This document is an amendment to a solicitation for a 112-ton c-frame hydraulic press and elastomeric forming kit installation. The key details are as follows:

The amendment extends the response deadline from January 5, 2023 to January 12, 2023 at 10:00 AM. It also provides answers to four questions from offerors. The first question clarifies that the solicitation seeks a Baileigh press with a custom Beckwood tooling kit. The second response specifies contractor responsibilities for equipment delivery, installation including electrical and anchoring, filling the hydraulic system, tooling installation, and testing. The third asks about required installation services, which the contractor must provide, including transport from the delivery vehicle into the building and to the final location. The fourth question indicates the Government will consider offers of presses from other manufacturers if performance requirements are met or exceeded.

View the file

Other files

File Type Posted
FINAL SOW 16 MARCH 2023.docx DOCX document
W912NW23Q0016 0005.pdf PDF
FINAL SOW 16 MARCH 2023.docx DOCX document
CHANGE IN REVISED SOW 14 FEB 2023.docx DOCX document
W912NW-23-Q-0016 0004.pdf PDF
FINAL REVISED SOW 19 JAN 2023 112t Press 5.docx DOCX document
QUESTIONS AND ANSWERS 6.docx DOCX document
W912NW-23-Q-0016 0003.pdf PDF
QUESTIONS AND ANSWERS 4.docx DOCX document
W912NW-23-Q-0016 0002.pdf PDF
QUESTIONS AND ANSWERS2 (answered).docx DOCX document
W912NW-23-Q-0016.pdf PDF
REDACTED Limiting-Competition-under-SAT_ACC.docx DOCX document
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARMY CONTRACTING COMMAND - REDSTONE

TERRY B. CLARK (361)961-6489

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the request for quote (RFQ) from 10:00 am Central Time, 05 January 2023 to 10:00 Central Time, 12 January 2023 and to provide answ ers to questions.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Jan-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912NW23Q0016

X 9B. DATED (SEE ITEM 11)

09-Dec-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Jan-2022

CODE

ARMY CONTRACTING COMMAND - REDSTONE

CONTRACTING OFFICE

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

W912NW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912NW

FACILITY CODECODE

EMAIL:TEL:

W912NW23Q0016

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS & ANSWERS

QUESTIONS AND ANSWERS

112 MACHINE PRESS

1. The bid says Baileigh C-Frame Press Brake and also says Beckwood Elastomeric sheet metal forming kit. We are a Baileigh distributor and we do not deal with Beckwood. I am not sure what you really requesting. Please advise.

The original intent was for a Baileigh press with Beckwood’ s tooling made custom for that press.

2. The contractor shall provide one (1) brand name Baileigh Industrial CFP-112HD 112- ton Elastomeric forming press with brand name Beckwood commissioned Elastomeric sheet metal forming Kit in accordance with the Statement of Work (SOW) contained herein. Who will be responsible for rigging, and we need clarification on the installation as well.

The contractor shall be responsible for everything including rigging. This is to be a turn-key project with minimal activity on CCAD’s part. “Installation” includes connecting the electrical service from a disconnect box within 10’ of the equipment’s location. The equipment needs to be anchored to the floor, filled with hydraulic fluid, the tooling needs to be installed, and test runs made.

3. What services do they need in installation?

The contractor shall be responsible for getting the equipment shipped to NASCC, removed from the freight truck/trailer, transported into the building, and adjusted to its final installation spot. The equipment needs to be hooked up to electricity, tooling installed, hydraulic fluid filled, and tested.

4. Will you accept only Baileigh?

The Government will consider other manufacturers if the proposed system meets or exceeds the performance characteristics: forming area, daylight, and tonnage.

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 05-Jan-2023 10:00 AM to 12-Jan-2023 10:00 AM.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .