Schedule of Material Submittals Project title:

TOC Number: DAHA Project Number: GUQE 192501 To be completed by Project Engineer Number Of Required To be completed by KO Approval Item or Description of Item Copies days after pre-con Submittal Date CE approval date Disapproval date

1 1 15

2 1 15

3 1 15

4 Power factor corrector equipment 1 15

5 Power factor corrector enclosure repairs 1 Prior to installation

6 Door size and cut sheet for both locations 1 15

7 Door opening modifications (lintels, frame, threshold) 1 15

8 Floor coating removal process 1 15

9 New joint sealant and floor coating material 1 Prior to installation

10 Comm conduit material, junction boxes, and terminations 1 Prior to installation

Conduit path drawing 1 Prior to installation

Base safety policy (signed by Prime CTR)

Bldg 662 Repairs

Project Schedule

HVAC unit & controls hardware/software