This is a Standard Form 30 (Amendment of Solicitation/Modification of Contract) issued by the U.S. Army Corps of Engineers (USACE) for solicitation W912P726BA001.

Amendment Details and Project Scope: Amendment 0001, effective April 20, 2026, modifies the San Joaquin/Stockton Deep Water Ship Channel (DWSC) FY26 Maintenance Dredging project located in Contra Costa, Sacramento, and San Joaquin Counties, California. The sole change reduces the Period of Performance from 196 calendar days to 166 calendar days after receipt of the notice to proceed. The work requires annual maintenance dredging of the San Joaquin/Port of Stockton River DWSC to -35 feet Mean Lower Low Water (MLLW) plus 1 foot of paid over-depth, with the sediment trap dredged to -38.5 feet MLLW plus 1 foot of paid over-depth. All dredge material is suitable for upland sites identified on plan sheets, with potential for beneficial reuse at contractor-furnished sites subject to permit requirements. The estimated cost range is between $5,000,000 and $10,000,000. Sealed bids are due May 11, 2026, at 11:30 AM local time, with the Government requiring 60 calendar days for acceptance. Performance bonds are required within 5 calendar days of award. The contracting officer is Lisa IP, USACE, San Francisco Division, (415) 503-6877.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of theoffer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

J 1 4

0001 20 APR 2026 0

W912P7

W075 ENDIST SAN FRAN

KO CONTRACTING DIVISION, 450 GOLDEN GATE AVENUE

SAN FRANCISCO, CA 94102-3406

UNITED STATES

LISA IP, EMAIL: LISA.I.IP@USACE.ARMY.MIL TELEPHONE: 415-503-6877

SCD: PAS:

W912P726BA001

10 APR 2026

SEE SECTION G - CONTRACT ADMINISTRATION DATA

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PROJECT TITLE: SAN JOAQUIN/ STOCKTON DWSC FY26 MAINTENANCE DREDGING

PROJECT LOCATION: CONTRA COSTA, SACRAMENTO, AND SAN JOAQUIN COUNTIES, CA

The purpose of this Amendment 0001 is to change the Period of Performance from 196 calendar days to 166 calendar days.

See continuation page for summary of amendment.

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

This amendment makes changes to the solicitation; these changes represent one of three types, either adding new information, deleting information, or revising existing information. Changes made by this amendment replace the previously issued sections of the advertisement, as referenced in the below summary of changes:

STANDARD FORM 1442

Box 11: Period of Performance changed from 196 calendar days after receiving notice to proceed to 166 calendar days after receiving notice to proceed.

SECTION 00 73 00 – SPECIAL CONTRACT REQUIREMENTS

Commencement, Prosecution, and Completion of Work – Construction (Apr 1984): POP changed from 196 calendar days to 166 calendar days.

(End of Summary of Changes)

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR

INFORMATION CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF PAGES

W912P726BA0010001 10 APR 2026

W075 ENDIST SAN FRAN

KO CONTRACTING DIVISION, 450 GOLDEN GATE AVENUE

SAN FRANCISCO, CA 94102-3406

UNITED STATES

LISA IP, EMAIL: LISA.I.IP@USACE.ARMY.MIL TELEPHONE: 415-503-6877

W912P7

LISA IP 415-503-6877

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

PROJECT TITLE: SAN JOAQUIN/ PORT OF STOCKTON FY26 MAINTENANCE DREDGING

PROJECT LOCATION: CONTRA COSTA, SACRAMENTO, SAN JOAQUIN COUNTIES, CA

WORK INCLUDES ANNUAL MAINTENANCE DREDGING OF THE SAN JOAQUIN/PORT OF STOCKTON RIVER DWSC TO -35-FT (MLLW) PLUS 1- FT OF PAID OVER-DEPTH, EXCEPT THE SEDIMENT TRAP, WHICH SHALL BE DREDGED TO -38.5-FT (MLLW) PLUS 1- FT OF PAID OVER-DEPTH. ALL DREDGE MATERIAL IS SUITABLE FOR THE

UPLAND SITES SHOWN ON PLAN SHEETS. DREDGE MATERIAL MAY BE SUITABLE OR BENEFICIAL REUSES AT CONTRACTOR FURNISHED SITES IN ACCORDANCE

WITH THE PERMIT REQUIREMENTS OF THE SPECIFIC REUSE SITES AND PER THE REQUIREMENT IN SPECIFICATION SECTION 01.11.00.

ESTIMATED COST RANGE IS BETWEEN $5,000,000 AND $10,000,000.

1 166

11:30 AM

11 MAY 2026

SECTION 00 73 00

Commencement, Prosecution, and Completion of Work - Construction (Apr 1984) The Contractor shall be required to (a) commence work under this contract within 1 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 196 166 calendar days.* The time stated for completion shall include final cleanup of the premises.

(End of condition)