This document contains answers to requests for information (RFIs) from contractors regarding the federal contract opportunity for maintenance dredging of Redwood City Harbor in 2023. The U.S. Army Corps of Engineers Engineering District San Francisco is seeking dredging of the federal channel, which cannot begin before June 1st and must be completed by December 31st, including placement of dredged materials at the Eden Landing Nearshore Site. Placement at other approved disposal sites may continue for the full 200 calendar day performance period. The Corps will provide required consultations and certifications for work beyond November 30th. Contractors requested and were provided relevant permits and environmental assessments for the Eden Landing Site as well as recent bathymetric data and EPA conditions for ocean disposal.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Answer RFI 1 Spec section 01 57 19.99 43 1.2 States “Any material dredged after November 30 in any year shall be placed either at and upland beneficiary reuse site benefiting aquatic species, as directed by the Government”. The timing of this contract will require the majority of the dredging to be performed after November 30th. Does USACE intend to enforce this requirement on this contract? Thank you, See amendment 1
RFI 2 The Pricing Schedule does not require the use of any beneficial resuse, however, Section 01 57
19.99 43 indicates that “Any material dredged after November 30 in any year (if approved by the Government)shall be placed either at an upland beneficial reuse site benefitting aquatic species, as directed by the Government.” Please clarify the requirement to place material either “at an upland beneficial reuse site benefitting aquatic species, as directed by the Government.”
See amendment 1
RFI 3 It is requested that we be provided with the xyz files for the Redwood City dredging site and the Eden Landing disposal site.
XYZ files provided
RFI 4 The “Important Notes” indicated within Section 00 10 00, Pricing Schedule state “6. Dredged material placement shall be consistent with the requirements in specification Section 01 11 00 SUMMARY OF WORK, including the DMMO Suitability Determination Memo (Attachment at the end of the specification package).” Please provide the DMMO Suitability Determination Memo for reference.
Suitability memo provided
RFI 5 Section 00 21 00,1.9 PERFORMANCE AND PAYMENT BONDS indicates the following: The offeror will, furnish performance and payment bonds within the time established in the contract in accordance with FAR 52.228-15 (DEVIATION 2020-O0016) located in Section 00 72 00. The offeror will provide the bonds to the Government electronically via the DoD SAFE. The offeror will also mail original, hard copies of bid bonds and performance bonds to the U.S. Army Corps of Engineers, San Francisco District, Contracting Division, 450 Golden Gate Avenue, Fourth Floor, San Francisco, CA 94102. It is requested that a hard copy of the bid bond not be required.
hard copy bid bond is not required
Redwood City RFI's from Contractors
RFI 6 SF 1442, Box 11 states, that the contractor is to complete work within 200 calendar days from notice to proceed. Section 52.211-10 additional states the contractor has 200 calendar days from notice to proceed to complete all work. However, Specification Section 01 11 00 para states, "...maintenance dredging of the federal channel in Redwood City Harbor, which cannot begin before 1 June in any year. Specification Section 35 20 24 para 3.5.1 states, "Placement at Eden Landing Nearshore Site shall be within the confines of the site no later than December 31."
Based on the above it would indicate that this project must be completed before the end of this calendar year. This seems extremely aggressive. Can you please clarify the Government's intentions on when the dredging will be complete?
Eden Landing placement shall be completed no later than December 31. All other dredge material placement/disposal may be placed after December 31
We would like to request a copy of the following documents for review:
(1) San Francisco Regional Water Quality Control Board (SFRWQCB) - Programmatic Water Quality Certification 2020-2024
(2) Bay Conservation Development Commission (BCDC) - Consistency Determination Consistency Notification Letter of Agreement 2020-2024
(3) National Marine Fisheries Service (MNFS) Long Term Management Strategy Biological Opinion (2015) Permits for the Eden Landing Nearshore Site:
(1) National Historic Preservation Act Section 106 Concurrence
(2) Endangered Species Act Not likely to Adversely Affect Concurrence and Magnuson-Stevens Essential Fish Habitat Conservation Recommendations
(3) Fish and Wildlife Coordination Act Planning Aid Letter
(4) Clean Water Act Section 401 Water Quality Certification
(5) Coastal Zone Management Act Letter of Agreement
(6) National Environmental Policy Act Environmental Assessment and Finding of No Significant Impact
RFI 8 A copy of the EPA Conditions for Disposal of Maintenance Dredged Material from the Redwood City Harbor Federal Channel, 2023 Episode, at the San Francisco Deep Ocean Disposal Site (SF- DODS) is requested to be provided.
This is provided
RFI 7 The documents are provided
RFI 9
Please clarify if a third party scow certifications are required or if the Corps will be providing scow certifications for scows going to SF-DODS.
Scow Certification is required for ocean disposal operations. The Contractor shall complete the Scow Certification Checklist and have it certified by the Government.
RFI 10 The “Maintenance Dredging Work Windows by Area and Species” used by the San Francisco LTMS group indicates that the herring work window is March 16 – November 30, and that a consultation is required for any work November – December and January – March. Please confirm that the Corps will be responsible for providing any consultations necessary for any work beyond November 30 at no cost to the Contractor.
Confirmed. The Corps will be responsible for providing any consultations necessary for any work beyond November 30
RFI 11 Please confirm that disposal at a contractor supplied beneficial use site is not part of this contract. Confirmed
RFI 12 Please confirm that the disposal of dredge sediment can occur for the full duration of the contract – 200 calendar days, at all of the designed disposal sites, Eden Landing, SF-11 and SF-
DODS.
See RFI 6 for Eden Landing placement. 200 calendar days for all other disposal sites is confirmed
RFI 13 Could you please provide the most recent bathymetric data from the April 2023 survey. Yes, see amendment 1