Bid Schedule Seven Points 2022-04-01.pdf

PDF 90 KB Posted

Attached to
JPP Seven Points Campground Sewer Rehab Project Federal contract opportunity
Solicitation number
W912P522B0009
Issued by
Department of the Army Corps of Engineers Engineering District Nashville

About this file

This document contains an invitation for bid for construction services and a bid schedule for the JPP Seven Points Campground Sewer Rehab Project. The Nashville District of the U.S. Army Corps of Engineers is seeking a firm fixed-price contract for construction of a sanitary sewer network at the Seven Points Day Use Area, including clearing, trench excavation, placement of HDPE force main and sewerline components, connection to existing networks, abandonment of septic tanks, construction of a wet well tank and pump vault, pump installation, backfilling, seeding and environmental protection. The contractor must coordinate with local utility providers and be completed by March 31, 2023, providing portable toilets if delays extend past that date. The estimated value of construction is between $500,000 and $1,000,000. The project is set aside solely for small businesses per NAICS code 237110 with a size standard of $39.5M.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Seven Points Day Use Area Sewer Rehab J. Percy Priest Lake

Hermitage, Nashville, Tennessee

BID SCHEDULE

JPP Seven Points Date: 2022-04-01

ITEM

NO. DESCRIPTION QTY. UNIT PRICE AMOUNT

0001 Mobilization and Demobilization 1 JOB $ - $ - 0002 Clearing and Grubbing 1 JOB $ - $ - 0003 Sewer Line (HDPE) 3,050 LF $ - $ - 0004 Duplex Pumps and Pump Controls 1 JOB $ - $ - 0005 Electrical Equipment 1 JOB $ - $ - 0006 Wet well tank 1 JOB $ - $ - 0007 Rock Excavation 13 CY $ - $ - 0008 Seeding 1 JOB $ - $ - 0009 Performance and Payment Bonds 1 JOB $ - $ - 0010 Decommision of existing septic tank 1 JOB $ - $ -

BASE TASK ORDER TOTAL AMOUNT (CLIN's 0001 through 0010): $ -

BASE TASK ORDER

Page 1 of 1 PRICE SCHEDULE

Price Schedule

File details come from the government source that posted it. Updated .