This document is an amendment to a federal solicitation for the Chicago Harbor Lock Power Distribution Upgrade project. The amendment adds Clarification Item 0008 for southeast and southwest bubbler conduit and wiring. It modifies the summation of bid price table to include this new line item and renumbers performance and payment bond from item 0008 to 0009. The amendment also provides responses to two questions from an interested party confirming item 0008 covers the specified scope of work and stating sealed PVC-RMC conduit must be used per the contract drawings. The North American Industry Classification code is 237130 and the competition is restricted to small businesses with a size standard of $39.5 million. The Department of the Army Corps of Engineers Engineering District Chicago is the issuing agency for this opportunity.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6611307068

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation W912P621B0015 for Chicago Harbor Lock Pow er Distribution Upgrade is hereby amended as follow s:

See page 2 SF30 Continuation Sheet.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P621B0015

X 9B. DATED (SEE ITEM 11)

05-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Sep-2021

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P621B0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SUMMARY OF CHANGES AMDT 0005

Continuation from SF30 Block 14

A. Added CLIN 0008 and moved Performance and Payment Bond to CLIN 0009.

B. Updated Section 00 10 00 Summation of Bid Price.

C. Add two questions from interested party and USACE response to the questions

Question We are asking what Item Number in the contract is the SE and SW bubbler conduit and wiring to be included. The answer provided on question 3 did not state where this work is part of. Please advise.

USACE Response: The Contractor shall see Specification 01 22 00.00 10 Price and Payment

Procedures. The Specifications have been changed to add CLIN 0008 for SE and SW Bubbler

Conduit and Wiring.

Question Is Sealtite allowed to be used if installed per NEC code?

USACE Response: Per the Power Distribution Project the contractor shall install PVC-RMC.

See Drawing Sheet ES-002 for conduit and wire schedule.

D. All other terms and conditions remain unchanged.

SECTION 00 10 00 - SOLICITATION

CLIN 0008

This CLIN has been renumbered to CLIN 0009.

CLIN 0008 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0008 1 Job OPTION SE and SW Bubbler Conduit & Cond Rep Opt

FFP

Southeast and Southwest Bubbler Conduit and Conductor Replacement (Option)

FOB: Destination

NET AMT

The following have been modified:

SUMMATION OF BID PRICE:

Base Bid Items Line Item 0001 $__________________________

Line Item 0002 $__________________________

Line Item 0003 $__________________________

Line Item 0004 $__________________________

Line Item 0005 $__________________________

Total for Line Items 0001, 0002, 0003, 0004 and 0005: $__________________________

Option Bid Items

Option Line Item 0006 $__________________________

Option Line Item 0007 $__________________________

Option Line Item 0008 $__________________________

Option Line Item 0009 $__________________________

OPTION LINE ITEMS 0006, 0007, 0008

and 0009: $__________________________

OVERALL BID PRICE

(ALL ABOVE MENTIONED LINE ITEMS,

TO INCLUDE THE OPTIONS): $________________________________________

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following Acceptance/Inspection Schedule was added for CLIN 0008:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

(End of Summary of Changes)