competition and will be awarded as a single Firm-Fixed Price (FFP) contract.
1.2 PROPOSAL EXPENSES AND PRE-CONTRACT COSTS
This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.
1.3 ACCURACY IN PROPOSAL
Proposal must set forth full, accurate, and complete information as required by this RFP (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.
1.4 PROPOSAL QUESTIONS
Questions relating to this solicitation and technical inquiries will be submitted via email to the assigned contract specialist, Lisa Ip via email at Lisa.I.Ip@usace.army.mil.
Please include the solicitation number, the project title, and location of the project together with company name, email address, and telephone number in your correspondence. Inquiries must be received no later than 14 calendar days prior to the proposal’s due date.
Answers to pertinent questions will be posted on PIEE (https://piee.eb.mil) and System for Award
Management website (sam.gov). Changes to the solicitation will be made by amendment only (SF30), which will also be posted to PIEE and SAM.
1.5 COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS
Copies of the solicitation are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to https://piee.eb.mil/ and sam.gov.
All amendments will be posted to https://piee.eb.mil/ and sam.gov. It shall be the contractor's responsibility to check the website for any amendments. The offeror shall submit in the proposal all requested information specified in this section of RFP.
1.6 PROPOSAL FORMAT AND SUBMITTAL REQUIREMENT
See 3.2 General Proposal Preparation located in Section 00 22 00 Supplementary Instruction.
1.7 SPECIAL INSTRUCTIONS FORSUBMITTING YOUR PROPOSAL:
SO
LI
C
IT
AT
**Note**: All prospective Offerors must be registered in the System for Award Management (SAM -www.SAM.gov) and the Procurement Integrated Enterprise Environment (PIEE) website to be able to view and download solicitation information, and to submit offers.
Solicitation documents, plans, and specifications are only available to be download from PIEE, which may be accessed at https://wawf.eb.mil OR https://piee.eb.mil OR https://piee.eb.mil/xhtml/unauth/ home/login.xhtml.
Offers MUST BE submitted electronically through the PIEE website. The Government is not responsible for any loss of internet connectivity or for an offeror’s inability to access the documents posted at the referenced website. All offerors are advised that this project may be delayed, cancelled or revised at any time during the solicitation, selection, evaluation, and/or final award process.
Registration should be completed one (1) week prior to the anticipated solicitation release date. USACE will not notify Offerors of any changes to the solicitation; Offerors must monitor PIEE and SAM for the solicitation to be posted, and for any posted changes or amendments.
See attachments "PIEE Solicitation Module Vendor Access Instructions", "SOP PIEE Proposal Manager Offeror", and "SOP PIEE Posting Offer" for instructions on getting access to the PIEE Solicitation Module and submitting Offeror proposals.
It is the responsibility of all Offerors to ensure their proposal submissions are complete, inclusive of the price schedule, acknowledge of amendments, bid guarantee, and all additional information requested through this advertisement.
1.8 OTHER DELIVERY METHODS
Telegraphic, Facsimile, emailed, HAND DELIVERED, MAILED, or comparable delivery methods of the Proposal Package are not acceptable.
Proposal may only be modified or withdrawn by electronic means through PIEE. A notice to modify or withdraw a proposal sent via PIEE must be received in PIEE no later than the due date and time.
1.9 PERFORMANCE AND PAYMENT BONDS
The offeror will, furnish performance and payment bonds within the time established in the contract in accordance with FAR 52.228-15 DEV located in Section 00 72 00. The offeror will provide the bonds to Lisa Ip at lisa.i.ip@usace.army.mil and Nairi Freeman at nairi.freeman@usace.army.mil.
2.0 INDIVIDUAL SURETIES IN SUPPORT OF BONDS
An offeror utilizing individual sureties in support of a bid bond shall include a Standard Form (SF) 28 (Affidavit of Individual Surety), accompanied by a pledge of acceptable assets from each person acting as an individual surety, and include these with the SF 24 (Bid Bond), and the proposal itself (see clause titled "Pledges of Assets," FAR 52.228-11 DEVIATION 2020 O0016).
Pledges of acceptable assets shall be in the form of (1) evidence of an escrow account and/or (2) a recorded lien on real estate.
Failure to provide required documentation described herein may cause the offeror to be deemed
"unacceptable".
