Shoreline Virtual Site Visit briefing with Attendance List 4 Feb 2021.pdf
PDF 3 MB Posted
- Attached to
- South San Francisco Bay Shoreline Reaches 1-3
- Solicitation number
- W912P721R0002
About this file
This briefing document outlines the requirements for the South San Francisco Bay Shoreline Levee construction project. The U.S. Army Corps of Engineers will construct levees across three reaches of shoreline. Reach 1 will include an educational overlook and water control structures. Reach 2/3 will include a new water control structure and boardwalk. Construction must comply with environmental regulations to protect endangered species habitat. The contractor will be responsible for hauling imported fill and excavated soils, with restrictions on truck cycles and working hours. The solicitation will use Lowest Price Technically Acceptable source selection and has a March 23rd proposal deadline and May 10th award date. Offerors should attend the February 4th virtual site visit and submit any requests for information by February 22nd.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Name Company Name
Jae Shin Ground Control Inc , Jack Shewmaker DeSilva Gates Construction
Gavin Archbald H. T. Harvey & Associates
Robin Carle H. T. Harvey & Associates
Dan Schultz, VP Nordic Industries, Inc.
Jared Williams Forgen
Chris Barr USFWS
Gavin Tasker Barnard Construction
Monte Molina Four M Contracting
Maximilliano Busnardo H. T. Harvey & Associates
Brett Bennett Anvil Builders
Jeff Rankin Odin Construction
Edgar Alvarez Curtin Maritime
James Ujah Valley Water
David Ray Walsh Construction
Katie Mackenzie Odin construction
Sean Sahlberg Odin Construction
Miguel Galarza Yerba Buena Engineering
Steve Rottenborn H. T. Harvey & Associates
Sunshine Julian Valley Water
Jack E. Shewmaker Desilva Gates Construction
Rob Snyder Granite Rock Company
Shoreline Reaches 1-3 W912P721R0002 Virtual Site Visit Attendance List
1SOUTH SAN FRANCISCO BAY SHORELINE
LEVEE CONSTRUCTION REACHES 1-3
Virtual Site Visit Solicitation # W912P721R0002
Date: 4 February 2021 Time: 1:00 PM WebEx: https://usace1.webex.com/meet/mary.fronck Conference # 844-800-2712 Access Code 1991291961
ADMINISTRATIVE ANNOUNCEMENTS
• No recording
• Posting of briefing
• Purpose
• Information in this presentation and potential USACE-led physical site visit is for informational purposes only and is not/will not be contractually binding
• All inquiries shall go through the points of contact listed in the announcement.
• Sign-in Sheet – write your name and affiliation in the chat box.
• Please submit any questions in the chat box, which we will try to address at the end of the presentation.
AGENDA
• Introductions
• Project Description
• Environmental Requirements
• Procurement Process
• Acquisition Target Milestones
• Physical Site Visit
4PROJECT DESCRIPTION: BACKGROUND 4
OVERVIEW
• Reach 1 levee designed by HDR.
• Reach 2/3 levee designed by USACE.
• A portion of the levee fill is government provided, with remainder to be imported by contractor.
• Excavated soil from Reaches 1-3 to be placed in area near Reach 1.
• Project access is through Alviso Marina County Park and the USFWS Don Edwards Wildlife Refuge Visitor Center.
• Access between Reach 1 and Reach 2/3 addressed via agreement with UPRR.
REACH 1 DESCRIPTION
• Levee
• Educational Overlook
• Gold Street Pump Station Outfall
• Tidal Marsh Intake Structure (A12/A13)
REACH 1 TYPICAL SECTION
Key Items:
• Soft Ground Foundation
• Levee Test Section Construction Submittal
• Staged Construction, Instrumentation
• Div 01 specs unique to Reach 1: Geogrid (31 05
21.01), Levee construction (35 14 00.01), Utilities (33 40 00.01)
8PROJECT DESCRIPTION: REACH 2/3 KEY FEATURES 8
• Levee
• New Chicago Marsh Water Control Structure
• Boardwalk
REACH 2/3 TYPICAL SECTION
Key Items:
• Single stage construction
• Excavation of foundation through Bay Mud
• Levee fill spec less strict below Elevation 0
• Div 01 specs unique to Reach 2/3: Geogrid (31 05 21.02), Levee construction (35 14 00.02), Utilities (33 40 00.02)
STAGING AREAS #1 AND #2 10
staging area #1 staging area #2
STAGING AREA #3 11
staging area #3
HAULING RESTRICTIONS
• Regular working hours shall consist of an 8.5 hour period between 7:00 am and 5:30 pm.
• Soil hauling limited to 224 truck cycles per day.
• Before 9 am, contractor shall limit truck cycles to
11 or fewer. After 3 pm, contractor shall limit truck cycles to 11 or fewer.
COUNTY PARK ENTRANCE
Delays to visitors shall be less than 2 minutes. Historical traffic counts provided in specifications.
No staging equipment in park parking lot.
No work shall be performed for 7 consecutive calendar days surrounding the "Day on The Bay Festival" held in October of each year.
