Site_Visit_Minutes_1414_2nd.pdf

PDF 234 KB Posted

Attached to
Bldg 1414 HVAC and Fire Alarm Repair
Solicitation number
W912JB-19-B-5006
Issued by

About this file

Meeting Minutes

View the file

Other files

File Type Posted
Bid_Opening_Abstract_1414.pdf PDF
Bid_Opening_Sign_In_Sheet.pdf PDF
RFI_DOCUMENT_8-20-19.pdf PDF
W912JB-19-B-5006_Solicitation_Amendment_0004.pdf PDF
W912JB-19-B-5006_Solicitation_Amendment_0003.pdf PDF
RFI's_From_15_August_Site_Visit.pdf PDF
Sign_In_Sheet_2nd.pdf PDF
Superintendent_RFI.pdf PDF
RFI_Clarification_on_ACM_and_Lead_Paint.pdf PDF
1414_TEOC_Sept_2012.pdf PDF
Appendix_D._SANG_Bldg_1414_ACM_Survey.pdf PDF
RFI_Clarification_on_4_subjects.pdf PDF
W912JB-19-B-5006_Solicitation_Amendment_0002.pdf PDF
Site_Visit_Minutes_1414.pdf PDF
Sign_In_Sheet.pdf PDF
W912JB-19-B-5006_Solicitation_Amendment_0001.pdf PDF
SANG_Bldg_1414-Upgrade_HVAC_&_Fire_Alarm_-_Drawings_Pt1.pdf PDF
Bldg_1414_HVAC_DDC_-_Brand_Name_Justification.pdf PDF
W912JB19B5006.pdf PDF
Building_1414_SIMPLEX_-_Brand_Name_Justification.pdf PDF
SANGB_Vetting_Access_Request.pdf PDF
SANG_Bldg_1414-Upgrade_HVAC_&_Fire_Alarm_-_Drawings_Pt2.pdf PDF
Building_1414_-_AF_Form_66_Rev_00.xls XLS spreadsheet
SANG_Bldg_1414-Upgrade_HVAC_&_Fire_Alarm_-_Drawings_Pt4.pdf PDF
SANG_Bldg_1414-Upgrade_HVAC_&_Fire_Alarm_-_Drawings_Pt3.pdf PDF
SANG_Bldg_1414-Upgrade_HVAC_&_Fire_Alarm_-_Specifications_-_Rev_01.pdf PDF
UPDATED___Presolicitation_Notice_1414_HVAC.PDF PDF
UPDATED___Presolicitation_Notice_1414_HVAC.PDF PDF
Presolicitation_Notice_1414_HVAC.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MICHIGAN AIR NATIONAL GUARD

127th MISSION SUPPORT GROUP

SELFRIDGE ANG BASE MICHIGAN

14 August 2019

MEMORANDUM FOR RECORD

FROM: 127 MSC

Contracting Division

43200 Maple St, Bldg. 105

Selfridge ANGB, MI 48045-5213

SUBJECT: Pre-Proposal Conference for Solicitation W912JB-19-B-5006, Project No. VGLZ 182018:

BLDG. 1414 HVAC & ROOF

1. Site visit held this date at the Contracting Division conference room commencing at: 10:00AM in conjunction with subject Request for Proposal. For list of attendees see sign in sheet.

2. Contract Specialist David Brown introduced himself, Tom Resh and Will Payne from the government’s team for the project. Steven Stocking was introduced as the Contracting Officer.

A. PROJECT DESCRIPTION:

The contractor shall schedule, mobilize and perform a complete construction project on Building 1414 ( TACOM ) in line with the engineering design for the project:

Building 1414 – Repair HVAC and Fire Alarm – VGLZ 182018 at Selfridge ANGB.

3. Bids are due NLT Tuesday 20 August 2019 at 2:00PM EST. Offerors are to hand carry bids to

127 MSC Lobby/Conference Room and deposit bids in a bid depository. Offerors are advised that this project is not currently funded and that offers must be good for 90 days.

a. Project Magnitude is between $1,000,000.00 and $5,000,000.00

b. After the notice to proceed is issued the project has a performance time of 548 calendar days for project completion.

c. A Site Visit will be held immediately after this pre-proposal conference at the construction site.

d. When amendments are issued they will be posted to the FBO website.

e. Bid, Payment, and Performance Bonds will be required for this project based on

Independent Government Estimate.

f. Liquidated damages are not applicable to this project.

g. Warranty of Construction clause is incorporated and applies to this project.

h. The most current wage determination is incorporated into the solicitation and will be made part of the resultant contract but it is the contractor's responsibility to keep track of the most current wage rate. Currently DBA MI20190091 Mod 3 dated 5 July 2019.

i. Safety measures are always a part of Government contracts and the Army Corp of

Engineers manual is incorporated in the contract.

j. RFI procedures were reviewed as follows:

i. Email technical questions in RFI format to the Contracting for resolution.

ii. All RFI questions and answers will be emailed out as soon as possible.

k. Please recall that only the Contracting Officer can approve changes such as price, schedule, specifications, and clauses with formal written notice typically in the form of a solicitation amendment or task order modification. Work undertaken regarding changes not formally approved by the Contracting Officer (save for COR approved no cost field changes) is at the Contractor’s risk.

l. This requirement is currently funded.

4. The project description was stated in the FBO announcement package repair transformers project announcement notice sent out with the Notice of Solicitation Form on 10 July 2019.

5. Any project specific questions were referred to the RFI submittal process.

6. The site visit concluded at 11:00am on Wednesday 14 August 2019.

8/14/2019

X David Brown

David Brown

Contract Specialist

Signed by: BROWN.DAVID.ALLAN.1096981950