2.1 BID GUARANTEE FORM AND AMOUNT
See Tab 5 Offer Guarantee Form and Amount; located in Section 00 22 00 Supplementary Instructions
2.2 CONTRACTOR RESPONSIBILITY, PRE-AWARD SURVEY
See Tab 6 Contractor Responsibility, Pre-Award Survey Information; located in Section 0022 00-
SO
LI
C
IT
AT
Supplementary Instructions
2.3 PREPARATION OF SUBCONTRACTING PLAN (SEP 2004)
a) See FAR 52.219-9, Small Business Subcontracting Plan, and DFARS 252.219-7996 DEV 2026-O0037, Small Business Subcontracting Plan (DOD Contracts), incorporated by reference into this contract in Section 00 70 00 and 00 72 00.
b) The Small Business Subcontracting Plan is not required from the low offeror until after the selection of the lowest offeror; it is not required as part of the proposal package. After the selection of offeror, if the selected offeror fails to submit an acceptable plan within the time prescribed by the Contracting Officer, the offeror will be ineligible for award.
c) Contact Contracting Officer with questions on the Small Business Subcontracting Plan requirements.
d) The acceptable Small Business Subcontracting Plan will be incorporated into and made a material part of the contract. The Corps of Engineers high encourages all offerors to meet the recommended subcontracting goals as follows:
Small Businesses 20% Small, Disadvantaged Businesses 10.0% Women-Owned Small Businesses 5.0% HUBZone Small Business 2.0% Service Disabled Veteran Owned Small Business 1.3%
The goals are calculated as a percentage of the TOTAL SUBCONTRACTING DOLLARS, NOT THE
TOTAL CONTRACT AMOUNT.
2.4 PERIOD OF PERFORMANCE (PoP):
The PoP for the base contract is 114 days.
SO
LI
C
IT
AT
Section 00 21 00 - Instructions
FAR Provisions Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.204-7 System for Award Management- Registration. (Deviation 2026- O0038)
2026-02
52.214-34 Submission of Offers in the English Language.
1991-04
52.214-35 Submission of Offers in U.S.
Currency.
1991-04
52.215-1 Instructions to Offerors- Competitive Acquisition.
(Deviation 2026-O0038)
2026-02
52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (Deviation 2026- O0038)
2026-02
52.233-2 Service of Protest. (Deviation 2026-O0038)
2026-02
DFARS Provisions Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.204-7024 Notice on the Use of the Supplier 2023-03
SO
LI
C
IT
AT
Performance Risk System.
252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors.
2023-01
FAR Provisions Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.216-1 Type of Contract. (Deviation 2026-O0038)
2026-02
Type of Contract (Feb 2026) (Deviation 2026-O0038)
The Government contemplates award of a contract resulting from this solicitation.firm fixed price
(End of provision)
52.228-1 Bid Guarantee. 1996-09
Bid Guarantee (Sept 1996)
Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening(a) of bids, may be cause for rejection of the bid.
The bidder shall furnish a bid guarantee in the form of a firm commitment, bid bond(b) e.g., supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds-
To unsuccessful bidders as soon as practicable after the opening of bids; and(1)
To the successful bidder upon execution of contractual documents and bonds (including any(2) necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
SO
LI
C
IT
AT
The amount of the bid guarantee shall be percent of the bid price or $(c) twenty (20) , whichever is less.3,000,000.00
If the successful bidder, upon acceptance of its bid by the Government within the period(d) specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
In the event the contract is terminated for default, the bidder is liable for any cost of(e) acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of clause)
52.252-1 Solicitation Provisions Incorporated by Reference.
1998-02
Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://acquisition.gov/far-overhaul
(End of provision)
52.252-3 Alterations in Solicitation. 1984-04
Alterations in Solicitation (Apr 1984)
Portions of this solicitation are altered as follows:
252.204-7998 Alt A
52.215-1 Alt 1
52.225-12 Alt II
SO
LI
C
IT
AT
(End of clause)
52.252-5 Authorized Deviations in Provisions.
2020-11
Authorized Deviations in Provisions (Nov 2020)
The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1)(a) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
The use in this solicitation of any 48(b) Defense Federal Acquisition Regulation Supplement ( CFR Chapter ) provision with an authorized deviation is indicated by the addition of2 "(DEVIATION)" after the name of the regulation.
(End of provision)
DFARS Provisions Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.215-7012 Requirements for Submission of Proposals via Electronic Media.
