Questions that have been responded to are as follows and will be incorporated into a forthcoming Amendment.

Question Submitted on September 4, 2009 by Crowther Roofing

Question: “Upon review of the specification section 07 51 13, Built-up Asphalt Roofing, we found under section 2.2 Fiberglass Felt Materials, a. Venting Base Sheet. The wrong material is specified. The ASTM D 4897, Type II is designed for high moisture content substrate, and not over the type used on this project. It is also designed to be mechanically fastened or spot mopped to the substrate, and not mopped solid. The proper Fiberglass Base Sheet is the ASTM 4601, Type II product. I have attached product data sheets on these two products.

You can also apply four piles of the Ply Felt in lieu of the base sheet, which the manufacture’s would rather see.”

USACE Response to Question: The Venting Base Sheet should be ASTM D 4897, Type II as specified. USACE has specified the correct product for the application.

Questions Submitted on September 1, 2009 by Walsh Construction

Question #1: “Please list the equipment items that will be supplied and installed by others and not in this scope.”

USACE Response to Question #1: All work done “by others” is shown on the plans. Please see the drawings set.

Question #2. “Please confirm this project requires an overall 1-year project warranty signed by the general contractor.”

USACE Response to Question #2: The Contractor shall reference Solicitation Section 00700 FAR Clause 52.246-21 "Warranty of Construction (MAR 1994)", which is in reference. The full text Clause can be read by going to www.arnet.gov.

Question #3. “Please confirm that temporary utilities will be provided to the General Contractor at no cost.”

USACE Response to Question #3: Contractor shall build costs in its Bid Price.

Question #5. “Underground plumbing piping not detailed on M-06 plan view, please issue revised drawing.”

USACE Response to Question #5: Please refer to architectural drawings.

Question #6. “A-02 shows what appears to be an underground drain line running behind all of the garage doors going into trench drains. Neither the drain line or trench drain are shown on the mechanical drawings. Please confirm that there should be a drain line at this location.”

USACE Response to Question #6: Contractor shall refer to Drawing Sheet A-04.

Question #7. “S-01 refers to the same line I believe in question #4 tying into an underground plastic floor drain collection unit. Is this new or existing? What exactly is this system? It is not shown on mechanical drawings.”

USACE Response to Question #7: Contractor shall refer to Drawing Sheet A-04.

Question #8. “Verify that the roof drainage and cooling tower drain line are to dump into the Canal.”

USACE Response to Question #8: This is a new drainage system. It carries any water or other liquid waste that flows into the floor drain trench in front of each exterior garage door to an underground plastic storage take that can be pumped out and the liquid disposed of properly. See Drawing Sheets A-04 and S-06 for details.

Question #9. ”Plumbing spec calls for floor drains, area drains and floor sinks, however none are shown on the drawings. Please provide locations, quantities, and details of these items.”

USACE Response to Question #9: Yes, roof and cooling tower drain discharge into the canal. Please see Drawing Sheet M-06.

Question #10. “Water meter and remote readout are specified but not shown on the drawings. Please verify if one is required. If so provide location for both the meter and remote readout.”

USACE Response to Question #10: Specification Section 22 00 00 will be revised by way of Amendment 0004 to delete paragraphs 2.4.1 Floor drain,

2.4.2 Area drains, 2.4.3 Floor sinks.

Question #11. “There is no listing for the horizontal storm piping insulation specification. Please verify it should be insulated and if so what thickness.”

USACE Response to Question #11: Contractor shall refer to Drawing Sheet M-11.

Question #12. “The specification for the mechanical calls for this job to be commissioned in accordance with LEED even though it is not a LEED project.

All the paperwork has to be maintained and it appears a commissioning agent needs to be hired. Please confirm that a commissioning agent has to be hired and clarify if the cost of this commissioning agent is to be carried in our bid.”

USACE Response to Question #12: Per Solicitation Section 23 08 00.00 10, Paragraph 1.3.2 formal LEED certification is not required; however, the Contractor is required to provide documentation that meets the LEED Energy & Atmosphere (EA) Prerequisite 1, Fundamental Commissioning.

Questions Submitted on August 24, 2009 by Responses to Schaefges Brothers Inc.

Question #1. “01 57 20.01 03 page 11 3.1 - Permits - Have permits been applied for? If no, will the time it takes to receive permits be added into the length of the contract?

What permits are required?

Will permit costs be waived?”

USACE Response to Question #1: See Specification Section 01 57 20.01 03, Part 3 Execution, Paragraph 3.1 Environmental Permits and Commitments, “…The Contractor shall be responsible for obtaining at its expense any and all building permits, well permits, or other permits needed for the project and not specifically stated in the specifications.” Also see FAR Clause 52.236-7 “Permits & Responsibilities”, Section 00700 of the Solicitation package.

Question #2.

a. “01 52 02 page 5 3.3 Temp Field office - Is there an existing electrical service at the site we can use for temp electric? If yes, where is it located? If no, due to the location of the site it may be very costly (or not possible) for a temp electric service to be installed. Can trailers be powered by temp generators during working hours only?”

USACE Response to Question #2a: No existing power is available for temporary field offices. Power for trailers must be requested through COM- ED. Generators are acceptable during work hours, as long as they conform to noise and air pollution constraints (Gasoline powered Generators are acceptable.)

Question #2b. “Is there an existing phone service to the site? If yes where is it located? If no, can we provide cellular voice & internet in lieu of land lines?”

USACE Response to Question #2b: Phone service for the contractor is not available. If ATT can't provide line, cellular phones are acceptable.

Question #4. Will ComEd bring the appropriate power to the transformer? Has the Gov consulted with ComEd regarding any service fees for the new service?

USACE Response to Question #4: Refer to Specification Section 26 20 00 Paragraph 1.7 Commercial Power Service.

Question #5. “Please confirm that the Site Safety & Health Officer (SSHO) and the Contractor Quality Control Manager (CQC) must be onsite everyday from start of phase 1 to the successful completion of phase 3. Also confirm that these individuals cannot perform any additional duties outside of those described in the specifications (safety/Q.C.). Will these individuals be required to be onsite during the punch list phase?”

USACE Response to Question #5: SSHO and Quality Control Systems Manager must be on site when work is being performed. That includes punch-list work. SSHO cannot be the QCSM, QCSM may not have any other duties than Quality Control.

Question #8. “While reviewing the specifications we have identified the following submittals as being required(approved) by the Gov prior to starting work onsite;

Accident prevention plan, Quality control plan, Construction site plan, Environmental protection plan and Storm water pollution prevention plan. How long will the Gov take to review these plans (due to tight schedule this is critical information)? How long will the Gov take to re-review corrected plans?”

USACE Response to Question #8: Refer to Specification Section 01 33 00 Paragraph 1.8 Scheduling.