This document outlines requirements for a federal design-build contract to expand the Fort Jackson National Cemetery in Columbia, South Carolina. The solicitation seeks a contractor to design and construct additional gravesites, roads, drainage improvements, landscaping, and other site work. Key requirements include pre-placed crypt installation for 5,632 spaces, as well as additional in-ground cremation and traditional burial sites. The contractor must provide topographic surveys, geotechnical investigations, and demolition services. Additional specifications cover utilities installation, fencing, signage, and an irrigation system. The selected offeror will design the project in accordance with the scope and criteria outlined, including all federal, state, and local regulations. The Army Corps of Engineers Engineering District Charleston is the contracting agency.

View the file

Other files

File Type Posted
B.08.03 19R4000 Amendment 2 Spec Section 01 45 35 (edited 1.3.2020) 1-7-2019.pdf PDF
B.08.03 19R4000 Amendment 2 PrecastConcBurialCrypts 6.1.2013.doc DOC document
B.08.03 19R4000 Amendment 2 Appendix C (Sheet C-505) 1-6-2020.pdf PDF
B.08.03 19R4000 FINAL AMENDMENT 2 1-6-2020.pdf PDF
B.08.03 19R4000 Amendment 2 Tab L (Updated - 1.6.2020).pdf PDF
B.08.03 19R4000 Amendment 2 Water Analysis 1-6-2020.pdf PDF
B.08.03 19R4000 Amendment 2 Environmental Assessment for Cemetery 1-6-2020.pdf PDF
B.08.03 19R4000 Amendment 2 E-Mail Bidder Inquiries and Responses 1-6-2020.pdf PDF
B.08.03 19R4000 Amendment 2 Tab D (Updated - 1.6.2020).pdf PDF
B.08.03 19R4000 Amendment 1 Appendix C (Phase 2 Reference) 12-23-2019.pdf PDF
B.07.01 19R4000 Pre Proposal Site Visit Sign In Sheet 12-12-2019.pdf PDF
B.08.03 19R4000 Amendment 1 Spec Section 01 32 01.00 10 12-23-2019.pdf PDF
B.08.03 19R4000 Amendment 1 2 Wire Decoder Module 12-23-2019.jpg JPG image
B.08.03 19R4000 Amendment 1 12-23-2019.PDF PDF
B.08.03 19R4000 Amendment 1 Spec Section 01 45 00.00 10 12-23-2019.pdf PDF
B.08.03 19R4000 Amendment 1 Bidder Inquiry Responses 12-23-2019.pdf PDF
B.08.03 19R4000 Amendment 1 Precast Concrete Cyst Specs 12-23-2019.pdf PDF
B.08.03 19R4000 Amendment 1 Irrigation Controller 12-23-2019.jpg JPG image
B.08.03 19R4000 Amendment 1 07-437 GEO-REPORT 12-23-2019.PDF PDF
B.08.03 19R4000 Amendment 1 Pump controller 12-23-2019.jpg JPG image
B.08.03 19R4000 Amendment 1 Spec Section 01 45 35 12-23-2019.pdf PDF
A.02.16 19R4000 Appendix A 12-3-2019 .pdf PDF
B.08.02 19R4000 Final Released Solicitation 12-3-2019.pdf PDF
A.02.16 19R4000 Appendix D 12-3-2019 .pdf PDF
A.02.16 19R4000 Appendix E 12-3-2019 .pdf PDF
A.02.16 19R4000 Appendix F 12-3-2019 .pdf PDF
A.02.16 19R4000 Appendix B 12-3-2019 .pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

Charleston District 69A Hagood Avenue Charleston, SC 29403

RFP

Fort Jackson National Cemetery

Gravesite Expansion Phase II

Columbia, SC

September 18, 2019

FORT JACKSON NATIONAL CEMETERY GRAVESITE EXPANSION PHASE II

RFP TABLE OF CONTENTS

SPECIFICATIONS TABLE OF CONTENTS

01 10 00

Project Requirements 01 11 00 Summary of Work 01 14 00 Work Restrictions 01 30 00 Administrative Requirements 01 32 01.00 10 Project Schedule 01 33 00 Submittal Procedures 01 33 16 Design After Award

01 35 26 Governmental Safety Requirements

01 42 00 01 45 00.00 10 01 45 00.10 10 01 45 00.15 10 01 50 00 01 57 19 01 74 19 01 78 00 01 81 13 04 05 13 04 05 16 04 20 00 04 72 00 06 10 00 06 16 63 06 44 43

Sources for Reference Publications Quality Control Quality Control System (QCS) Resident Management System Contractor Mode (RMS CM) Temporary Construction Facilities and Controls Temporary Environmental Controls Construction and Demolition Waste Management Closeout Submittals Sustainable Construction Requirements Masonry Mortar Masonry Grouting Unit Masonry Cast Stone Masonry Rough Carpentry Cementitious Sheathing Polyester-Resin-Stone-Composite Columns

10 14 00 Signage

07 11 13 Bituminous Dampproofing 07 22 00 Roof & Deck Insulation 07 40 00 Roofing Siding Panels 07 60 00 Flashing Sheet Metal 07 92 00 Joint Sealants 08 11 13 Hollow Metal Doors and Frames 08 71 00 Door Hardware 09 06 00 Schedule of Finishes 09 39 00 Direct Applied Finish System (DEFS) 09 91 00 Painting

APPENDIX A: FORT JACKSON NATIONAL CEMETERY MASTER PLAN

APPENDIX B: FJNC PHASE II EXPANSION RFP DRAWINGS

APPENDIX C: FJNC PHASE 1 SITE RECORD DRAWINGS

APPENDIX D: QAR FINAL CRYPT INSPECTION CHECKLIST

APPENDIX E: CRYPT INSPECTION TRAINING SLIDES

APPENDIX F: TOPOGRAPHICAL SURVEY

NOTE:

Division 01 Specification Sections included in this RFP are provided as guidance to Offerors for direction concerning management and oversight of the awarded D-B contract by the U.S. Army Corps of Engineers, Charleston District, as the design and construction agent for the National Cemetery Administration (NCA). For the awarded contract, the D-B A-E will be required to include these specifications in their design package.

Division 02 and later Specification Sections included in this RFP are provided as a representation to Offerors of expected specifications and technical requirements that the awarded D-B A-E may use in the development of their design package. For the awarded contract, the D-B A-E should consider these specifications and technical requirements for inclusion in their design package, as well as any additional specifications necessary to support the D-B execution strategy.

Section 01 10 00 Page 1

Section 01 10 00

Project Requirements

1. GENERAL:

1.1. INTRODUCTION: The purpose of this project is to construct Phase II of the Fort Jackson National Cemetery (FJNC) as depicted on the Master Plan developed in 2009 and provided in Appendix A. This project will consist of the design and construction of the primary roads, service roads, committal service shelter, grading, drainage improvements, landscaping, irrigation system and well, NCA site furnishings (benches, vase and trash receptacles, and signage), and perimeter fencing as well as the installation of 5,632 pre-placed crypts (PPC). Other interment sites depicted on the RFP Drawings include accommodations for 2,376 in-ground cremains sites and 729 traditional burial sites.

1.2. TOPOGRAPHIC AND UTILITIES SURVEY: Topographic and utilities surveys are not provided in this RFP. See Appendix C for Site Record Drawings of Fort Jackson National Cemetery Phase 1. These are provided as reference only.

Contractor shall complete a topographic and utilities survey of the entire Phase II project area as part of the design effort.

1.3. SUBSURFACE GEOTECHNICAL INVESTIGATION: A subsurface geotechnical investigation is not provided with this RFP. Contractor shall complete a subsurface geotechnical investigation to support design efforts. Design and construction efforts shall be in accordance with the recommendations provided in the Geotechnical Report.

1.4. DEMOLITION & CLEARING: Prior to construction start, the areas identified on sheet C-0.1 “Timber Harvest Plan” of the RFP drawings will be cleared or thinned by the Fort Jackson forestry division. The contractor shall verify these limits during design and use caution during construction to preserve the areas of natural vegetation that are to remain. Tree protection shall be utilized to preserve these areas. The contractor shall grub out stumps, brush, and other vegetation within the project limits to facilitate grading of the site. Vegetation must be hauled off site to an approved disposal site. Burning will not be permitted onsite. The Contractor shall take the necessary precautions to avoid damages to existing items to remain in place, to be reused or to remain the property of the Cemetery. Any damaged items shall be repaired or replaced at the Contractor’s expense as directed by USACE.

The Contractor shall remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to USACE before it is disturbed. Materials and workmanship used in restoring work shall conform in type and quality of the original construction.

1.5. SITE CONTROLS & ACCESS: FJNC will remain operational during construction activities. The Contractor shall coordinate daily activities with the FJNC staff to ensure no disruption to Cemetery activities. The Contractor shall establish construction limits, install safety controls, and install

Section 01 10 00 Page 2 construction fencing to maintain construction site safety. The Contractor shall maintain and facilitate full access to the spoils area and maintenance building for FJNC staff. No construction access or traffic shall be permitted through the Cemetery and access shall be restricted to the FJNC Maintenance driveway on Percival Road. The Contractor shall coordinate with the Cemetery Director for parking, material storage, temporary portable restroom facilities and any other needs for the work. Public access to the National Cemetery shall not be impaired.

1.6. UTILITIES: The Contractor shall conduct a complete site investigation;

including utility locates, prior to start of work. The contractor shall exercise care with underground utilities, to avoid damage to government property and utility service interruption to occupied buildings and FJNC operations. This includes the irrigation systems and services. Damage to these utility services shall be repaired immediately at no additional cost to the Government.

1.7. LANDSCAPING: Detailed landscape planting specifications provided in the RFP drawings. All plants shall be warranted to remain alive, healthy and in a thriving condition for a period of one year from final acceptance.

Plants shall meet American Standard for Nursery Stock standards. Height and spread dimensions specified on the RFP drawings refer to the main body of the plan and not from branch tip to branch tip. If a range of size is given, no plant shall be as large as the maximum size specified. The Contractor shall also:

Place plants upright and turn so that the most attractive side is viewed

Install guy anchors on each tree to support during growth

Be responsible for the coordination and location of underground utilities before digging. The contractor will be fully responsible for the repair of damaged utility lines.

Provide shovel-cut trenches at shrub beds in lawn areas

Be responsible for landscape maintenance until date of final acceptance by Owner or Owner’s Representative

1.8. IRRIGATION: Contractor is responsible for providing a programmable, fully automatic system with full and complete coverage within the areas indicated on the RFP drawings and to the specifications and performance requirements provided on sheets I-1 through I-1.7 of the RFP drawings. Furnish all labor, materials, supplies, equipment, tools, and transportation to perform all operations in connection with and reasonably incidental to the complete installation of the fully functional irrigation system and well and warranty as shown on the RFP drawings, the installation details, and as specified. Other items of work specifically included in Contractors scope of work are:

Procurement of all applicable licenses, permits, and payment of required fees.

Section 01 10 00 Page 3

Coordination of Utility Locates ("Call Before You Dig").

Maintenance period services.

Sleeves for irrigation pipes and wires as indicated, and/or beneath all hardscape surfaces.

Connection of new irrigation system into existing irrigation central control system (including all required programming/reprogramming of the system).

Installation of New Irrigation Well and Well Pumping unit, including any required discharge water filtration/treatment. Irrigation well performance requirements provided on sheets I-1 through I-1.7 of the RFP drawings.

Contractor is responsible to coordinate construction of irrigation system with Owner’s Representative and FJNC Staff. Coordinate temporary shutdown of existing system with FJNC Staff prior to construction.

Disturbance to cemetery operations shall be minimized. See irrigation plans and installation details and Specifications Sections for required coordination efforts related to the installation of specific irrigation components.

Connections to the existing mainline must be approved by the Owner’s Representative while minimizing the impact on the operation of the existing irrigation system.

Install irrigation mainline, control, and power wiring in sleeves under new roads prior to installation of road base and under all other concrete or asphalt, either existing or new, for this project.

Irrigation components shall be installed in all landscaped areas unless specifically indicated otherwise. Irrigation components in other than landscaped areas shall be placed in PVC pipe sleeves, with no joints beneath the non-landscaped areas, unless otherwise noted on plans.

Construction cannot proceed unless staking of irrigation mainline, remote control valve locations, and sprinkler locations are reviewed and accepted by the Owner’s Representative.

The irrigation well shall be a prefabricated well pump unit. The detailed specifications are identified on sheet I-1.7 of the RFP drawings.

1.9. MASTER PLAN AND SIGNAGE: Cemetery signage and wayfinding signage shall be designed and built to be consistent with existing FJNC signage and in accordance with the VA Signage Design Guide for National Cemetery Signs.

The Contractor shall update the master plan provided in Appendix A to reflect the final Phase 2 gravesite expansion site layout. The master plan shall be developed through coordination with FJNC staff as this will replace the overall public wayfinding sign in the FJNC administrative office.

1.10. DESIGN SUBMITTALS: This is a Design Build project. Provide design submittals in accordance with Section 01 33 16 Design After Award.

Section 01 10 00 Page 4

1.11. AS-BUILT DRAWINGS: Contractor shall provide As-built drawings.

See specification 01 78 00 CLOSEOUT SUBMITTALS.

1.12. ENVIRONMENTAL: Provide stormwater and erosion control and pollution prevention measures as required by federal, state and local authorities.

1.12.1. HAZARDOUS MATERIALS: A Hazardous materials survey is not included in this RFP. Because this is new construction, the contractor is not expected to encounter hazardous materials.

The area of the project limits as defined in the RFP documents has previously been surveyed and cleared of Unexploded Ordinances (UXO) by a separate contractor.

1.13. EXISTING CONDITIONS: The contractor shall field verify all conditions prior to the start of work, including locating all utilities within the work area. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs and grass) on or adjacent to the work site not to be removed and do not reasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by USACE.

1.14. ENVIRONMENTAL PERMITS: The contractor is responsible for obtaining all permits.

1.15. OCCUPIED FACILITIES: FJNC will remain operational and in use while work is underway. The contractor shall avoid interruption of daily operations at the areas of work to the maximum extent possible.

2. CRITERIA: Design and Construction shall be completed in accordance with the following list of criteria.

1. Current American with Disabilities Act (ADA) requirements

2. Life Safety Code, NFPA 101

3. PG 18-13 VA Barrier Free Design Standard

4. International Code Council (ICC)

5. American National Standards Institute (ANSI)

6. ASTM International

7. American Nursery and Landscape Association (ANLA), American Standard for Nursery Stock (latest addition)

8. VA Program Guide PG-18-3, Topic 1 - Codes, Standards and Executive Orders

(September 2013) www.cfm.va.gov/til/cPro.asp

9. VA Program Guide PG-18-3, Topic 4 - Foundation Drainage (April 2001) www.cfm.va.gov/til/cPro.asp

Section 01 10 00 Page 5

10. VA Program Guide PG-18-3, Topic 16 - Sustainable Buildings Policy for VA Renovation and New Construction (May 2006) www.cfm.va.gov/til/cPro.asp

11. VA Sustainable Design Manual (May 2014) http://www.cfm.va.gov/til/sustain/dmSustain.pdf

12. Green Globes-New Construction http://www.cfm.va.gov/til/sustain/GPChecklist-GG-NC.docx

13. VA Design and Construction Criteria, NCA Specific Criteria and Specifications http://www.cfm.va.gov/til/nca.asp

14. VA PG 18-15 Volume D A/E Submission Requirements for National Cemetery

Projects as applicable to design portion of D/B contract. Use VA PG 18-15 Volume D as a general guide; see Section 8.0 on this SOW for the required deliverables on this project.

http://www.cfm.va.gov/til/ae/aesubcem/

15. National Cemetery Signs. VA Signage Design Guide Section 12 (December

2012) http://www.cfm.va.gov/til/signs/Signage12-Cemetery.pdf

2.1. Gravesite Standards:

Traditional Burial Sites – the 1800 mm x 3000 mm (6' x 10') gravesite will be used for single depth side-by-side interments where excavation below 1500 mm (5') is impractical due to soil conditions.

Pre-placed Crypts – the 900 mm x 2400 mm (3' x 8') gravesite will be used in the pre-placed lawn crypt sections. Lawn crypts are pre-placed concrete containers with removable concrete lids which are installed at the time of land development. Crypts are installed by excavating the burial area and preparing it to provide adequate drainage. Pre-cast crypts are then placed adjacent to one another and abutting on another.

Designated Cremains Sections – a 4’x4’x ±2’ deep gravesite with upright granite markers to match existing FJNC cremains sections will be used.

2.2. Building Code:

International Building Code, as adopted by UFC 1-200-01

2.3. Unified Facilities Criteria

UFC 1-200-01 General Building Requirements

UFC 3-201-01 Civil Engineering

UFC 3-220-01 Geotechnical Engineering

UFC 3-301-01 Structural Engineering

UFC 3-501-01 Electrical Engineering

UFC 3-550-01 Exterior Electrical Power Distribution System

Section 01 10 00 Page 6

3. FJNC Phase II Expansion SITE:

3.1. DEMOLITION and SITE WORK

Provide site work as needed to prepare for the Gravesite Expansion, including clearing/grubbing of stumps and shrubs, grading, roads, drainage systems, landscaping, and irrigation.

Grading and earthwork specifications, compaction, and testing shall be in accordance with the criteria set forth in the Geotechnical Report.

The Contractor shall provide documentation and reports that all earthwork was tested and completed in accordance with the specifications and criteria set forth in the Geotechnical Report.

Modify existing fences and provide new fencing as indicated on the RFP drawings to provide security for the Phase II Expansion site and UXO clearance area.

Provide all work necessary to create construction access as needed.

See Appendix A for RFP Drawings

3.2. UTILITIES: Provide electrical and communications for the irrigation well, controller, and the committal shelter. Electrical and Communications shall be run below ground.

ELECTRICAL: Provide electrical power service for irrigation well and committal shelter.

3.2.1. Irrigation Well requires three phase, 460 VAC power with a 400 AMP circuit.

3.2.2. Irrigation Controller requires single phase, 120 VAC power with a 20 AMP circuit.

3.2.3. Provide power for the committal shelter.

3.2.4. Power is available from the transformer near the FJNC

maintenance building.

SECURITY AND TELLECOMMUNICATIONS: Not Applicable

3.3. CONCRETE SLAB: Provide a new concrete slab. Provide concrete sidewalk from new concrete slab to new roadway. See Appendix A and B.

Slab shall be nominally 20’ x 54’. Sidewalk shall be nominally 8’-0” wide around the committal shelter.

Slab shall be level with sufficient crown to prevent standing water.

Top of slab elevation shall be higher than surrounding grade. The site

Section 01 10 00 Page 7 is located in the sheet flow area downstream of a large paved area. Slab elevation shall be located above surrounding sheet flow. Use topographic survey data to determine proper elevation.

Surrounding grade shall slope away from slab.

Top of slab shall be a minimum of 6” above surrounding grade.

3.4. STRUCTURAL: Provide complete structural system, including slab and foundation that meet the requirements of this project.

LOADS: The structure shall be able to support itself and additional loads provided in UFC 3-301-01.

FOUNDATION: Provide as needed to support committal shelter and asphalt pavement.

A. GEOTECHNICAL INFORMATION: The Contractor shall perform a soils investigation at the site for use in the design and construction of the new shelter and pavements. A report including laboratory analysis of samples and recommendations for foundation and slab design shall be prepared by a professional engineer registered in the state of Indiana and familiar with subsurface conditions in the area.

3.5. FENCING: Provide security fencing as depicted on the RFP drawings for the Phase II Expansion and UXO clearance areas. Perimeter security fencing shall be 6’ high galvanized or vinyl coated. Permanent FJNC perimeter fencing shall be black, vinyl coated and temporary perimeter fencing for UXO clearance delineation shall be galvanized. Interior screening fence shall be 6’ high vinyl coated. See RFP Drawings for locations and typical fence details.

3.6. LIGHTING: Not Applicable.

3.7. PPC INSTALLATION: Contractor shall unload, inspect, and install Contractor-Furnished pre-cast crypts. Installation shall include numbering and leveling of each PPC in accordance with NCA requirements.

Jobsite inspections shall be performed upon delivery and after placement of the pre-cast crypts in accordance with the criteria outlined in the Crypt Inspection Training Slides provided in Appendix F.

END OF SECTION

Section 01 11 00 Page 1

SECTION 01 11 00

PART 1 GENERAL

1.1 SUBMITTALS

SUMMARY OF WORK

08/15

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes the design and construction of the Phase II expansion at Fort Jackson National Cemetery to accommodate for additional pre-placed crypts, in-ground cremains, and traditional burial sites. The project shall result in complete and useable facilities including all site work, PPC installation, paving, drainage, landscaping, irrigation and incidental related work. All work will be designed and constructed in conformance with the RFP Documents.

1.2.2 Location

The work is located at Fort Jackson National Cemetery, Columbia, SC. The exact location is illustrated in the RFP drawings.

1.3 OCCUPANCY OF PREMISES

The project site area consists of primarily wooded and unoccupied land.

