Amendment 0004 The purpose of this amendment is to 1. Revise Plans 2. Revise Technical Specifications 3. Post Set Three Q A 4. Update DFARS clause 252.236-7001 and 5. Update FAR clause 52.252-3.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTING DIVISION (JD9)
JAMIE.DAVIES@USACE.ARMY.MIL
(615) 736-7921
(615) 736-7124
NASHVILLE TN 37202-1070
W38XDD60272136
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Revise Plans;
2. Revise Technical Specifications;
3. Post Set Three Q&A;
4. Update DFARS clause 252.236-7001; and
5. Update FAR clause 52.252-3.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P5-16-B-0004
X 9B. DATED (SEE ITEM 11)
13-Jun-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Aug-2016
CODE
US ARMY CORPS OF ENGINEERS-CELRN-RC-N
DIRECTORATE OF CONTRACTING
110 9TH AVENUE SOUTH, ROOM A680
NASHVILLE TN 37202-1070
W912P5 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE W912P5
FACILITY CODECODE
EMAIL:TEL:
W912P5-16-B-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMEND. 0004 TECHNICAL CHANGES
IFB No. W912P5-16-B-0004 Amendment No. 0004
Downstream Cofferdam Kentucky Lock
Livingston County, Kentucky
I. CHANGES TO TECHNICAL SPECIFICATIONS
A. Section 13 50 00 INSTRUMENTATION PROGRAM
1. Remove Section 13 50 00, as revised by Amendment No. 0002, in its entirety (14 pages), and replace with revised Section 13 50 00 (12 pages).
II. CHANGES TO CONTRACT DRAWINGS
A. Replace the following drawings:
Drawing No. Description
61N650-4 CONCRETE COFFERDAM, GENERAL NOTES AND DETAILS, SHEET 1 OF 3
61N650-5 CONCRETE COFFERDAM, GENERAL NOTES AND DETAILS, SHEET 2 OF 3
--- END OF AMENDMENT NO. 0004 TECHNICAL CHANGES---
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been added by full text:
Q&A SET THREE
Kentucky Lock Downstream Cofferdam Solicitation Number: W912P5-16-B-0004
Questions and Answers Set Three
102. Question: Is a third part ACR & ASR testing acceptable to quote for this project? Who will be responsible to show the ‘passed’ testing? The contractor or quarries?
Answer: The aggregate used for the concrete production shall meet all the requirements set forth in the Specifications. It is the responsibility of the aggregate supplier to provide documentation that their aggregate meets the requirements set forth in the Specifications.
The following have been modified:
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Amendment 0001: The purpose of this amendment is to:
1. Inform site visit registrants to send their registration to both Jamie Davies (Jamie.Davies@usace.army.mil) and Isaac Taylor (Isaac.J.Taylor@usace.army.mil) as Mrs. Davies will be unavailable June 24-July 4. Failure to do this could result in registrants not being able to attend the site visit.
2. Revise FAR Clause 52.211-10 to add a delayed notice to proceed
3. Update FAR Clause 52.252-3.
Amendment 0002: The purpose of this amendment is to:
1. Post Q&A Set One,
2. Extend Q&A deadline to July 15, 2016 and extend the bid opening due date to August 16, 2016 at 1:00 pm CDT.
No additional requests for extension will be considered.
3. Revise the Bid Schedule: quantity of CLINs 0008, 0041, 0044 and 0063 changed, new CLIN 0024 added, CLINs renumbered, and CLINs within option 6 removed;
4. Update Specifications (See list of changes to follow);
5. Replace Drawings 510N100 and 61N852-10, Remove Drawing 61N52-11, add DGN drawings;
6. Add Appendix A;
7. Instructions Paragraph 1.3 revised to change option exercise deadline; and
8. Update clauses 52.217-7, 52.252-3 and 252.236-7001.
Amendment 0003: The purpose of this amendment is to:
1. Post Set Two Q&A;
2. Update the technical specifications;
3. Include Cofferdam Design Document Report;
4. Revise Plans and include DGN version of those plans;
5. Add an order of precedence;
6. Update DFARS clause 252.236-7001;
7. Update FAR clause 52.252-3; and
8. Include "Highway" Wage Determination.
Amendment 0004: The purpose of this amendment is to:
1. Revise Plans;
2. Revise Technical Specifications;
3. Post Set Three Q&A;
4. Update DFARS clause 252.236-7001; and
5. Update FAR clause 52.252-3.
(End of provision)
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Technical Specifications: W912P5-16-B-0004 TSpecs.pdf W912P5-16-B-0004_TSpecs-Am2pgs.pdf W912P5-16-B-0004_TSpecs-Am3pgs.pdf W912P5-16-B-0004_TSpecs-Am4pgs.pdf
Drawings: W912P5-16-B-0004 Drawings.pdf
W912P5-16-B-0004_Plans-Am2shts.pdf W912P5-16-B-0004 DGN Files.7z W912P5-16-B-0004_Plans-Am3Shts.pdf W912P5-16-B-0004 DGN Files_Am3.7z W912P5-16-B-0004_Plans-Am4Shts.pdf W912P5-16-B-0004 DGN Files_Am4.7z
Appendix A: W912P5-16-B-0004_AppA-Am2.pdf
Reference:
KY DS Cofferdam Design Document Report: W912P5-16-B-0004-DDR-Am3.pdf
GENERAL
510N100 INDEX OF DRAWINGS, SHEET 1 OF 2
510N100A INDEX OF DRAWINGS, SHEET 2 OF 2
510N101 STANDARD ABBREVIATIONS, AND LEGENDS
SITE WORK
510N102 PROJECT LOCATION PLAN
510N102A CONSTRUCTION LIMITS PLAN
510N103 HORIZONTAL AND VERTICAL CONTROL SURVEY MONUMENTS & BASELINES
510N104 EXISTING SITE TOPOGRAPHY PLAN WITH CLEARING & GRUBBING
510N104A DISPOSAL AREA "D", PLAN
510N104B DISPOSAL AREA "D", SECTION
CELLULAR COFFERDAM
510N105 CELLULAR COFFERDAM, FINAL GRADING PLAN
510N106 CELLULAR COFFERDAM, PLAN AND GENERAL NOTES
510N107 CELLULAR COFFERDAM, TYPICAL SECTIONS
510N107A CELLULAR COFFERDAM, TYPICAL SECTIONS
518N200 CELLULAR COFFERDAM, PROFILES
518N201 CELLULAR COFFERDAM, SHEET PILE LAYOUT
518N202 CELLULAR COFFERDAM, SHEET PILE, DETAILS
518N203 CELLULAR COFFERDAM, TIE-IN TO EAST BANK, PLAN AND ELEVATIONS
518N204 CELLULAR COFFERDAM, TIE-IN TO EAST BANK, SECTIONS
518N205 CELLULAR COFFERDAM, TIE-IN TO EAST BANK, DETAILS
518N206 CELLULAR COFFERDAM, FLOODING FACILITY, PLAN AND ELEVATIONS & SECTIONS
518N207 CELLULAR COFFERDAM, FLOODING FACILITY, FLOOD GATE, ELEVATION AND SECTIONS 518N208 CELLULAR COFFERDAM, FLOODING FACILITY, FLOOD GATE, ELEVATIONS, SECTIONS &
DETAILS
518N209 CELLULAR COFFERDAM, FLOODING FACILITY, REINFORCING DETAILS
518N210 CELLULAR COFFERDAM, FLOODING FACILITY, BRIDGE, PLAN, SECTIONS AND DETAILS
518N211 CELLULAR COFFERDAM, FLOODING FACILITY, BRIDGE, SECTIONS AND DETAILS
518N212 CELLULAR COFFERDAM, FLOAT-IN CONNECTION, PLAN, SECTION AND DETAILS
GUARD CELLS
518N250 GUARD CELLS PLAN
518N251 GUARD CELL NO. 1 PLAN, ELEVATION AND SECTION
518N252 GUARD CELL NO. 2 PLAN, ELEVATION, SECTIONS AND DETAILS
CONCRETE COFFERDAM
61N650-1 CONCRETE COFFERDAM, GENERAL PLAN
61N650-2 CONCRETE COFFERDAM, TYPICAL SECTION A-A
61N650-3 CONCRETE COFFERDAM, TYPICAL SECTION B-B
61N650-3A CONCRETE COFFERDAM, GENERAL NOTES
61N650-4 CONCRETE COFFERDAM, GENERAL NOTES AND DETAILS, SHEET 1 OF 3
61N650-5 CONCRETE COFFERDAM, GENERAL NOTES AND DETAILS, SHEET 2 OF 3