S: 01 14 00
USFWS VISITOR CENTER ENTRANCE
Typical traffic consists of 15- 20 vehicles per hour, with a maximum potential of 50 vehicles per hour. Vehicle loads approaching the maximum would correlate with special events, and notice would be provided to the contractor 48 hours in advance. Two (2) special events per week each lasting 3 hours are anticipated.
S: 01 14 00 S: 01 50 00
ENVIRONMENTAL REQUIREMENTS
•Endangered Species •Resource Agency Submittals •Fill Quality Approval •Pond Water Levels •Dewatering Discharge Monitoring
ESA LISTED SPECIES
Imagery sources: USFWS, USEPA, NOAA Fisheries S: 01 57 19 P: 3.1
Species Restrictions
WhereJan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
CA Ridgeway Rail Potential nesting area unless surveyed (700 feet)
Western Snowy Plover Active nest/brood buffer
(300 feet)
CA Least Tern Active nest buffer (300 feet)
Steelhead Tidal waters
Salt Marsh Harvest Mouse Pickleweed
ESA LISTED SPECIES CONTINUED
A USFWS-approved biological monitor will be present during all work activities in or immediately adjacent to habitat that could be occupied by federally listed species to look for individuals that may be impacted by construction. The biologist will have stop-work authority if any individual of a federally listed species is detected in an area where it may be injured or killed by construction activities.
S: 01 57 19 P: 3.1
RESOURCE AGENCY SUBMITTALS
• Some submittals require resource agency approval with varying review timelines:
– Dewatering Plan (SFBRWQCB, BCDC) – 30 days
– Spill Prevention and Containment Plan (SFBRWQCB, BCDC) – 90 days
– Biological Monitor Qualifications (USFWS)
– Map of High-Quality Habitat for Listed Species (USFWS)
– Quality Assurance Project Plan Addendum
(SFBRWQCB) – 90 days S: 01 57 19, P: 3.3 S: 01 57 19, P: 3.14 S: 01 57 19, P: 1.6.5 S: 01 57 19, P: 1.6.1 S: 01 57 19, P: 1.6.8
FILL QUALITY APPROVAL
Follow QAPP guidelines
Some changes to fill quality evaluation process
QAPP addendum and personnel need to be approved by
RWQCB
S: 01 57 19 P: 1.6.8 Attachment 8 and 8a
POND WATER LEVELS
Reach 1
• Pond A12: ~1 ft NAVD88
• Pond A13: ~3-5 ft NAVD88
Reach 2/3
• Pond A16: ~5 ft NAVD88
• New Chicago Marsh: ~1 ft NAVD88
- Discharging into New Chicago Marsh is prohibited
R1 – Plan Sheet G-004 R2/3 – Plan Sheet G-03
DEWATERING DISCHARGE MONITORING
Monitor receiving water and discharge at least one time every 8 hours, monitor for:
pH, range of 6.5 to 8.5, cannot cause change greater than 0.5 unit Dissolved Oxygen, must be greater than 0.5 mg/L Dissolved Sulfide, must be less than 0.1 mg/L Turbidity
If natural turbidity is greater than 50 NTU, discharge can be no more than 10% above
If natural turbidity is less than 50 NTU, cannot cause increase of greater than 5
NTU
Temperature, cannot increase by more than 5°F Nutrients, cannot contain enough biostimulatory substances to cause nuisance growths or adversely affect beneficial uses S: 01 57 19 P: 3.3.1.1
22PROCUREMENT PROCESS
• Solicitation – Lowest Price Technically Acceptable (LPTA)
Source Selection in accordance with FAR 15
• Full and Open Competition
• Technical and Past Performance will be evaluated as outlined in Section 00 22 00 and 00 22 16 of the solicitation
Point of Contacts (POC):
Primary Erica Miller, Contract Specialist Erica.B.Miller@usace.army.mil
Secondary Mary Fronck, Contracting Officer Mary.Fronck@usace.army.mil
*All inquiries shall go to the POC
23ACQUISITION TARGET
MILESTONES
• Advertisement: January 22, 2021
• RFI Deadline: February 21, 2021
• Proposals Due: March 23, 2021
• Contract Award: May 10, 2021
PHYSICAL SITE VISIT
All of the areas that would be available on a USACE-led site visit are open to the public.
If a USACE-led site visit is desired, please contact Neil Hedgecock at neil.c.hedgecock@usace.army.mil or 415- 503-6728.
mailto:neil.c.hedgecock@usace.army.mil
| South san Francisco Bay Shoreline �Levee construction Reaches 1-3� |
| Administrative announcements |
| Agenda |
| Project description: Background� |
| Overview |
| Reach 1 Description |
| Reach 1 Typical Section |
| Project Description: REACH 2/3 Key Features |
| Reach 2/3 Typical Section |
| Staging AReaS #1 and #2 |
| Staging Area #3 |
| Hauling Restrictions |
| County Park Entrance |
| uSFWS Visitor Center Entrance |
| Environmental Requirements |
| Esa listed species |
| ESA Listed Species Continued |
| Resource agency submittals |
| Fill Quality Approval |
| Pond Water levels |
| Dewatering discharge monitoring |
| Slide Number 22 |
| Slide Number 23 |
| Physical Site Visit |
| Shoreline Virtual Site Visit Attendance Sheet.pdf |
| Sheet1 |
File details come from the government source that posted it. Updated .