This document provides details for a federal solicitation seeking construction services for a shoreline project. The U.S. Army Corps of Engineers, San Francisco District is soliciting proposals for work on South San Francisco Bay Shoreline Reaches 1-3. A virtual site visit will be held on February 4th, with a request for information deadline of February 22nd and advertisement close date of March 23rd. Contractors will be required to execute agreements for a temporary private road crossing with the Santa Clara Valley Water District and Union Pacific Railroad. Insurance requirements are specified in FAR 52.228-5 and further detailed in Section 007300. Funding for the project has been acquired based on the government's estimate despite recent cost increases for infrastructure and energy.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31. Second paragraph of section 01 50 01 part 1, 1.1 states “After completion of the work, remove the entire structure from the site and shall restore the site to original conditions.” Further into the same part 1, 1.3 (h.) states “The PFO modular office building, landings, stairs, ramps and all Contractor-purchased furniture, fixtures, and equipment (FFE) shall be become Government property at the completion of this contract and will remain on-site to be used by the Government into the future for other work.” Please confirm the government’s intent to either have the PFO and all associated support equipment/material/services removed from the site at project completion or remain onsite at project completion and become the property of the government.
Governments response- Confirm that The PFO and all associated support equipment/material/services shall be removed from the site at the completion of the project. (See the updated paragraph 1.1.4 (h) of the 01 50 01 spec).
32. The COE has yet to provide in detail the limits and types of insurance in this RFP per, 52.228- 5 Insurance - Work On A Government Installation JAN 1997. Please expand on the aforesaid regulation with the types and specified limits of insurance.
Governments response- See additional information in Section 007300
33. In regard to the Temporary Private Road Crossing Agreement between Santa Clara Valley
Water District and UPRR, will Contractor be required to execute the Exhibit E Private Road Crossing Agreement, Contractor’s Right of Entry Agreement?
Governments response- Confirmed.
34. The reference to “Special Contract Clauses”, specifically one which references the NOAA data regarding budgeted weather days however no NOAA data has been provided. Please provide.
Governments response- See additional information in Section 007300
35. In light of recent infrastructure and energy cost escalations, has necessary funding been acquired?
Governments response- The Shoreline project is currently funded based on the Government’s estimate.