61N650-6 CONCRETE COFFERDAM, GENERAL NOTES AND DETAILS, SHEET 3 OF 3
61N650-7 MONOLITHS M-22C THROUGH M-24C, CONCRETE COFFERDAM, PLAN, ELEVATION, & SECTIONS 61N650-8 MONOLITHS M-25C THROUGH M-26C, CONCRETE COFFERDAM, PLAN, ELEVATION, & SECTIONS 61N650-9 MONOLITHS M-27C & M-28C, CONCRETE COFFERDAM, PLAN, ELEVATION, & SECTIONS 61N650-10 MONOLITHS M-29C & M-30C, CONCRETE COFFERDAM, PLAN, ELEVATION, & SECTIONS
61N650-11 MONOLITH M-31C, CONCRETE COFFERDAM, PLAN, ELEVATION, & SECTIONS
61N650-12 CONCRETE COFFERDAM, VERTICAL JOINT
61N650-13 CONCRETE COFFERDAM, TEMPORARY COFFERDAM, ANCHORS AND DETAILS
61N650-14 CONCRETE COFFERDAM, TEMPORARY COFFERDAM, INFILL AND DETAILS
61N650-15 CONCRETE COFFERDAM, TIE-IN TO L-25, PLAN
61N650-16 CONCRETE COFFERDAM, TIE-IN TO L-25, ELEVATION
61N650-17 CONCRETE COFFERDAM, TIE-IN TO L-25, SECTIONS
61N650-18 CONCRETE COFFERDAM, TIE-IN TO L-25, CLOSURE PC PANEL REINF DETAILS
61N650-19 CONCRETE COFFERDAM, TIE-IN TO L-25, TRANSITION NOSE
61N650-20 CONCRETE COFFERDAM, MISCELLANEOUS METAL WALL ARMOR
61N650-21 CONCRETE COFFERDAM, MISCELLANEOUS METAL, CORNER PROTECTION
FOUNDATIONS
61N651-1 FOUNDATIONS, EXCAVATION/BLASTING, EXCAVATION SEQUENCE
61N651-2 FOUNDATIONS, GENERALIZED CONSTRUCTION SEQUENCE, SCHEMATIC SECTION
61N651-3 FOUNDATIONS, EXCAVATION/BLASTING, TOP OF ROCK
61N651-3A FOUNDATIONS, EXCAVATION/BLASTING, EXISTING GRADE
61N651-4 FOUNDATIONS, EXCAVATION/BLASTING, SECTIONS A-A, B-B AND C-C
61N651-5 FOUNDATIONS, EXCAVATION/BLASTING, SECTIONS D-D AND E-E
61N651-6 FOUNDATIONS, EXCAVATION/BLASTING, SECTION F-F
61N651-7 FOUNDATIONS, UNDERWATER, BLASTING & EXCAVATION, PLAN AND GUIDELINES
61N651-8 FOUNDATIONS, SPECIALTY WORK, OVERALL PLAN
61N651-9 FOUNDATIONS, DENTAL CONCRETE & CELL 1/1A FILL AREAS, ENLARGED PLANS
61N651-11 FOUNDATIONS, CELLULAR COFFERDAM, DRILLED PIPE PILES, ENLARGED PLAN & PILE
SCHEDULE
61N651-16 FOUNDATIONS, DRILLED PIPE PILES, PROFILES AND DETAILS
INSTRUMENTATION
61N852-10 INSTRUMENTATION, PLAN AT EL. 343.5
U/S SITE DEWATERING AND INSTRUMENTATION
61N852-13 U/S SITE DEWATERING AND INSTRUMENTATION, PLAN AND DETAILS
POWER AND LIGHTING
65N480 ELECTRICAL, LEGEND, GENERAL NOTES, ABBREVIATIONS AND LIGHTING SCHEDULE
65N481 ELECTRICAL, PLAN FOR POWER, INSTRUMENTATION AND LIGHTING
65N482 ELECTRICAL, MISCELLANEOUS ELECTRICAL DETAILS
65N483 ELECTRICAL, MISCELLANEOUS ELECTRICAL DETAILS
65N484 ELECTRICAL, GEN SET & AUTOMATIC TRANSFER, SWITCH LOCATION
65N780 ELECTRICAL, SINGLE LINE DIAGRAM AND PANELBOARD SCHEDULES
65N880 ELECTRICAL GROUNDING AND BONDING
GEOTECHNICAL BORINGS
822N3030 EXPLORATORY BORINGS, LOWER GUIDE WALL SECTION
822N3031 EXISTING BORING LOCATIONS, LOWER GUIDE WALL SECTION
822N3032 GEOTECHNICAL LEGEND
822N3033 BORING LOGS, SHEET 1 OF 27
822N3034 BORING LOGS, SHEET 2 OF 27
822N3035 BORING LOGS, SHEET 3 OF 27
822N3036 BORING LOGS, SHEET 4 OF 27
822N3037 BORING LOGS, SHEET 5 OF 27
822N3038 BORING LOGS, SHEET 6 OF 27
822N3039 BORING LOGS, SHEET 7 OF 27
822N3040 BORING LOGS, SHEET 8 OF 27
822N3041 BORING LOGS, SHEET 9 OF 27
822N3042 BORING LOGS, SHEET 10 OF 27
822N3043 BORING LOGS, SHEET 11 OF 27
822N3044 BORING LOGS, SHEET 12 OF 27
822N3045 BORING LOGS, SHEET 13 OF 27
822N3046 BORING LOGS, SHEET 14 OF 27
822N3047 BORING LOGS, SHEET 15 OF 27
822N3048 BORING LOGS, SHEET 16 OF 27
822N3049 BORING LOGS, SHEET 17 OF 27
822N3050 BORING LOGS, SHEET 18 OF 27
822N3051 BORING LOGS, SHEET 19 OF 27
822N3052 BORING LOGS, SHEET 20 OF 27
822N3053 BORING LOGS, SHEET 21 OF 27
822N3054 BORING LOGS, SHEET 22 OF 27
822N3055 BORING LOGS, SHEET 23 OF 27
822N3056 BORING LOGS, SHEET 24 OF 27
822N3057 BORING LOGS, SHEET 25 OF 27
822N3058 BORING LOGS, SHEET 26 OF 27
822N3059 BORING LOGS, SHEET 27 OF 27
RIVER CURRENT TRAINING DIKE
518N230 TRAINING DIKE, PLAN
518N231 TRAINING DIKE, SECTIONS
SHEET PILE REMOVAL
510N240 SHEET PILE REMOVAL, OVERALL PLAN
510N241 SHEET PILE REMOVAL, INVENTORY & PLAN VIEW
FOR INFORMATION ONLY
23N217 P&L RAILWAY OVER TENN. RIVER, WEST BANK BOAT BASIN, GENERAL PLAN
61N247-4 SURVEY CONTROL PLAN
61N218 LOCK PLAN SHEET 1, STA. 6+95.00A TO STA. 2+56.00B
61N219 LOCK PLAN SHEET 2, STA. 2+56.00B TO STA. 7+06.00B
61N220 LOCK PLAN SHEET 3, STA. 7+06.00B TO STA. 13+15.00B
61N221 LOCK ELEV. LAND WALL, STA. 2+05.00A TO STA. 10+45.00B
61N250 LOCK CONCRETE, ARMOR, CHECK POSTS, LADDERS, GAGES; DETAILS
61N251 LOCK CONCRETE, DERRICK BASE, JOINTS, PORTS, SLEEVES; DETAILS
61N345 LOCK LOWER GUIDE WALL, CONCRETE, BLOCKS L-21, & L-22
61N348 LOCK LOWER GUIDE WALL, CONCRETE, BLOCKS L-23, L-24, & L-25
61N454 LOCK LOWER GUARD WALL, CONCRETE, BLOCKS R-29 & R-30
505N100-8 APPROACH WALL, CONSTRUCTION GRADING PLAN
65W702 SWITCHBOARDS, 440V. A.C. SWITCHBOARD, FRONT VIEW & WIRING
65W805 CONDUIT & GROUNDING, PLAN & DETAILS, LOWER PORTION
SK-4-25-16 KENTUCKY LOCK, TAILWATER ELEVATION, INFORMATION SKETCH
TRANSMISSION LINE INFORMATION
LW-2171s1A KENTUCKY DAM - NASHVILLE TRANSMISSION LINE, STA. 0+00 TO STA. 18+91.81 LA LW-2284s1 KENTUCKY DAM - MURRAY TRANSMISSION LINE, STA. 0+00 TO STA. 3080+00 LW-2666s2 KENTUCKY DAM - PADUCAH-EARLINGTON TRANS. LINE, (S.LOOP), STA. 0+00 TO STA. 35+83.6 LW-2986s1AA KENTUCKY DAM - CALVERT TRANSMISSION LINE, STA. 0+00 TO STA. 17+26.9 LA LW-3068s1 KENTUCKY DAM - CADIZ TRANSMISSION LINE, STA. 0+00 TO STA. 70+00 LW-3395s1B KENTUCKY DAM - HOPKINSVILLE TRANSMISSION LINE, STA. 0+00 TO STA. 17+40.21 LB LW-5732s4A KENTUCKY DAM - CALVERT NO. 2 TRANSMISSION LINE, STA. 0+00 TO STA. 18+55.96