The existing service road on the north side of the project provides access to the spoils area and FJNC maintenance building. FJNC will continue to use this road throughout the duration of this project and the road should remain accessible during construction.

Before work is started, the Contractor shall arrange with the Contracting Officer's Representative (COR) a sequence of procedure, means of access, and space for storage of materials and equipment. Construction access will be limited to the maintenance driveway off Percival Road and no access will be permitted through the existing cemetery.

The Contractor shall plan all work to minimize impact to the normal operation of the cemetery, its staff, and mission. The contractor shall be responsible for all temporary provisions necessary to meet this requirement, including but not limited to access to existing buildings, roads, and public access to burial sites. All provisions are subject to the approval of the COR and FJNC.

Section 01 11 00 Page 2

1.4 SPECIAL SCHEDULING REQUIREMENTS

The contractor shall cooperate and coordinate with the Cemetery Director, through the COR, in arranging the construction schedule to cause the least possible interference with Cemetery activities. Construction noise during committal services shall not disturb the service. Trucks, workmen, and equipment shall not pass through the cemetery at any time.

Unless otherwise specified in the contract documents, the contractor shall only be allowed to complete work in the project construction area. A construction route will be provided to allow access to the spoils area for the disposal of excess soil from excavation.

Contractor shall lead a coordination meeting with all existing occupants of the cemetery’s facilities and if applicable, other Government contractor's working at the cemetery to de-conflict the planned work area access with that of the occupants and to synchronize his work efforts with that of other Government contractors. The intent is that each occupant is able to continue work and the cemetery will be able to continue to run as normal during construction activity. There may be more than one unit/organization at the cemetery facilities, so coordination to minimize impact on their operations is paramount.

Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

FJNC will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of activity.

Permission to interrupt any activity roads and/or utility service shall be requested in writing a minimum of 14 calendar days prior to the desired date of interruption.

Request utility and facility system outages in accordance with 01 30 00

ADMINISTRATIVE REQUIREMENTS.

1.5 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the COR. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

Section 01 11 00 Page 3

1.6 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 72 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

1.6.1 Notification Prior to Excavation

Notify the Contracting Officer at least 72 hours prior to starting excavation work.

1.7 NOT USED

PART 2 PRODUCTS

NOT USED.

PART 3 EXECUTION

NOT USED.

-- End of Section --

SECTION 01 14 00 Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 SPECIAL SCHEDULING REQUIREMENTS

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

1.4.1.1 Subcontractors and Personnel Contacts

1.4.1.2 No Smoking Policy

1.4.2 Working Hours

1.4.3 Work Outside Regular Hours

1.4.4 Occupied Buildings

1.4.5Utility Cutovers and Interruptions

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 14 00 Page 2

SECTION 01 14 00 WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. Code (USC)

10 USC 6011 Navy Regulations

8 USC 1101 Definitions

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G

1.3 SPECIAL SCHEDULING REQUIREMENTS

a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.

b. The cemetery will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

c. Permission to interrupt any activity roads and/or utility service shall be requested in writing a minimum of 14 calendar days prior to the desired date of interruption.

1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize cemetery inference, delivery of materials shall be restricted to the FJNC maintenance driveway unless otherwise approved by the COR. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.

Mark Contractor equipment for identification.

SECTION 01 14 00 Page 3

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 No Smoking Policy

Smoking is prohibited on cemetery grounds, except in designated smoking areas. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The COR will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours consist of a 10-hour period established by the COR, between 7 a.m. and 5 p.m., Monday through Friday, and 7 a.m. to 11 p.m. on Saturday, excluding Government holidays. All work must be coordinated and scheduled with the Fort Jackson National Cemetery (FJNC) ceremonial schedule. Areas requiring access around the site during ceremonies will be cleaned, adequately signed, and equipment and materials removed. Where work is on-going, provide adequate barriers, temporary fencing or other devices as needed for the unit to access all areas of the Center. While the FJNC ceremonial schedule will have priority, the FJNC will make all efforts to minimize or eliminate impact to the construction schedule.

1.4.3 Occupied Premises

The Contractor shall be working around existing buildings and an adjacent cemetery. Do not enter any buildings or the adjacent cemetery area without prior approval of the COR.

The existing buildings and their contents and the adjacent cemetery area must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the COR.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the adjacent areas during the construction period.

1.4.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph 1.4.3 WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and are considered utility cutovers pursuant to the requirements of paragraph 1.4.3 WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation.