2018-01
REQUIREMENTS FOR SUBMISSION OF PROPOSALS VIA ELECTRONIC MEDIA (JAN
2018)
The Offeror shall submit the cost portion of the proposal via the following electronic media: PIEE
(End of provision)
SO
LI
C
IT
AT
Section 00 22 00 – Supplementary Instruction
GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS, EVALUATION STANDARDS
FOR CONTRACT AWARD
1. OVERVIEW
Proposals received in response to this solicitation for the Richmond Inner Harbor FY26 Maintenance Dredging Project, Contra Costa County, California will be evaluated using the Lowest Price Technically Acceptable method of selecting the contractor oƯering best value to the Government, as explained below.
2. BASIS OF AWARD
2.1. ELIGIBILITY FOR CONTRACT AWARD
In accordance with the requirements of Federal Acquisition Regulation (FAR) Part 9, no contract shall be entered into unless the Contracting OƯicer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met. This includes the FAR requirement that no award shall be made unless the contracting oƯicer makes an aƯirmative determination of responsibility of the prospective awardee. To be determined responsible, a contractor must meet the general standards in FAR Part 9 and any special standards set forth in this solicitation.
2.2. SOURCE SELECTION USING THE LOWEST-PRICE, TECHNICALLY-ACCEPABLE
(LPTA) METHOD
The Government shall evaluate all proposals. The contract will be awarded to this oƯeror upon a determination of responsibility by the Contracting OƯicer (see paragraph 2.1, above).
3. GENERAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS
For purposes of this RFP, an “OƯeror” may include a group of two or more entities that have formed a “contractor team arrangement”. In the case of entities that have formed a contractor team arrangement, the experience and performance history of any member of the team, whether or not gained while working with the other member(s) of the currently-proposed contractor team arrangement, may be presented in the OƯeror’s proposal.
In the case of contractor team arrangements involving a prime contractor and subcontractor(s), where the prime contractor submits the proposal in response to this RFP, the prime contractor must have completed at least one of the projects submitted in fulfillment of Factor 1 of this RFP. If information about a subcontractor is submitted, the
SO
LI
C
IT
AT
Government will review the information on the presumption that this subcontractor will perform similar work in the construction of this project, should award be made to the respective oƯeror. No such awardee may substitute another subcontractor without the Government’s prior written approval.
Similarly, an OƯeror that relies on the performance history of a member or members of a proposed contractor team arrangement will be expected to maintain that arrangement during performance of any contract awarded to that OƯeror under this RFP. As a part of its proposal, the OƯeror must provide a contractor team agreement signed by all parties, identifying the legal name(s) of all entities and describing the nature of each entity’s relationship (teaming/partnering, joint venture, etc.) and its proposed role in performance of this contract. Past Performance information of other than the OƯeror will not be considered without the team agreement. In the case of joint ventures, at least one project will be submitted from each member to demonstrate past experience. This documentation must be provided in the applicable section of the OƯeror's proposal.
3.1 Media, Page Size, Margins, Fonts, and Page Limitations.
Submit only electronic files as specifically stated in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. Do not include links to information on websites in lieu of incorporating the information physically into the proposal. Except where another size is specifically authorized for a submission, use only 8 1/2” x 11” electronic pages. Use at least 1-inch margins; except headers and footers may be outside the 1-inch margins. Do not justify the right margin. Ensure that all text and graphics are clearly legible. Do not use a font size smaller than 10-point font, and do not use unusual font styles such as script, or condensed fonts. Pages furnished for organizational purposes only, such as a “Table of Contents” or divider tabs, are excluded from page limitations.
3.2 Conditional OƯers.
Do not include exceptions to the terms and conditions of the solicitation in either the technical or price proposal volumes. Inclusion of any company terms and conditions that conflict with the terms and conditions of the solicitation may result in a determination that the oƯer is unacceptable and thus ineligible for award. Resolve questions about the terms and conditions or technical requirements of the solicitation prior to submission of your oƯer; see “Special Instructions for Submitting Your Proposal”, located in Section 00 21 00.
3.3 Restrictions on OƯeror-Provided Information.
Proposals shall not contain classified data. “Confidential” projects may be submitted to demonstrate capability as long as all of the information required for evaluation as specified
SO
LI
C
IT
AT
herein can be provided to the Government as part of the oƯeror’s technical proposal.
