About this file

Amendment 0002 - SF30 As-Builts

View the file

Other files for this federal contract opportunity

Other files attached to Pier 36; demolition and removal, newest first.
File Type Posted
Bid Results W912P7-11-B-0005 - Pier Demo.pdf PDF
QA Responses Pier 36 3 Nov 2011 1115.pdf PDF
Amendment 0008 SF30.pdf PDF
Summary of Docs required in the IFB —
QA Responses Pier 36 27 OCT 2011 1515.pdf PDF
Amendment 0007 SF30.pdf PDF
QA Responses Pier 36 25 OCT 2011 1330.pdf PDF
Amendment 0006.pdf PDF
SF30 Amendment 0005 plus attachments.pdf PDF
QA Responses Pier 36 21 OCT 2011 0100.pdf PDF
Attendees list.pdf PDF
Pier 36 Demolition Final Drawings - Revision 1 - 11 OCT 2011.pdf PDF
8469-30-4 Piers 30thru38 Seawall Repairs 1973 —
Pier 36 Demolition Final Drawings 2011-09-16.pdf PDF
SF30 Amendment 0004.pdf PDF
Q A Responses Pier 36 10-11-11.pdf PDF
Amendment 0003.pdf PDF
Pier 36 - Final Biological Opinion —
SF30 Amendment 0001.pdf PDF
P36 - Seawall As-Builts —
Pier 36 - HAZMAT Survey Report —
Pier 36 - Environmental Assessment and FONSI —
Pier 36 - Water Quality Control Board Certification —
Clause SPN 14-4001 Inquiries —
Pier 36 - Extension of Shed 2.pdf PDF
Pier 36 - BCDC Consistency Determination —
Q A Responses Pier 36 10-6-11.pdf PDF
Pier 36 - Pier 36 As Builts —
Pier 36 - Extension of Shed 1.PDF PDF
Pier 36 - Biological Assessment —
Q A Responses Pier 36 9-30-11.pdf PDF
Final Plans 2011-09-16.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

W912P7-11-B-0005, Pier 36 Demolition Project (All amendments must be acknowledged at time of bid opening)

Summary of changes:

- As-Built documents for the project (4 attachments).

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

MODIFICATION OF CONTRACTS/ORDER

NO.

E. IMPORTANT: Contractor

15B. CONTRACTOR/OFFEROR

is not, copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer tended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

is extended, B.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CON-

TRACT ORDER NO. IN ITEM 10A.

2. AMENDMENT/MODIFICATION NO.

6. ISSUED BY

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) is required to sign this document and return

15A. NAME AND TITLE OF SIGNER (Type or print)

PAGE OF PAGES 1. CONTRACT ID CODE

5. PROJECT NO. (If applicable) 4. REQUISITION/PURCHASE REQ. NO. 3. EFFECTIVE DATE

7. ADMINISTERED BY (If other than Item 6)

15C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA

BY

16C. DATE SIGNED

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10B. DATED (SEE ITEM 13)

CODE CODE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

is not ex-copies to the issuing office.

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

(Signature of person authorized to sign) (Signature of Contracting Officer)

USAPPC V2.00

10A.

30-105-02

See item 6US ARMY ENGINEER DISTRICT, SAN FRANCISCO

CONTRACTING DIVISION

1455 MARKET ST., 17TH FLOOR SUITE 1741

SAN FRANCISCO CA 94103-1398

CODE

FACILITY CODE

0002 6 Oct 2011

W912P7-11-B-0005

15 Sep 2011