SECTION 01 14 00 Page 4

d. Operation of Facility Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the COR, giving reasonable advance notice when such operation is required.

PART 2 PRODUCTS

Not Used

Not Used

Section 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

02/10

PART 1 GENERAL

1.1 Not Applicable

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Utility Outage Requests; G

Utility Connection Requests; G

Excavation Permits; G

Progress and completion pictures; G

List of contact personnel; G

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations and Security Requirements

It should be recognized that requirements for security and Fort Jackson National Cemetery (FJNC) access may vary depending on current security settings. It is incumbent on the Contractor to ascertain the current security and access requirements appropriate to the project location and incorporate the cost, if any, for compliance to said requirements into Contractor's proposal. Lack of knowledge of current requirements does not constitute a basis for an adjustment to the contract.

Ensure that Contractor personnel employed on the project site or Activity become familiar with and obey all local and Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats and required Personal Protective Equipment (PPE)in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.

The Contractor's equipment shall be conspicuously marked for identification.

Contract Clause "FAR 52.204-2, Security Requirements and Alternate II" and the following apply.

a. Restrict employees/representatives to the work site and control travel directly to and from the work site.

b. Restore all traffic/parking/security signs and markings, including space numbers, designations, and lines, to their original form if such signs/markings are defaced or deleted during construction/repair.

Section 01 30 00 Page 2

c. Be responsible for control and security of Contractor-owned equipment and materials at the work site. Report immediately missing/lost/stolen property to the COR and the FJNC staff as each case occurs.

d. Not used

e. Ensure that no opening in the fence along the cemetery’s property line exists at the end of the work-day and do not exist where penetration is possible during non-working hours. If the site cannot be secured at the end of the workday, coordinate action with the COR to notify FJNC to arrange for a security watch by their personnel.

f. Seventy-two (72) hours prior to making any penetrations (such as cutting through a fence) in a restricted area, contact the Security Office to make arrangements for a security guard or other measures required to meet all security requirements. Cost of security guard will be charged to the Contractor.

1.3.1.1 Identification Badges and Installation Access

Government issued Identification badges, if required, will be furnished without charge. Application for and use of badges will be as directed.

Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/files/form/i-9.pdf. Immediately report instances of lost or stolen badges to the COR.

If Government issued badges are not available or required at the project site or Activity, the Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the work to display, identification as approved and directed by the COR. Prescribed identification shall immediately be delivered to the COR for cancellation upon release of any employee. When required, the Contractor shall obtain and provide fingerprints of persons employed on the project. Contractor and subcontractor personnel shall wear visible Contractor-furnished employee identification badges while physically on FJNC property. Each badge shall include, as a minimum, the company name, employee name, photograph, Contract Title, Contract number, and the expiration date of the badge. Contractor personnel shall clearly identify themselves to all attendees as a contractor employee before the commencement of meetings with Government of other contractor personnel.

1.3.1.2 Personnel Entry Approval

Failure to obtain entry approval will not affect the contract price or time of completion.

1.3.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installations under the cognizance of the Fort Jackson National Cemetery except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The COR will identify designated smoking areas.

Section 01 30 00 Page 3

1.3.3 Working Hours

Regular working hours shall consist of a 10-hour period established by the Contractor Officer, Monday through Friday, excluding Government holidays.

1.3.4 Work Outside Regular Hours

Work outside regular working hours requires COR approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the COR may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the COR.

1.3.5 Occupied and Existing Buildings

The Contractor shall be working around existing buildings and an adjacent cemetery. Do not enter any buildings or the adjacent cemetery area without prior approval of the COR.

The existing buildings and their contents and the adjacent cemetery area must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the COR.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the adjacent areas during the construction period.

Relocate movable furniture and equipment away from the Contractor's working area as required to perform the work, protect the furniture, and replace the furniture in its original location upon completion of the work. Leave attached equipment in place, and protect it against damage, or temporarily disconnect, relocate, protect, and reinstall it at the completion of the work.

The Government may remove and relocate other Government property in the areas of the site scheduled to receive work. Any property that remains shall be handled as stated above

1.3.6 Restrictions on use of Camouflage Clothing

Contractor and subcontractor personnel shall not wear camouflage clothing in order to avoid confusion with military personnel.

1.3.7 Subcontractors and Personnel Contacts

Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur an dadditional information becomes available, correct and change the information contained in previous lists.