OƯerors that include data in their proposals that they do not want disclosed or used except for evaluation purposes, must redact the data in accordance with FAR 52.215-1, Instructions to OƯerors - Competitive Acquisition.
4 GENERAL PROPOSAL PREPARATION.
The proposal shall be submitted as summarized below.
(1) Volume I – Technical Volume
(a) Factor 1: Past Performance
(b) Factor 2: Availability of Equipment
(2) Volume II – Price Volume
(a) Proposal Cover Sheet
(b) Standard Form (SF)1442, to include acknowledgement of Amendments, and Joint Venture Agreement (if applicable)
(c) Price Schedule
(d) Annual Representations and Certifications
(e) OƯer Guarantee
(f) Pre-Award Survey Information
Each oƯeror must submit a proposal consisting of a “technical” volume, and a “price” volume. The two volumes must be submitted as separate volumes. Both volumes must be received no later than the date and time specified in Block 13 of SF 1442, or as amended in the SF 30. The information in the two volumes is evaluated separately and independently.
Do not cross-reference material between the non-price and price volumes.
4.1 Marking of Proposal Volumes.
Name the technical volume as the “Technical Volume” and name the price volume as the “Price Volume”, and include the project title and location, solicitation number, name and address of the oƯeror on the title page of each volume. OƯerors must include a table of contents for each proposal volume.
4.2 TECHNICAL VOLUME
The Technical proposal must be submitted as one complete PDF electronic document.
4.2.1. Format, Content and Tabs for the Technical Volume:
There is a fifteen (15) page limit for the overall technical proposal; however, there may be limits imposed at the tab level. Organize your technical proposal as indicated below.
The tabs directly correlate to the technical evaluation factors. Although the Government may use information obtained from any source in its evaluation of the technical
SO
LI
C
IT
AT
proposal, the Government is not obligated to search for or to consider information that belongs under a specific tab in an oƯeror’s proposal but is actually elsewhere in the proposal. Limit proposal submittals to the information specified; excess information will not be evaluated.
The term “tabs” means searchable PDF bookmarks.
4.2.2 Tab 1 of the Technical Proposal: Factor 1 Past Performance
4.2.2.1 Submission Requirements
The OƯeror shall provide past performance information on dredging projects within the last three (3) years. Experience and Capability, using the Contractor Performance Assessment Reporting System (CPARS) for any past federal projects submitted, and other sources for non-federal projects.
If CPARS evaluations are not available, the OƯeror shall submit a Past Performance Questionnaire (PPQ) for each project. OƯerors should follow-up with clients/references to ensure timely submittal of questionnaires. Completed PPQs should be submitted as part of the oƯeror’s proposal. If the OƯeror is unable to obtain a completed PPQ before the proposal closing date, the OƯeror shall complete and submit the first page of the PPQ, which provides contract and reference contact information for the project(s). The OƯeror shall ensure correct phone numbers and email addresses are provided for each point of contact.
Completed PPQs may also be submitted by the preparer directly to the Contract Specialist (lisa.i.ip@usace.army.mil) and Contracting OƯicer (nairi.freeman@usace.army.mil) via email prior to the RFP closing date.
The Government may review and consider information obtained from other sources, e.g., CPARS information using CAGE/Unique Entity ID of the teaming arrangement, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), etc.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the OƯeror.
Each example project must start on a new page and there is no page limitation for CPARS and PPQ’s submission. Pass Performance will not count against the page limitation for this volume.
4.2.2.2 Evaluation Criteria:
SO
LI
C
IT
AT
The past performance evaluation is an assessment of the oƯeror’s ability to successfully perform this requirement based on the oƯeror’s record of relevant past projects, and the documented level of satisfaction of each project owner after completion of construction.
Past Performance will be determined relevant if a submitted project is similar in size, scope, and complexity to this requirement.
How well the oƯeror performed the prior contracts submitted under Factor 1 will be evaluated by reviewing CPARS evaluations, completed PPQ forms and other information available to the Government.
*NOTE: If an oƯeror does not have a record of relevant past performance or information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the oƯeror may not be evaluated favorably or unfavorably on past performance (IAW FAR 15.202(c)(1)). A neutral rating shall be considered acceptable.
Each OƯeror shall be assigned one of the two ratings listed below.
