GUQE192501
2019 Bldg 662 Repairs
190 Civil Engineer Squadron
03 Apr 2019
Contract Officer Representative (COR): Capt Jarrod Brunkow, 785.250.9221, jarrod.a.brunkow.mil@mail.mil
Alternate COR: Maj Noah Diehl, 785.861.4029, noah.w.diehl.mil@mail.mil
Contracting Officer (KO): Bill Phillips, 785.646.0845, william.m.phillips44.civ@mail.mil
Contracting Administrator (KO): Mr. Joe Weber, 785.646.0852, joseph.w.weber6.civ@mail.mil
Base Bid Items: This project is located within Building 662, the jumbo hangar at Forbes Field AFB. The work required covers multiple disciplines and is divided into the following items.
Item A: Replacement of HVAC unit, 3rd Floor of Bldg 662: Contractor shall replace HVAC unit feeding the 3rd Floor of Bldg. 662. Contractor shall remove and dispose of existing unit and replace with a new unit that meets the specifications provided in the attached drawing. Contractor shall install and commission a unit compatible with Bldg. 662’s HVAC controls systems. Contractor shall be responsible for installing all required control hardware/software and connecting this unit to the building controls system. "Backnet" 64-bit compatible controls are required for this unit. All new work shall comply with UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems and UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems. *See attachment A for drawings/specifications.
Item B: Replace Power Factor Corrector: Contractor shall replace entire power factor corrector system located southwest of Bldg. 662 with a new unit in the same location. Data plate from the existing unit listed in supporting documentation. Contractor is allowed to re-use existing conduits and utility connections. All new work should comply with local electrical codes and UFC 3-501-01 Electrical Engineering and UFC 3-520-01 Interior Electrical Systems. *See attachment B for drawings/specifications.
Item C: Install Communications drops, Tier 4: Contractor shall core drill through concrete decking and install (2) 4" diameter Sch 40 conduits on tier 4 into room number 314 in Bldg 662. Conduits will begin at the junction box located on Tier 4 and extend into room 314 and terminate 24" above from the carpet. Conduit will be run without hindering access to nearby electrical equipment. Contractor shall also add (2) junction boxes and (2) conduits into the northeast wall in room 314 as indicated on drawing in attachment 0007. Contractor shall also install flush mounted junction boxes into the concrete floor beneath the conference room (312) table to accommodate 4 additional phone jacks on each side of the table for a total of 8 jacks per side. *See attachment C for drawings/specifications.
mailto:jarrod.a.brunkow.mil@mail.mil mailto:noah.w.diehl.mil@mail.mil mailto:william.m.phillips44.civ@mail.mil mailto:joseph.w.weber6.civ@mail.mil
Additive Bid Items:
Item 0001: Repair floor coating, center hallway: Contractor shall remove all existing floor coating within the center hallway of building 662 and replace with new epoxy coating. Movement and re-installation of hallway lockers shall be performed by the Contractor. Exact boundaries of the work area are provided in attachment 0006. Contractor shall perform floor moisture test and mitigation prior to application of new coating. Contractor shall remove and replace all incompatible caulking that will affect adherence of the new coating. Existing coating is a Tnemec product, contractor shall use equivalent products to match color to adjacent bays. *See attachment 0001 for drawings/specifications.
Item 0002: Door and frame repairs for multiple doors in 662:
(a) Sheet metal shop, tool room: Contractor shall remove and reinstall door, frame and all wood/metal furring material. Contractor shall use appropriate metal bracing when re-installing door frame and coverall exposed material with trim that is painted to match.
Contractor shall purchase and install Schlage CO- 100 (or equivalent) cypher lock with an IC core in place of the current door lock hardware.
(b) Flight line side mechanical room: Contractor shall demolish existing 5'x8' doors, frame and threshold. Threshold shall be demolished 6" deep and re-cast with concrete that will seal against the door bottom. Contractor shall widen opening and install a double 6'x84" fiberglass reinforced panel (FRP) door and steel frame with new lock configuration (one door keyed, one door bolted from inside). Top section of opening shall be in-filled with insulated metal panel and painted to match doors. Contractor shall provide lock hardware and blank cores.
*See attachment 0002 for drawings/specifications.
Link to UFC Codes:
http://www.wbdg.org/FFC/dod/unified-facilities-criteria-ufc http://www.wbdg.org/FFC/dod/unified-facilities-criteria-ufc
SPECIAL PROVISIONS:
1. Contractor shall furnish all labor, materials, equipment and supervision necessary to complete this specified work unless otherwise noted. Contractor shall not assume use of government equipment.
2. During excavation activities, contractor shall remove and dispose all the demolished material to a designated location on Forbes or retain for Contractor use.
3. When demolishing facilities/equipment, recyclable material must be processed through the base recycling program unless directed otherwise by the COR or specified in the SOW line item.
4. Exact project quantities must be field verified by Contractor prior to award.
5. Work is to be performed between 7:00 a.m. to 5:00 p.m., Monday through Friday. Work on weekends and holidays only with coordination and written permission.
6. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
7. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.