About this file

This document is an amendment to a solicitation providing answers to questions from potential offerors. It specifies that the contractor shall provide one Baileigh 112-ton C-frame hydraulic press and one Beckwood elastomeric forming kit for installation at Corpus Christi Army Depot, including delivery, rigging, installation, filling with hydraulic fluid, tooling installation, testing, and on-site training for up to 12 people. The contractor is responsible for all aspects of delivery and installation. The electrical disconnect is in place, and the work area is on a level concrete surface. Packing material disposal and an initial fill of hydraulic fluid will be the contractor's responsibility.

View the file

Other files

File Type Posted
FINAL SOW 16 MARCH 2023.docx DOCX document
W912NW23Q0016 0005.pdf PDF
FINAL SOW 16 MARCH 2023.docx DOCX document
CHANGE IN REVISED SOW 14 FEB 2023.docx DOCX document
W912NW-23-Q-0016 0004.pdf PDF
FINAL REVISED SOW 19 JAN 2023 112t Press 5.docx DOCX document
QUESTIONS AND ANSWERS 6.docx DOCX document
QUESTIONS AND ANSWERS 4.docx DOCX document
W912NW-23-Q-0016 0002.pdf PDF
QUESTIONS AND ANSWERS2 (answered).docx DOCX document
W912NW-23-Q-0016 0001.pdf PDF
W912NW-23-Q-0016.pdf PDF
REDACTED Limiting-Competition-under-SAT_ACC.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARMY CONTRACTING COMMAND - REDSTONE

TERRY B. CLARK (361)961-6489

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide answ ers to questions submitted by potential offerors.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Jan-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912NW23Q0016

X 9B. DATED (SEE ITEM 11)

09-Dec-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Jan-2023

CODE

ARMY CONTRACTING COMMAND - REDSTONE

CONTRACTING OFFICE

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

W912NW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912NW

FACILITY CODECODE

EMAIL:TEL:

W912NW23Q0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

QUESTIONS & ANSWERS

QUESTIONS AND ANSWERS

112 MACHINE PRESS

1. The bid says Baileigh C-Frame Press Brake and also says Beckwood Elastomeric sheet metal forming kit. We are a Baileigh distributor and we do not deal with Beckwood. I am not sure what you really requesting. Please advise.

The original intent was for a Baileigh press with Beckwood’ s tooling made custom for that press.

2. The contractor shall provide one (1) brand name Baileigh Industrial CFP-112HD 112- ton Elastomeric forming press with brand name Beckwood commissioned Elastomeric sheet metal forming Kit in accordance with the Statement of Work (SOW) contained herein. Who will be responsible for rigging, and we need clarification on the installation as well.

The contractor shall be responsible for everything including rigging. This is to be a turn-key project with minimal activity on CCAD’s part. “Installation” includes connecting the electrical service from a disconnect box within 10’ of the equipment’s location. The equipment needs to be anchored to the floor, filled with hydraulic fluid, the tooling needs to be installed, and test runs made.

3. What services do they need in installation?

The contractor shall be responsible for getting the equipment shipped to NASCC, removed from the freight truck/trailer, transported into the building, and adjusted to its final installation spot. The equipment needs to be hooked up to electricity, tooling installed, hydraulic fluid filled, and tested.

4. Will you accept only Baileigh?

The Government will consider other manufacturers if the proposed system meets or exceeds the performance characteristics: forming area, daylight, and tonnage.

5. What is the shipping address for said bid?

The DODAAC is W45N7V which will be in block 15 of the contract with the address 9035 OCEAN DR. BLDG 10

CORPUS CHRISTI TX 78419-5260

6. Because this RFQ is asking for off-loading and setting the machine in place we need to know a few details regarding the site as follows:

o Once the machine is delivered to the dock, how far is it from the loading dock to the place where the machine will be located? Please be specific.

100ft in concrete parking lot area, 700 ft down the asphalt road, 1200ft down concrete road, 600ft inside the building on smooth concrete o Please specify what the pathway leading from the truck to the door of the building is made of

(gravel, concrete, or asphalt).

No gravel, building perimeters are all concrete, standard asphalt on the roads between buildings.

o Are there any steps or curbs involved? If there are steps or curbs how many?

No, however there is a level crossing of a monorail for the hangar door, the gaps are maybe 1.5” wide and an inch deep.

o How big is the doorway (height and width)?

21’ high 16’ wide o Are there any turns or obstructions that would limit the turning radius when the machine is being transported from the truck to the room where the machine needs to go? We need a description of the path the machine will take once it is delivered from the dock to its ultimate resting spot.

Additional detail from first question and map: the path is nice and open up until the last bit within the shop where the turn radius is very open, to the right and down another 80ft, but headroom is reduced to 13.5 ft and one width restriction of 10ft.

o Can you provide a map or sketch of the delivery dock location which includes the route the machine will take from the delivery location to the entrance to the building.

See below from google maps.

o Is there an onsite forklift that can be used to offload the machine or will the rigger need to bring one?

The contractor is preferred to be self-sufficient for the process.

o Is the area where the machine will be placed a flat surface?

Yes, it is a flat concrete surface, leveling shims may be required.

o If start up is required, who is responsible for electrical drop and connection for machine so that the machine is plug in ready when delivered? Please confirm that electrical wiring is either already done or will be done by end user. Electrical work of any kind CANNOT be done by the mfg or the contractor, by law this must be done by a licensed electrician, which will have to be outsourced.

The electrical drop and disconnect box will be in place by CCAD prior to equipment delivery.

o Who is responsible for startup of the machine prior to training?

The contractor is responsible for startup of the machine.

o Regarding training, please advise as how many people will need to be trained?

No more than 12 including operators and mechanics who will be responsible for periodic maintenance.

o Please advise what credentials are needed to deliver and install the machine (forms of ID that the carrier/rigger will need to enter the facility).

CLEAN CRIMINAL BACKGROUND (no felony convictions within 10 years, no sex crime convictions ever), NO WEAPONS, bring bill of lading/delivery invoice. Enter through commercial vehicle lane and fill out form for background check.

o Please confirm if facility allows for packing material to be disposed of onsite at Lackland.

Lackland?? Packing material is fine to dispose of onsite at Corpus Christi Army Depot (CCAD), wooden crating material shall be disposed of in scrap wood roll-off, hazmat turned into environmental, and the remainder in regular dumpsters.

Please note: Prior to startup/training, coolant or Hydraulic fluid will be needed to be on hand prior to start up and training.

Contractor shall supply the initial fill of hydraulic fluid and any other chemicals needed. It may be drop shipped in advance though, this is primarily due to a very lengthy process to order hazmat/material that isn’t already stocked by CCAD. Contractor shall provide a list of all chemicals needed for the

7. Section 3.6 Site Specific Safety Plan

a. With past contracts we have had the SSSP is usually provide by facility not contractor, please clarify.

Contractor shall submit the safety plan to the COR for review by safety office.

b. Will SSSP from rigger and/or mfg suffice.

The plan should cover all the aspects pertinent to the whole scope of work, such it would make sense for the prime contractor to submit the documents.

8. Can you please share the part # for elastomeric forming kit?

The elastomeric forming kit does not have a part number and it is no longer offered, only a complete system is available now.

9. Because this RFQ is wanting to have the Beckman tooling which is specifically designed for the Baileigh C-Frame Press. It would be most helpful if we had a part # to reference. Do you have a part number?

The elastomeric forming kit does not have a part number as it was a proposed kit built-to-order, it is no longer offered, only a complete system is available and there is no part number.

(End of Summary of Changes)