Acceptable - Based on the oƯeror’s performance record, the Government has a reasonable expectation that the oƯeror will successfully perform the required eƯort, or the oƯeror’s performance record is unknown *(See note above).
Unacceptable - Based on the oƯeror’s performance record, the Government does not have a reasonable expectation that the oƯeror will be able to successfully perform the required eƯort
4.2.3. Tab 2 of the Technical Volume: Factor 2 – Availability of Equipment
4.2.3.1 Availability of Equipment – Evaluation Factor
The OƯeror shall provide a projected timeline and supporting narrative detailing the availability of equipment. The narrative shall be task-oriented, clearly indicating the number of calendar days following pre-construction submittals and mobilization— assumed to occur approximately 30 calendar days after Notice to Proceed (NTP)—by which dredging activities are to commence and be completed.
The narrative shall also include a summary of any failures and/or successes related to equipment availability on the last five dredging projects.
SO
LI
C
IT
AT
Constraints:
The OƯeror must demonstrate the capability and flexibility of equipment availability to meet the proposed contract completion period. The narrative shall clearly identify any known or anticipated constraints, such as:
• Equipment or labor availability
• Weather impacts
• Other logistical or operational limitations
4.2.3.2 Submission Requirements Evaluation Criteria:
The Government will evaluate the OƯeror’s Availability of Equipment narrative to assess the likelihood that equipment will be provided in a timely and eƯective manner to ensure successful completion of the project within the specified period of performance.
Narratives that clearly demonstrate the OƯeror’s ability to complete dredging within 114 calendar days from Notice to Proceed (NTP), along with a general understanding of potential factors that could impact availability (e.g., labor, weather, logistics), will be considered acceptable.
Proposals that indicate equipment availability or project completion beyond 114 calendar days after NTP will be rated Unacceptable under this factor.
A proposal will be rated as Unacceptable if it does not meet the definition of Acceptable.
Technical Acceptable/Unacceptable Ratings:
o Acceptable - Proposal meets the minimum requirements of the solicitation o Unacceptable - Proposal does not meet the minimum requirements of the solicitation
4.3. PRICE VOLUME.
4.3.1 FORMAT, CONTENTS, AND LIST OF TABS FOR THE PRICE PROPOSAL
This should be a separate file from the technical proposal. There are no page limits for the price proposal; however, responses should be focused, providing required information only. Organize your price proposal as indicated below.
Tab 1: Proposal Cover Sheet.
SO
LI
C
IT
AT
As required by FAR 52.215-1(c)(2)(i)-(v), the proposal cover sheet must include the following items:
1. Solicitation Number.
2. The name, address, email, and telephone numbers of the oƯeror.
3. A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are oƯered at the price set opposite each item.
4. Names, titles, e-mail address, and telephone numbers of persons authorized to negotiate on the oƯeror’s behalf with the Government in connection with this solicitation
5. Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority, unless that evidence has been previously furnished to the issuing oƯice.
Tab 2: SF 1442; Acknowledgement of Amendments; Joint Venture Agreement
The Standard Form (SF) 1442 must be completed by the oƯeror and duly executed with an original signature by the oƯicial(s) identified in the proposal cover sheet as authorized to bind the oƯeror in accordance with FAR 4.207, which includes Contractor Team Arrangements. Include the oƯeror’s CAGE code in block 14 of the SF 1442, along with the oƯeror’s address. All amendments must be acknowledged in accordance with the instructions on the Standard Form 30, Amendment. If the oƯeror is a Joint Venture (JV), include a copy of the JV agreement and indicate its status.
Tab 3: Contract Line-Item Number (CLIN) and Pricing Schedule and Dredging Plant and Equipment Schedule
Submit the completed Contract Line-Item Number (CLIN) Schedule on the SF 1442 and provided Price Schedule with the oƯeror’s proposed contract prices inserted in the appropriate spaces. Prices must be provided for all CLINs. Submit the Dredging Plant and Equipment Schedule under Section 00 10 00.
Tab 4: Annual Representations and Certifications
The oƯeror must have electronically completed the annual representations and certifications on the “System for Award Management” (SAM) website in accordance with DFARS 252.204-7998. The oƯeror is responsible for ensuring that these on-line Representations and Certifications are updated as necessary to reflect changes, but at least annually to ensure that they are kept current, accurate and complete.
SO
LI
C
IT
AT
Tab 5: OƯer Guarantee Form and Amount
The oƯeror shall furnish a separate bid guarantee in accordance with the solicitation provision titled "Bid Guarantee", FAR 52.228-1. In accordance with FAR 28.101-2 (b) the bid guarantee amount shall be at least 20 percent of the "proposed price" but shall not exceed $3 million. When the penal sum is expressed as a percentage, a maximum dollar limitation may be stated.
In accordance with FAR 28.106-1, a Standard Form (SF) 24 shall be used for the bid bond.
In accordance with FAR 28.202(a) (1), corporate sureties utilized must appear on the list contained in the Department of Treasury Circular 570 titled, "Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and Acceptable Reinsuring Companies."
Contractor shall provide written confirmation that the Contracting Specialist may contact the bonding company to confirm the bond agreement’s legitimacy.
Tab 6: Contractor Responsibility, Pre-Award Survey Information
To determine a contractor's responsibility for purposes of contract award in accordance with FAR Part 9, the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work (see Attachment 2, Pre-award Survey). The Government will request this information from the eligible contractor after receipt of oƯer if they have not had a contract with the San Francisco District within the last twelve months and the Government will set a due date for its submission.
(a) If required to determine that a prospective contractor is responsible, the oƯeror must:
1) Demonstrate that they have adequate financial resources to perform the contract or the ability to obtain them.
2) Be able to comply with the required or proposed delivery or perform schedule, taking into consideration all existing commercial and governmental business commitments.
3) Have a satisfactory performance record. In making the determination of responsibility, the Government Contracting OƯicer shall consider relevant past performance information. A prospective contractor shall not be determined as
SO
LI
C
IT
AT
responsible or not responsible solely based on a lack of relevant performance history except when there are special standards set forth in the solicitation, which applies, to all oƯerors that must be met in order to receive the award. These special standards may be necessary when unusual expertise or specialized facilities are necessary in the performance of the contract; therefore, in order to be determined as responsible for a particular contract, the oƯeror must be able to meet those special standards. A prospective contractor that is or recently has been seriously deficient in contract performance shall be presumed to be nonresponsive unless the Contracting OƯicer determines that the circumstances were beyond the contractor's control or that the contractor has taken appropriate corrective action.
Other responsibility considerations by the Contracting OƯicer will include past eƯorts by the contractor to apply suƯicient tenacity and perseverance to perform acceptably, to meet quality requirements of contracts, and the contractor's past compliance with subcontracting plans (if required) under recent contracts.
4) Have a satisfactory record of integrity and business ethics.
5) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
6) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them.
7) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
SO
LI
C
IT
AT
Section 00 45 00 - Representations and Certifications
FAR Provisions Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions.
2024-09
52.229-12 Tax on Certain Foreign Procurements.
2021-02
DFARS Provisions Incorporated by Reference
Number Title Effective Date
Alternate Deviation
Variation Effective Date
252.203-7005 Representation Relating to Compensation of Former DoD Officials.
2022-09
252.204-7008 Compliance with Safeguarding Covered Defense Information Controls.
2016-10
252.225-7055 Representation Regarding Business Operations with the Maduro Regime.
2022-05
252.225-7057 Preaward Disclosure of Employment of Individuals Who Work in the People's Republic of China.
2022-08
SO
LI
C
IT
AT
252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region- Representation.
2023-06
FAR Provisions Incorporated by Full Text
Number Title Effective Date
Alternate Deviation
Variation Effective Date
52.203-2 Certificate of Independent Price Determination.
1985-04
Certificate of Independent Price Determination (Apr 1985)
(a) The offeror certifies that-
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to-
(i) Those prices;
(ii) The intention to submit an offer; or
(iii) The methods or factors used to calculate the prices offered.
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
SO
LI
C
IT
AT
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory-
(1) Is the person in the offeror's organization responsible for determining the prices being offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to paragraphs (a)(1) through (a)(3) of this provision; or
(2)
(i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to paragraphs (a)(1) through (a)(3) of this provision ____[insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization];
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) of this provision have not participated, and will not participate, in any action contrary to paragraphs (a)
(1) through (a)(3) of this provision; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to paragraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) above, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of provision)
52.204-5 Women-Owned Business (Other Than Small Business).
2014-10
Women-Owned Business (Other Than Small Business) (Oct 2014)
(a) Definition."Women-owned business concern," as used in this provision, means a concern
SO
LI
C
IT