Amendment 0004 for SDVOSB Request for Proposal W912HY-09-R-0026

View the file

Other files

File Type Posted
Amendment0008.pdf PDF
Amendment0007.pdf PDF
Amendment0006.pdf PDF
Amendment0005.pdf PDF
Amendment0003.pdf PDF
Pre-Proposal conference.ppt PPT presentation
sign-in sheet.pdf PDF
Amendment0002.pdf PDF
Amendment0001.pdf PDF
FINAL.RFP.09-R-0026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

0004 - 2

RFP for IDIQ MATOC, Design-Build and Design-Bid-Build Projects for Horizontal Construction Services, Southwestern Division (SWD), Service-Disabled Veteran-Owned Small Business Pool of Contractors, for which proposals are due on 30 Oct 09 is amended as follows:

1. AMENDMENT 0002, Page 0002 - 2, Paragraph 6.1.1,– the striked-through language below is hereby deleted from the paragraph:

6.1.1. The Government will evaluate the required information to determine how well the offeror identifies and demonstrates that its key personnel meet or exceed minimum qualifications necessary, which includes previous satisfactory experience in similar type work, to manage, SWD DB/DBB IDIQ MATOC SDVOSB W912HY-09-R-0026 00 22 20 – 7 control and perform the design, and to perform construction. Performance of key personnel proposed for this project may be taken into account when it comes to the attention of the Government. Evaluate how well the Offeror demonstrates that it has the necessary structure and experienced, qualified personnel within its organization to effectively manage, control, administer and execute the integrated design and construction operations, quality control program and subcontracts. This shall be achievable with other projected on-going work. Give additional consideration to previous design-build experience. Evaluate whether designers of record are registered (a requirement), experienced and qualified, that permit preparers are qualified in the jurisdiction (a requirement). The minimum experience requirements for the Project Manager are at least 5 years construction and construction management experience. The minimum experience requirements for the Design manager are at least 5 years of design experience or at least 5 years of construction and construction management experience.

The minimum experience requirements for the project superintendent are at least 5 years experience as superintendent, managing multiple trades and subcontractors. If alternates are proposed for key positions, the evaluation rating will consider the lesser qualified or experienced person, if there is a difference.

2. Section 00 22 10: Page 13, Paragraph 7.1.1: “Mechanical” is hereby added to the list of Designers of record.

4. Section 00 73 00 – revise SCR (15) to add mechanical to the list of designers, which was inadvertently deleted by AMD 0001.

1) Section 00 73 00, Special Contract Requirements: Page 5, Paragraph (15): Replace with the following paragraph.

“(15) REQUIREMENTS FOR REGISTRATION OF DESIGNERS (APR 1984) FAR 52.236-

25 (July 03)

The design of structural, mechanical, electrical, civil, hydrology, geotechnical, or other engineering features of the work shall be accomplished or reviewed and approved by designers registered/licensed to practice in the particular professional field involved in a State or possession of the United States, in Puerto Rico, or in the District of Columbia. Each final design submittal drawing and certified final drawings ready for construction shall be signed and

0004 - 3 sealed by the registered professional (Designer of Record) responsible for the design indicated on the particular sealed sheet.”

00 73 00 Revised 10-5-09 (AMD0001).pdf
(8) SUBMITTAL OF WORK TO BE PERFORMED BY THE CONTRACTOR – JUL 2001
(9) PROTECTION OF MATERIAL AND WORK – AUG 1997
(11) APPROVAL OF MACHINERY AND EQUIPMENT
(29) ELECTRONIC SUBMITTAL OF OFFEROR’S PROPOSAL
IDCode:
Page: 1
Pages: 3
AmendNo: 0004
EffDate: 10/20/09
ReqNo:
ProjNo:
IssCode:
IssuedBy: U. S. ARMY CORPS OF ENGINEERS

GALVESTON DISTRICT OFFICE

P. O. BOX 1229

GALVESTON, TEXAS 77553-1229

AdmCode: CT
AdminBy: U. S. ARMY CORPS OF ENGINEERS

GALVESTON DISTRICT OFFICE

P. O. BOX 1229

GALVESTON, TEXAS 77553-1229

ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolAmdNo: W912HY-09-R-0026
AmendDate: 10/20/09
ModNo:
ModDate:
NoCopies:
Amended: Off
ApprData:
ChgeOrder:
Modify: Off
SuppAuth:
OthrSpec:
Require: No
Copies: 1
Descript: IDIQ MATOC for Horizontal Construction Services, Southwestern Division (SWD), Service-Disabled Veteran-Owned Small Business Pool of Contractors for which proposals are due on 30 Oct 2009 at 2:00 P.M.CT is amended as follows:

CONTINUED

SignName:
SignTitl:
ContDate:
CoName:
CoTitle:
CODate:
SolChgYs: Yes
SolChgNo: Off
OffrExt: Off
OffrNoEx: No
ChgeOrd: Off
SuppAgre: Off
ModOthr: Off
NoReq: Off

File details come from the government source that posted it. Updated .