Amendment 0003 W912P522B0009 JPP SEWER REHAB 06.29.2022.pdf

PDF 370 KB Posted

Attached to
JPP Seven Points Campground Sewer Rehab Project
Solicitation number
W912P522B0009
Issued by

About this file

This federal contract opportunity solicitation and related amendment provide details for the JPP Seven Points Campground Sewer Rehab Project. The project scope involves minor clearing and grubbing, trench excavation, installation of HDPE force main and sewer lines, construction of a wet well and pump vault, pump installation, potential pavement replacement, backfilling, seeding and mulching. The contract value is between $500,000 and $1,000,000. The solicitation is a 100% small business set-aside issued by the U.S. Army Corps of Engineers, Nashville District. The amendment extends the bid due date to July 7th, 2022 at 1:00pm Central Time, provides revised technical specifications and drawings from bidder questions, and updates the wage determination. Completion is required by March 31st, 2023.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W38XDD13471401

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project Title: JPP Seven Point Sew er Rehab This solicitation is being amended to:

1. Provides revised changes to TECHNICAL SPECIFICATIONS and CONTRACT DRAWINGS as a result of Bidder inquiry responses.

2. Revised and updated the Wage Determination from TN20220083 to TN20220142.

3. No additional questions w ill be accepted follow ing the issuance of this amendment.

4. FAR 52.252-3 has been updated.

Note: The deadline for receipt of quotes remains unchanged and is not extended by this Amendment.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 29-Jun-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P522B0009

X 9B. DATED (SEE ITEM 11)

24-May-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jun-2022

CODE

CELRN-RC-N CONTRACTING BRANCH

110 9TH AVE SOUTH, A405

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P522B0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0003 CHANGES

Solicitation No. W912P522B0009 Amendment No. 0003

I. CHANGES TO TECHNICAL SPECIFICATIONS

II. CHANGES TO CONTRACT DRAWINGS

A. The following CONTRACT DRAWINGS have been revised and replaced:

Drawing No. Description

Q5-SPS-C-101 PLAN & PROFILE 1

Q5-SPS-C-501 WET WELL SITE DETAIL 1

B. The following CONTRACT DRAWING has been added to the package:

Drawing No. Description N/A N/A

C. The following REFERENCE DRAWING / FOR INFORMATION ONLY DRAWING has been added to the package:

Drawing No. Description N/A N/A

--- END OF AMENDMENT NO. 0003 TECHNICAL CHANGES---

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001 for Solicitation W912P522B0009 is to extend the ability to enter technical inquiries and

W912P522B0009 questions relating to proposal procedures or bonds will be disabled on 13 June 2022 prior to the closing date stated in the solicitation. The Government responses will be entered into the ProjNet system after 17 June 2022 prior to the closing date stated in the solicitation.

Amendment 0002

1. Provide Government's response to the Contractor's questions from ProjNet.

2. Provide revised changes to TECHNICAL SPECIFICATIONS and CONTRACT DRAWINGS as a result of Bidder inquiry responses.

3. Extend the Bid due date from Friday, 24 June 2022 to Thursday, 07 July 2022 at 1:00 pm Central Time.

Amendment 0003

This solicitation is being amended to:

1. Provide revised changes to TECHNICAL SPECIFICATIONS and CONTRACT DRAWINGS as a result of Bidder inquiry responses. No additional questions will be accepted following the issuance of this amendment.

2. Provide an updated Wage Determination.

3. FAR 52.252-3 has been updated.

Note: The deadline for receipt of bids remains unchanged and is not extended by this Amendment.

SECTION 01 00 00 - GENERAL REQUIREMENTS

The following have been modified:

WAGE DETERMINATIONS

The WAGE DETERMINATION (Davis Bacon Act WD TN20220142.pdf) is attached as a separate document but is intended to be part of this solicitation /contract. This document has five (5) page.

(End of Summary of Changes)