FY18 DESC1805 Upgrade Fuel Wharf COMFLEACT Sasebo, Yokose, Japan
SECTION 00 10 00, Soliciation, Contract Line Item Number (CLIN) Schedule SECTION 00 21 00, Instructions SECTION 00 22 00, Proposal Submission and Evaluation Criteria SECTION 00 45 00, Representations and Certif ications SECTION 00 70 00, Conditions of the Contract SECTION 00 73 00, Supplementary Conditions DIVISION 01, General Requirements DIVISION 02-41, Technical Provisions
DRAWINGS
JIRO MIYAIRI 046-407-8837
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
21-May-2018
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______15 calendar days and complete it w ithin ________750 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________3 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________06 Aug 2018 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USACE-JAPAN DISTRICT
RM 147, BLDG. 250
CAMP ZAMA
ZAMA-CITY, KANAGAWA 252-8511
JAPAN
W912HV
PAGE OF PAGES
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 046-252-0994 TEL: FAX:
W912HV18R0006 1 OF 70
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912HV18R0006
SECTION 00 10 00
SOLICITATION, CONTRACT LINE ITEM NUMBER (CLIN) SCHEDULE
ITEM
NO.
DESCRIPTION QUANTITY UNIT UNIT
PRICE
AMOUNT
BASE ITEMS
0001 Demolition 1 JB - ¥________
Fuel Wharf, Mooring Dolphins, Small Boat Dock, Dock Shed, and Supporting Facilities
1 JB - ¥________
0003 Oil Boom and Reel 1 JB - ¥________
TOTAL BASE CLIN SCHEDULE ¥________
NOTES:
1. Failure of the offeror to propose prices for all items in the CLIN Schedule may be cause for rejection of the proposal as unacceptable.
2. See Section 01 22 00.00 10, for additional line item description.
3. Any reference to “bid”, bidder, or “bidding schedule” shall be construed to mean “offeror” and “CLIN schedule”
4. LEGEND: JB = Job
Section 00 21 00 - Instructions
1. DELIVERY OF BIDS/OFFERS (MAR 2014).
a. Each bidder/offeror is solely responsible for ensuring that their bid/offer is received by the Government as specified in the solicitation. Please read the following statements to ensure timely submittal of your bid/offer:
(1) Closely coordinate the delivery of your bid/offer in sufficient time before the bid opening date/proposal due date.
(2) Bids/offers will not be accepted at the main gate of Government facilities.
(3) Valid picture identification is required for entry into Government facilities.
b. For Japanese visitors, Residential Registration Card, Passport, or Japanese Driver's License are considered valid picture Identification. Those individuals using a newly issued Japanese driver’s license with an Identity Code (IC) chip as a form of identification will be required to enter an 8 digit Personal Identification Number (PIN) into an IC Chip Reader.
Individuals are granted 3 attempts to input their PIN and will be denied access if they are unable to input the correct PIN. To obtain or reset the PIN code, individuals should go to their local Japanese police driver’s licensing center for assistance.
c. For non-Japanese visitors, Passport or Alien Registration Card are considered valid picture identification.
d. The Government will not escort or provide any base access to any door-to-door service company.
e. For bids/offers addressed to Camp Zama.
(1) The Japan Post has access to Camp Zama.
(2) If you decide to hand-carry your bid/offer to Camp Zama, please allow sufficient time to have a Government personnel meet your representative(s) at the Camp Zama main gate, sign your representative(s) in, and be escorted to our office. We suggest arriving at the gate to Camp Zama at least 30 minutes before the closing time for bid/offer acceptance.
2. BIDDERS MAILING LIST APPLICATIONS. Firms which have not submitted Bidders Mailing List Applications to this office are requested to go to the U.S. Army Corps of Engineers, Japan Engineering District, Contracting Division website:
http://www.poj.usace.army.mil/BusinessWithUs/GettingStarted.aspx to download the Bidders Mailing List Application. Such firms shall be required to complete the aforementioned application and submit documents indicating they are registered with the Government of Japan to perform construction in Japan and possess both the necessary construction licenses and permits required to perform the requisite work identified in the solicitation. This documentation must be submitted prior to or at the time of proposal submission.
