Bid Results W912P7-11-B-0005 - Pier Demo.pdf

PDF 20 KB Posted

Attached to
Pier 36; demolition and removal
Solicitation number
W912P7-11-B-0005
Issued by

View the file

Other files

File Type Posted
QA Responses Pier 36 3 Nov 2011 1115.pdf PDF
Amendment 0008 SF30.pdf PDF
Summary of Docs required in the IFB —
Amendment 0007 SF30.pdf PDF
QA Responses Pier 36 27 OCT 2011 1515.pdf PDF
QA Responses Pier 36 25 OCT 2011 1330.pdf PDF
Amendment 0006.pdf PDF
SF30 Amendment 0005 plus attachments.pdf PDF
QA Responses Pier 36 21 OCT 2011 0100.pdf PDF
Attendees list.pdf PDF
Pier 36 Demolition Final Drawings 2011-09-16.pdf PDF
Pier 36 Demolition Final Drawings - Revision 1 - 11 OCT 2011.pdf PDF
8469-30-4 Piers 30thru38 Seawall Repairs 1973 —
SF30 Amendment 0004.pdf PDF
Q A Responses Pier 36 10-11-11.pdf PDF
Amendment 0003.pdf PDF
Pier 36 - Final Biological Opinion —
Pier 36 - Water Quality Control Board Certification —
Clause SPN 14-4001 Inquiries —
Pier 36 - Extension of Shed 2.pdf PDF
Pier 36 - HAZMAT Survey Report —
SF30 As-Builts.pdf PDF
SF30 Amendment 0001.pdf PDF
Pier 36 - Environmental Assessment and FONSI —
P36 - Seawall As-Builts —
Pier 36 - BCDC Consistency Determination —
Pier 36 - Extension of Shed 1.PDF PDF
Pier 36 - Biological Assessment —
Pier 36 - Pier 36 As Builts —
Q A Responses Pier 36 10-6-11.pdf PDF
Q A Responses Pier 36 9-30-11.pdf PDF
Final Plans 2011-09-16.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Item Number

Description Cayo Dallas, TX

Manson Seattle, WA

Silverado Oakland, CA

West Bay Navato, CA

DD-M

San Rafael, CA

Power Alameda, CA IGE

0001 Mobilization and Demobilization

$227,930.00 $600,000.00 $186,000.00 $218,000.00 $465,000.00 $566,845.00 $110,805.00

0002 Safety and Traffic Control $156,000.00 $210,000.00 $132,000.00 $19,000.00 $130,000.00 $92,361.00 $79,012.00

0003 Environmental Protection/Monitoring

$50,000.00 $85,000.00 $18,600.00 $15,000.00 $43,000.00 $44,017.00 $18,688.00

Demolition/Deconstructio n of (E) Pier XX Structural Building

(36,075 Sq. Ft)

$577,200.00 $144,300.00 $1,118,325.00 $360,750.00 $447,330.00 $409,812.00 $175,756.00

Demolition/Deconstructio n of (E) Pier XX Decking,

(E) Steel Ferry Ramp (86,095 Sq. Ft)

$1,894,090.00 $1,721,900.00 $1,247,330.00 $1,119,235.00 $1,463,615.00 $1,569,511.85 $2,557,990.00

Complete Removal/Demo of Caissons and Piles to 3

Feet Below Mud Line (437 Each)

$1,966,500.00 $1,048,800.00 $1,727,024.00 $1,704,300.00 $1,988,350.00 $1,446,907.00 $1,760,398.00

Remove and Salvage (E)

Fire Hydrants (2 Each)

$5,000.00 $10,000.00 $11,600.00 $3,400.00 $3,800.00 $3,361.94 $1,346.00

Pier 36 Building Hazmat

Abatement (36,075 Sq. Ft)

$288,600.00 $194,805.00 $150,072.00 $180,375.00 $144,300.00 $143,217.75 $347,801.00

Complete Removal/Demo of (E) Timbers Standing and Submerged to 3 Feet Below Mud Line

(1420 Tons)

$631,900.00 $568,000.00 $587,880.00 $549,540.00 $511,200.00 $378,004.06 $250,530.00

Seawall:

Phase 1 - Exploratory

Work Phase 2 - Concrete Crack

Repair

$575,000.00 $468,000.00 $1,038,800.00 $575,000.00 $500,000.00 $532,548.00 $655,183.00

Demo of Marginal Wharf Installation of Inclinometers

Demolition of (E) Utilities Structural Patch Repairs over Orifices

$495,000.00 $575,000.00 $235,500.00 $449,000.00 $370,000.00 $402,664.00 $599,131.00

Demo of (E) 16" Dia. Piles at Marginal Wharf to 3 Feet Below Mud Line

(74 Each)

$34,780.00 $111,000.00 $120,620.00 $29,600.00 $30,340.00 $28,350.14 $95,967.00

Complete Removal/Demo of Caissons Supporting the Marginal Wharf at former Pier 34 Footprint to 3 Feet Below Mud Line

(10 Each)

$45,000.00 $28,000.00 $34,650.00 $30,000.00 $36,000.00 $28,350.00 $49,038.00

$6,947,000.00 $5,764,805.00 $6,608,401.00 $5,253,200.00 $6,132,935.00 $5,645,949.74 $6,701,645.00

YES YES YES YES YES YES

YES YES YES YES YES YES

SB LB LB LB SB LB

Total Bid

W912P7-11-B-0005 - Pier 36 Demolition Project Bid Sheet: Opening Date Nov 8 2011 and 1PM

All Amendments acknowledged:

Yes or No

Responsive Bid Bond:

Yes or No

Business size:

(Ex.: LB, SB, WOSB, 8a)

Sheet1