3. SOLICITATIONS FOR LOCAL SOURCES ONLY. This contract will be performed in its entirety in the country of Japan and is intended only for local sources. (See Federal Acquisition Regulation 5.202(a)(12) and Paragraph titled, ”Offeror Eligibility”.) (JED APR 2006)
4. SUBMISSIONS OF OFFERS IN JAPANESE YEN. Offers submitted in response to this solicitation shall be in terms of Japanese Yen, including any required bid guarantee. Offers received in other than Japanese Yen shall be rejected.
5. MAGNITUDE OF THE PROPOSED PROJECT.
a. Physical Characteristics: Project construction shall include, but is not limited to the demolition of the existing Marine Loading Arms (MLA’s), fuel piping, pavement, and existing dock house; construction of a 891 SM (9,590 SF) extension of the existing fuel wharf including new catwalks, mooring dolphins, marine fenders, mooring bollards, new MLA’s, fuel pipe manifold, fuel stripping system, extension of the existing fuel lines between the existing wharf and new MLA’s, fuel spill containment system with sump pumps, wharf fascia, dock shed, and oil boom reel system; and construction of a new small boat dock system including a wave breaker wall, concrete floating dock, and catwalk. The fuel wharf extension shall include all necessary supporting utilities including but not limited to, potable water, fire protection, electrical, communications, lighting, cathodic protection, access roads, sidewalks, fencing, gates and demolition of miscellaneous structures. Site work consist of both demolition and new construction.
b. Magnitude of the Proposed Project. The estimated price range of this work is between ¥2,500,000,000 and ¥10,000,000,000 [FAR 36.204].
6. REQUESTS FOR INFORMATION (PROJNET Bidder Inquiry Module).
a. All questions regarding this solicitation are to be submitted through the web-based program “Bidder Inquiry Module”. This program is located on the world-wide internet and can be accessed at https://www.projnet.org/projnet/. This program will allow contractors to submit questions and see all other questions related to this project. Telephonic and email questions sent directly to Government representatives will not be accepted. All questions (requests for information) must be submitted through the web-based program, Bidder Inquiry Module.
b. To submit and review questions related to this project, prospective offerors will need to use the Bidder Inquiry Key and follow the instructions listed below for access.
The Bidder Inquiry Key is: 94ZSF9-PJPPM2
c. Access Instructions:
(1) Go to the website: https://www.projnet.org/projnet/.
(2) At the home page, select USACE for the “Managing Agency” field
(3) At the home page, enter your email address under the “EMAIL” field (do not enter a password in the “Regular Accounts” Section)
(4) At the home page, enter the Bidder Inquiry Key under the “KEY ACCESS” field
(5) Read and check “I agree to the privacy & security notice”
(6) Press Sign-in button
(7) A page will open requesting user account information and will ask you to create a new account (if you don’t have an existing account in the system). Enter all data fields required for account creation. When you log back in, you will need to answer your security question.
(8) Press add user to continue
(9) Upon completion of account creation, you will have access to the ProjNet system and project page.
(10) Review and submit questions regarding this project. An offeror who submits a question will receive an automated email notification that their question has been received. All questions and answers can be viewed from this program.
(11) For questions about ProjNet, please contact the Call Center help desk toll free number at 1-800-428-HELP, which operates from 8 am to 5 pm (U.S. Central Time Zone). Questions can be emailed to the helpdesk at staff@rcesupport.com.
d. Request for Information must be submitted within the ProjNet Bidder Inquiry Module no later than June 27, 2018 at 1700 local time. The Government reserves the right to answer questions after this deadline and is not obligated to provide a response. The Government will not respond to the inquiries in ProjNet but will respond to the inquiries via an amendment. Any information given a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment to the solicitation, if that information is necessary in submitting proposals or if the lack of it would be prejudicial to other prospective offerors.
e. Notes:
(1) Offerors should review the solicitation and specifications in their entirety, review the Bidder Inquiry Module for questions and answers, prior to the submission of a new inquiry.
(2) Offerors should submit their questions one at a time and not submit multiple questions embedded into a singular statement. Please cite the reference for each question and where in the solicitation that question is located or predicated upon.
(3) Please include any correspondence towards this project.
7. BONDING THRESHOLDS (MAR 2015).
a. Under the Federal Acquisition Streamlining Act of 1994, Public Law 103-355 (FASA), the Miller Act (40 U.S.C. 270a-270f) no longer applies to contracts that do not exceed the amount of $150,000. Therefore, the Government will not require the successful bidder to furnish a performance bond if it appears that award of a contract to the bidder will be in an amount of ¥17,250,000 or less.
b. The government requires a bid guarantee to accompany a bid when a performance bond will be required under the resulting contract. Therefore, under this solicitation, any bid that is in excess of ¥17,250,000 shall be accompanied by a bid guarantee, in the form and amount that is required by provision "52.228-1, BID GUARANTEE," and other pertinent provisions and clauses in this solicitation. Failure to submit a bid guarantee in such case may render the bid non-responsive to the solicitation.
c. A bid under this solicitation that does not exceed ¥17,250,000 shall not require a bid guarantee to be submitted with the bid. Absence of a bid guarantee in such case will not, in and of itself, render the bid non-responsive to the solicitation.
8. SAFETY STANDARDS. The successful offeror will be required to comply with the Occupational Safety and Health Act (OSHA) standards as well as the Corps of Engineers Manual 385-1-1, Safety and Health Requirements Manual.
9. PERFORMANCE OF WORK BY THE CONTRACTOR – DEFINED. For the purpose of Clause entitled, "PERFORMANCE OF WORK BY THE CONTRACTOR", of Special Contract Requirements, work on the site with the Contractor's own organization means physical activities at the site other than work performed by subcontractors, procurement of materials for installation by subcontractors, or providing equipment to be used solely by subcontractors.
10. PRORATED COSTS. All costs pertaining to the performance of work under the contract over and above the direct costs for the work shall be prorated to and included in the price quoted for each item in the Bidding Schedule.
11. SPECIAL TREATMENT OF PACKAGING OF EQUIPMENT AND MATERIAL. Bidders are cautioned that equipment and material requiring ocean transportation may be subjected to inordinate dangers and special treatment or packaging may be necessary to assure arrival in a condition conforming to contract requirements.
12. SIGNATURE ON OFFERS. Offers must be signed by an officer of the company or an individual who is authorized to sign offers for and on behalf of the company. An individual, other than an officer of the company, who signs an offer must submit evidence of his authority to sign such offer. This evidence must accompany the offer. Failure to comply with this requirement may be cause for rejection of the offer.
13. JOINT VENTURE. In the event the offeror is a joint venture, the offer must be signed by an authorized representative of each participant in the joint venture. Failure to comply with this requirement may be cause for rejection of the offer.
14. OFFEROR ELIGIBILITY. Only local sources will be considered under this solicitation.
Local sources are sources (e.g. corporations, partnerships, or Joint Ventures [For a Joint Venture, the Joint Venture as an independent entity must satisfy the local source requirements or, in the alternative, each member of the Joint Venture must individually satisfy the local source requirements]) that are physically located in Japan and authorized (i.e. licensed and registered) to perform in Japan, the type of construction work specific in this solicitation. Specifically, a prospective offeror must be duly authorized to operate and conduct business in Japan and must fully comply with all laws, decrees, labor standards, and regulations of Japan during the performance of the resulting contracts. In addition, prior to award of the contracts, offerors must be registered with the Government of Japan to do construction work in Japan and possess necessary construction licenses and permits to perform work required under this solicitation.
The U.S. Government will not offer “United States Official Contractor” status under Article XIV of the US-Japan Status of Forces Agreement (SOFA) to U.S. contractors normally resident in the United States; nor will the U.S. Government certify employees of such contractors as “Members of the Civilian Component” under Article I(b) of the SOFA.
15. JAPANESE CONSUMPTION TAX (APR 2014). Effective April 1, 2014, the Government of Japan increased the rate of Japanese Consumption Tax from 5% to 8%. By virtue of Article XII of the Status of Forces Agreement (SOFA), materials, supplies, equipment and services procured for official purposes in Japan by the United States armed forces, or its authorized procurement agencies are EXEMPT from various Japanese Taxes, including Consumption Tax.
The exemption from the Japanese Consumption Tax applies not only to Japanese prime contractors, but also to Japanese subcontractors or suppliers at every level regardless of the nationality of the prime contractor whether a Japanese or a Foreign firm. The instruments listed hereinafter have been agreed to by both governments of Japan and the U.S. as "Proof of Purchase by U.S. Forces in Japan.”
Standard Form 1034 Public Voucher for Purchases and Services other than Personal
DD Form 1155 Order for Supplies or Services
Standard Form 44 Purchase Order-Invoice-Voucher
ENG Form 93 Payment Estimate
Therefore, Japanese Consumption Tax shall NOT be included in your bid, proposal or quote.
16. DEFINITION OF THE WORDS ITEM/ITEMS.
a. This solicitation contains a single schedule for award to a single bidder.
b. For the purpose of this solicitation, the words "ITEM" and "ITEMS" as used in provision(s) of this section shall be construed to mean "SCHEDULE" and "SCHEDULES", respectively.
17. BID GUARANTEES AND PERFORMANCE BONDS (MAR 2018).
a. ACCEPTABLE SURETIES. Notwithstanding the statement contained in paragraph (d) of the clause, FAR 52.228-15, "Performance and Payment Bonds - Construction", concerning the acceptable corporate sureties appearing on the Treasury Department Circular 570, a corporate surety that has received official approval to execute bid bonds (Standard Form 24) and performance bonds (Standard Form 25) on United States Forces Japan construction projects from the Government of Japan will be considered an acceptable surety. Banks are not acceptable sureties; bid bonds and performance bonds executed by banks will be rejected.
b. Notwithstanding the statement contained in paragraph (b) of clause FAR 52.228-1, “Bid
Guarantee”, the bid guarantee must be supported by good and sufficient corporate surety or sureties acceptable to the Government.
c. Notwithstanding the statement contained in paragraph (d) of clause FAR 52.228-15, "Performance and Payment Bonds – Construction”, the performance bond must be supported by good and sufficient corporate surety or sureties acceptable to the Government.
18. FUNDING. Funds are not presently available for this acquisition. No contract award will be made until appropriated funds are made available from which payment for contract purposes can be made.
19. METHOD OF PROCUREMENT. The US Army Corps of Engineers, Japan District, intends to solicit this requirement using the source selection procedures in accordance with the provisions set forth in this Request For Proposal (RFP). A Firm-Fixed Price construction contract will be awarded to the offeror who submits a proposal determined to be the Lowest Evaluated Priced and meets the Technically Acceptable Standards for the non-price factors (see Section 00 22 00).
20. PRE-AWARD SURVEYS. The Government reserves the right to conduct a pre-award survey of any firm under consideration to confirm any part of the information furnished by the offeror, or to require other evidence of managerial, financial, technical, and other capabilities, the positive establishment of which is determined by the Government to be necessary for the successful performance of the contract.
21. PRE-PROPOSAL CONFERENCE.
a. Offerors are strongly urged and expected to attend and participate in the pre-proposal conference. The purpose of this conference is to promote uniform interpretation of the solicitation documents and work requirements and can include discussions of any problems with interpretations of the solicitation documents and work execution identified by potential offerors through written questions. In no event will a failure to attend the pre-proposal conference constitute grounds for a claim after award of the contract.
b. Offerors are encouraged to ask questions at the conference. Any questions made at the conference may or may not be addressed at the conference, but will be addressed in the minutes of the conference.
c. This Pre-proposal Conference will be conducted concurrently with the pre-proposal site investigation. Please see 52.236-27 SITE VISIT section for information regarding the meeting.
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2016 52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017 52.236-28 Preparation of Proposals--Construction OCT 1997
252.204-7004 Alt A
System for Award Management Alternate A FEB 2014
252.204-7008 Compliance With Safeguarding Covered Defense Information Controls
OCT 2016
252.215-7008 Only One Offer OCT 2013
CLAUSES INCORPORATED BY FULL TEXT
52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM
DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND
STANDARDIZATION INFORMATION SYSTEM (ASSIST) (APR 2014)
(a) Most unclassified Defense specifications and standards may be downloaded from the following ASSIST websites:
(1) ASSIST (https://assist.dla.mil/online/start/);
(2) Quick Search (http://quicksearch.dla.mil/);
(3) ASSISTdocs.com (http://assistdocs.com).
(b) Documents not available from ASSIST may be ordered from the Department of Defense Single Stock Point (DoDSSP) by--
(1) Using the ASSIST Shopping Wizard (https://assist.dla.mil/wizard/index.cfm);
(2) Phoning the DoDSSP Customer Service Desk (215) 697-2179, Mon-Fri, 0730 to 1600 EST;
or
(3) Ordering from DoDSSP, Building 4, Section D, 700 Robbins Avenue, Philadelphia, PA 19111-5094, Telephone (215) 697-2667/2179, Facsimile (215) 697-1462.
(End of provision)
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm fixed-price construction contract resulting from this solicitation.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20 percent of the bid price or ¥345,000,000, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
CONTRACTING DIVISION - CONTRACTING OFFICER
U.S. Army Corps of Engineers, Japan District Camp Zama - Bldg 250, Room 147 Zama-City, Kanagawa 252-8511 Japan
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for --
Date: June 13, 2018 Time: 0900 hrs Location of Meeting: CFAS Nimitz Park, Pavilion No 2 (Facility No 1686) COE POC/phone number/email:
Ms. Fumi Shimomura (DSN: 252-3598; LOCAL 0956-50-3598), Fumi.Shimomura.ln@usace.army.mil, The meeting location at CFAS Nimitz Park occasionally has controlled access. All contractors visiting the construction site must be approved for entry by CFAS Security.
Prospective Offerors interested in attending the site investigation shall contact Ms. Fumi Shimomura at commercial phone No. 0956-50-3598, or e-mail Fumi.Shimomura.LN@usace.army.mil for base access (forms and information). Completed forms and information for base access shall be provided to her NOT LATER THAN 1100 hours on Friday, June 1, 2018.
For CFAS Security access approval, prospective offerors must provide:
Individual Names and Addresses of personnel representing the Offeror written in both English and Japanese.
Telephone Numbers of Company and Individual Company Name & Address Vehicle Information: Make, Model, Year and License Plate Number* Driver’s Information: Driver’s License and Insurance Information Proof of citizenship (Koseki Tohon or Passport) A valid government issued photo ID card (Driver’s License or Passport) is required during the site investigation
* If using a rental car, coordinate with the rental car company to identify the license plate in advance.
Prospective offerors shall be limited to ten (10) personnel per company. Transportation to the site will NOT be provided by the Government. Commercial Vehicles (taxis) will NOT be allowed access on the base.
Individuals not identified on the CFAS Security approved list shall NOT be allowed access to the base. Please arrive at the meeting location 15 minutes before the meeting time.
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/
52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)
Portions of this solicitation are altered as follows:
Subparagraph (c)(5) of FAR clause 52.215-1 -- Instructions to Offerors -- Competitive Acquisition, is revised to read as follows. “Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in Japanese yen.”
Section 00 22 00 - Supplementary Instructions
SUBMISSION AND EVALUATION CRITERIA
1.0 BASIS FOR AWARD
1.1 Contract award will be made to the responsible offeror whose proposal represents the best value to the Government utilizing the Lowest Price Technically Acceptable (LPTA) source selection procedures. To receive consideration for award, a rating of no less than “Acceptable” must be achieved for Factor 1 -- Experience and Factor 2 -- Past Performance. In accordance with (IAW) FAR 15.404-1 -- Proposal Analysis, price will be evaluated for fairness and reasonableness and the adequacy of the offer in fulfilling the requirements of the solicitation in their proposal. The Government intends to evaluate proposals and award a contract without holding discussions; however, reserves the right to conduct discussions if deemed necessary by the Contracting Officer.
2.0 GENERAL INSTRUCTIONS
This acquisition is being conducted using a design-bid-build procurement process.
2.1 Offerors shall strictly adhere to the requirements in this Section when preparing the proposal to be submitted in response to this Request for Proposal (RFP). All proposals shall be in English. The Government will not reimburse any offeror any cost incurred in response to this RFP. Proposals that fail to comply with the proposal submittal requirements addressed in this section of the solicitation may be deemed unacceptable. Copies of the RFP are available by INTERNET ACCESS ONLY. All RFP documents will be posted to and made available for viewing in Federal Business Opportunities (http://www.fbo.gov). All amendments will be posted to and made available for viewing in FedBizOpps. It shall be the Offeror’s responsibility to check the website for any amendments. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the Amendment(s).
2.2 The Government seeks award of one contract to the responsible offeror whose proposal conforms to the solicitation and represents the best value to the Government utilizing Lowest Priced Technically Acceptable (LPTA) source selection procedures. An offeror that obtains an “Acceptable” rating on all non-price factors (Factor 1, Experience and Factor 2, Past Performance) will be technically acceptable. Award will be made to the lowest priced responsible offeror that is technically acceptable.
2.2.1 Offerors are advised the Government intends to make an award on the basis of initial proposals without conducting discussions with the offerors. However, the Government reserves the right to discuss aspects of proposals with Offerors in the competitive range, if one is determined to be necessary, upon completion of the evaluation. Offerors are advised that the Government may make award without discussions, clarifications, or any contact concerning the proposals received. Therefore, proposals should be submitted initially on the most favorable terms from a price and technical standpoint. Offerors shall not assume that they will be contacted or afforded an opportunity to clarify, discuss or revise their proposals.
2.3 Proposals received by the Government after the date and time set for receipt of proposals will be handled in accordance with the requirements of Provision “52.215-1, Instructions to Offerors – Competitive Acquisition”. Note: When hand-carrying proposal, offerors are advised they must process through the base security and should be aware of possible delays.
2.4 Offerors are required to provide information addressing all stated factors in a clear and understandable format. If an offeror does not have information relating to a specific factor, the offeror shall clearly state so in the proposal. Proposals that do not clearly address all factors may be considered unacceptable and may not receive further consideration.
3.0 PROPOSAL REQUIREMENTS AND SUBMISSION FORMAT
3.1 General Requirements: The proposal shall be clear, concise and shall include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal shall not simply rephrase or restate the Government’s requirements, but rather provide convincing rationale to address how the Offeror intends to meet the requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience and will base its evaluation on the information presented in the offeror’s proposal.
3.2 General Format
3.2.1 Proposals shall be submitted in two (2) separate envelopes as indicated below:
3.2.1.1 Volume I shall contain the Technical Proposal and shall be clearly marked Volume I – Technical Proposal. In addition, follow instructions in Paragraph (c)(1) of Section 00 21 00, 52.215-1, INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION.
3.2.1.2 Volume II shall contain the Price Proposal and shall be clearly marked Volume II – Price Proposal. In addition, follow instructions in Paragraph (c)(1) of Section 00 21 00, 52.215-1, INSTRUCTIONS TO OFFERORS--COMPETITIVE ACQUISITION.
3.2.3 Each volume shall be separate and complete in itself so that evaluation of one may be accomplished independently from evaluation of the other. It is recommended that the pages be standard 8-1/2” x 11” or A4 white bond paper using 12 characters per linear inch or equivalent as the minimum size standard for text. Volume I, Technical, shall not contain any reference to cost for this project. The total pages submitted for Volume I, Technical Proposal shall not exceed 45 pages. Any pages over the prescribed limit will not be considered for evaluation.
Each volume shall include page numbers on each page
3.2.4 The Government recognizes that offerors go to considerable expense to prepare proposals for this solicitation, so the Government prefers that proposals be practical. Elaborate format, special binders, special reproduction techniques, and the like are not necessary or desired. In short, the proposal shall completely and adequately address the requirements stated in solicitation. Proposal legibility, clarity, coherence, and contents are important. The technical proposal, Volume I of the Offeror’s proposal shall be bound and shall not exceed 45 single-spaced single sided sheets. Do not include the front and back cover of the technical proposal in the 45 sheet count. However, all other sheets, including Past Performance Questionnaire, will be included in the count. Since only the first 45 sheets of the offeror’s technical proposal will be evaluated by the Government, it is highly recommended that the offeror number each page of the proposal. Proposal legibility, clarity, coherence, and contents are important.
3.2.5 Revised Proposal. Revised proposals will not be accepted unless specifically requested by the Contracting Officer. If the Contracting Officer decides to conduct discussions and requests revised proposals from the offerors; offerors shall ensure that all replacement pages are clearly marked “REVISED”, shall show the date of revision, shall be submitted in the appropriate number of copies (e.g., if two copies of the original page was required, then two copies of the revised page will also be required). All proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g. bold face print or underlining.
4.0 SUBMISSION AND EVALUATION CRITERIA
VOLUME I – TECHNICAL PROPOSAL (1 Original and 4 Copies)
FACTOR 1 – EXPERIENCE
a. Submission Requirements: Using Attachment A - Project Information Sheet, provide a detailed narrative that explains how each project included in Factor 1 – Experience, is similar to the work described in the solicitation
1. The Technical Proposal shall be bound, tabbed and in the order as shown in the table below. The Technical Proposal shall not contain any reference to cost for this project. The total pages submitted for the Technical Proposal shall not exceed sixty (60) pages. Each page should be numbered. Any pages over the prescribed limit will not be considered for evaluation. Do not include the front and back cover of the technical proposal in the sixty (60) page count.
Provide the original and four (4) hard copies of the Technical Proposal.
2. Provide the complete Volume I – Technical Proposal submittal, inclusive of text, renderings, drawings, photographs, etc. as PDF files and on CD (one copy). The CD should be marked with the offeror’s name, the solicitation number, and should be identified as the electronic copy of the Volume I - Technical Proposal. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one file using WinZip version 6.2 or later. Self extracting exe files will not be accepted. Electronic files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text.
3. In the event of any conflicts or differences between the original sealed offer and any paper copy or electronic (PDF) copy of the proposal, the sealed original offer shall control. The offeror is responsible for ensuring that all copies of the proposal, whether a paper copy or an electronic copy, is consistent with the original sealed offer.
The submittals should be formatted as follows:
Volume I – Technical
Tab Documents to be Included
Cover Sheet. Follow instructions in Paragraph (c)(2) in Section 00 21 00, 52.215- 1, Instruction to Offerors—Competitive Acquisition
Attachment A - Project Information Sheet. Submit one information sheet per project. Submit at least one but not more than three projects.
Attachment B – USACE Past Performance Questionnaire. Submit one sheet for each project submitted under Factor 1 – Experience.
4. Additional Submittal Instructions
i. Project Information Sheet (Attachment A) is included in this solicitation and provided for the offeror to submit for each project included for Factor 1, Experience. Submit one information sheet per project. Submit at least one (1) but not more than three (3) projects. Factor 1, Experience, sets forth project relevancy requirements
ii. USACE Past Performance Questionnaire (Attachment B) included in this solicitation is provided for the offeror to submit information for Factor 2, Past Performance. See Factor 2 for more information.
b. Evaluation Criteria: The Government will evaluate the offeror’s experience on recent and relevant projects.
1. This Factor evaluates the offeror’s experience. The Government will evaluate the experience an offeror displays on relevant projects. Projects not meeting all the relevancy criteria listed below will be considered not relevant for this factor evaluation. For purposes of evaluation of this Factor, a relevant project is a project that meets the following criteria:
i. Project was one of the following:
A. New construction, repair, or renovation of a Hydrant Fueling
System with a contract award value which equaled or exceeded ¥1,000,000;
B. New construction, repair, or renovation of a Fuel Offloading and Loading Facility with a contract award value which equaled or exceeded ¥1,000,000;
C. New construction of a pier with a contract award value which equaled or exceeded ¥500,000,000; OR
D. New construction of a wharf with a contract award value which equaled or exceeded ¥500,000,000;
ii. Project must be either currently well underway (at least 50% construction progress completed) or was completed and turned over no longer than ten (10) years preceding the issuance date of this solicitation; AND
iii. Project was performed by the Offeror as the prime contractor (see below notes).
Note (1):
The Government will also consider prime contractor experience of the offeror's parent/subsidiary/affiliate firm as experience attributable to the offeror for evaluation purposes if the offeror can establish that the parent/subsidiary/affiliate firm will have a significant involvement in performance of this contract and describe the resources of the parent/subsidiary/affiliate firm that will be utilized on project that is the subject of this procurement.
If submitting a parent/subsidiary/affiliate firm’s project for experience, it is the offeror's responsibility to effectively demonstrate and describe how the parent/subsidiary/affiliate firm's resources (such as workforce, management, facilities, or other resources) will significantly contribute to the execution of the project which is the subject of this procurement; failure to effectively demonstrate and describe the planned contribution of the parent/subsidiary/affiliate firm’s involvement in the subject project of this procurement will cause the past experience of the parent/subsidiary/affiliate firms to be considered not relevant for evaluation purposes in this procurement. Further, any project in which the parent/subsidiary/affiliate firm performed the role of a subcontractor will not be considered relevant when evaluating the experience of the offeror.
Note (2):
A Single Award Task Order Contract (SATOC) or Multiple Award Task Order Contract (MATOC) alone is not considered a relevant construction project, but an individual task order project against its SATOC or MATOC may be submitted if it meets the requirements for a relevant construction project set forth above.
Note (3):
(a) If a Joint Venture (JV) is identified in Block 14 of the SF 1442, then a signed joint venture agreement must be submitted with the proposal.
(b) If offeror identified in Block 14 is a JV, a project currently well underway (at least 50% construction progress completed) or completed by a JV may be submitted for purposes of demonstrating prime contractor experience, so long as at least one member of the offeror JV was a member of the JV on the project. Offeror must demonstrate evidence that at least one member of the offeror JV was a member of the JV on the project, such as a signed joint venture agreement or similar documentation.
(i) Example: Offeror for this solicitation is Joint Venture A-B. JV A-B is comprised of Company A and Company B. Past projects completed by JV A-C, comprised of Company A and Company C may be used to demonstrate prime contractor experience for this solicitation, as Company A, a member of the offeror JV, was a member of JV A-C.
(c) Projects currently well underway (at least 50% construction progress completed) or completed by a joint venture where the offeror was a member of the JV may be submitted for the purpose of demonstrating prime contractor experience. Offeror must demonstrate evidence of JV membership on the project, such as a signed joint venture agreement or similar documentation.
(i) Example: Offeror for this solicitation is Company A. Past projects currently well underway or completed by JV A-C, comprised of Company A and Company C may be used to demonstrate prime contractor experience for this solicitation, as Company A, the offeror, was a member of JV A-C.
(d) Projects currently well underway (at least 50% construction progress completed) or completed by a member of a joint venture for this solicitation (as demonstrated by a signed joint venture agreement for this effort) may be submitted for the purpose of demonstrating prime contractor experience.
(i) Example: Offeror for this solicitation is JV A-B. Past projects currently well underway or completed by Company A may be used to demonstrate prime contractor experience for this solicitation, as Company A is a member of the offeror JV A-B.
2. The minimum requirement for this evaluation factor has been met when the offeror demonstrates minimally acceptable construction experience through at least one (1) but not more than three (3) relevant construction projects. To be considered acceptable, relevant project(s) must demonstrate the proposal meets all of the below acceptability criteria:
i. Demonstrates experience in at least one (1) project for the new construction, repair, or renovation of either a Hydrant Fueling System or Fuel Offloading and Loading Facility; AND
ii. Demonstrates experience in at least one (1) project for the new construction of either a pier or a wharf.
3. Construction Experience will be rated on an “Acceptable” or “Unacceptable” basis using the ratings and descriptions shown below:
Acceptable – Proposal clearly meets the minimum requirements and indicates an adequate approach and understanding of the requirement.
Unacceptable – Proposal does not meet the requirements and contains one or more deficiencies and is unawardable.
FACTOR 2 – PAST PERFORMANCE
a. Submission Requirements: Each offeror’s past performance will be reviewed to determine relevancy and confidence assessment.
1. The Government will evaluate the relative merits of each Offeror’s past performance on the same relevant projects submitted and evaluated under Factor 1 – Experience. Please keep in mind that “Past Experience” measures “what you have done” while “Past Performance” measures “how well you have done it.” A completed Past Performance Questionnaire should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment B), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contacts listed below via email prior to proposal closing date and time.
Jiro Miyairi, E-mail: mailto:Jiro.Miyairi.ln@usace.army.mil Tristin N. Suetsugu, E-mail: Tristin.N.Suetsugu.civ@usace.army.mil
2. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
3. In addition to the above, the Government may review any other sources of information for evaluating past performance. Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS), including Contractor Performance Assessment Reporting System (CPARS), using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS) and any other known sources not provided by the offeror.
4. While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
b. Evaluation Criteria: The past performance evaluation is an assessment of the offeror’s probability of meeting the solicitation requirements. The past performance evaluation determines how relevant a recent effort accomplished by the offeror is to the effort to be acquired through the source selection. The evaluation also assesses the degree of confidence the Government has in an offeror’s ability to supply products and services that meet the user’s needs, based on a demonstrated record of performance. See FAR 15.305.
1. Past performance shall be evaluated for each offeror. Evaluation of past performance will be based upon consideration of all facts and circumstances. As a minimum, the offeror shall demonstrate overall satisfactory performance (to include a showing of adequate corrective action on adverse past performance information) on contracts that are of size and complexity similar to the requirements in the subject RFP. The Government will evaluate the breadth and depth of an offeror’s past performance on relevant projects. The Government will evaluate each offeror’s past performance to determine how well it conforms to specifications and standards of good workmanship, adheres to contract schedules including administrative aspects of the performance, exhibits reasonable and cooperative behavior and a commitment to customer satisfaction and has a businesslike concern for the interests of the customer. The Government may contact some of the offeror’s customers to determine whether the offeror conforms to the terms and conditions of its contract; obeys the law; is reasonable and cooperative; maintains good labor relations; manages its subcontractors effectively; and is committed to customer satisfaction.
2. The Government reserves the right to obtain or…