Section 01 30 00 Page 4

1.3.8 Emergency Response Requirement

The Fort Jackson National Cemetery (FJNC) has a requirement for all personnel to take shelter for personal safety in the event of certain emergencies. This policy includes Contractors, Subcontractors, and any person who is employed by the Contractor.

a. NOTIFICATION: The primary means of alerting personnel shall be through public address announcement system of the building. The notification for "all clear" shall be through direct communication by the Center Commander or their designated representative.

b. SHELTERING: When personnel hear the alert signal, the area of work must be secured in a manner that will leave the site in safe condition.

Personnel shall seek shelter in the nearest occupied building in calm and orderly manner. If possible, secure all windows and doors and shut off ventilation. If working aboard ship, proceed into the interior of the ship and wait for further directions from official personnel. If in a vehicle, park the vehicle so that it does not block the normally traveled portion of the road and proceed into the nearest occupied building.

c. EVACUATION: In the event of an evacuation, personnel shall receive directions from the Center Commander or their designated representative. Contract personnel shall comply with instructions given at all times.

1.3.9 Areas Not Covered by Contract

Contractor personnel will not be permitted to enter any area currently, or during a phase of the contract, designated as an 'off limits area', except on prior approval of the COR. Coordinate action with the COR to obtain such entry approval.

1.3.10 Access to Unclassified Information

Access to unclassified U.S. military technology and related technical information manuals, documents, drawings, plans, specifications, and other unclassified information is restricted to official need-to-know basis, designated by physical markings to show the appropriate control designations. Handle, control, and safeguard to prevent oral, visual, and documentary disclosure to the public, to foreign sources, and to personnel not having an official need-to-know. Return this information to the COR upon completion of contracted work, except when specific retention authorization is granted by the COR.

1.3.11 Photographs

Unofficial photography is prohibited at the project site except as required by these contract specifications. When operationally required, submit a written request containing specific justification and details to the COR prior to release.

1.3.12 Utility Cutovers and Interruptions: Not Used

Section 01 30 00 Page 5

1.4 ON-SITE REQUESTS AND PERMITS

1.4.1 Utility Outage Requests and Utility Connection Requests

Work shall be scheduled to hold outages to a minimum. Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the Government and shall be scheduled as directed by the COR. Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.

Requests for utility outages and connections shall be made in writing to the COR at least 15 calendar days in advance of the time required. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.4.2 Excavation Permits

ACTIVITY SUBMISSION DATE SUBMISSION FORM

Excavation Permits 14 calendar days prior to work Varies

Notify the COR at least 14 calendar days prior to starting excavation work and submit an excavation permit request on the form required by the local utility locating authority and if applicable, the installation utility provider(s). Contractor is responsible for requesting excavation permits, providing utility location markings, and verify all marked and resolve unmarked utilities prior to excavation. In addition to notifying the COR, the contractor shall contact local utility locating authority(ies) or as directed by the COR to request and receive excavation permits.

The Government will not perform on-site identification for Natural Gas, Stormwater, or the Electric Utilities. The Contractor is responsible and will verify the existence of all "utilities" in the area. The Government will not mark or identify any utilities. This is the sole responsibility of the contractor seeking the excavation/digging permit.

The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed, but indicated in locations to be transversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made. Mark the elevations of all exposed utilities on the As-built Record Drawings.

Excavation Permits shall be posted at a conspicuous location in the construction area.

1.5 UTILITY COORDINATION

Any existing utility that presents a conflict with the construction of the proposed expansion shall be brought to the attention of the utility owner. The Contractor is responsible for resolving the conflict as needed in order to construct the proposed improvements of this project.

Prior to the start of construction, the Contractor shall conduct a utility coordination meeting with the COR, utility owner, other

Section 01 30 00 Page 6 contractors working concurrently within the Complex, and the facility manager. The Contractor shall use the coordination meetings to identify utility lines impacted by project construction and verify working status of the existing lines. The Contractor shall coordinate the proposed work on impacted utility lines with the appropriate utility owner. Utility impacts to be coordinated shall include, but are not limited to: removals, temporary service then removal, and permanent relocations, where applicable.

1.6 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 3 Megapixels minimum resolution in JPEG file format with date stamp on photo showing the sequence and progress of work.

Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of 10 views from points located by the COR. Submit with the monthly invoice two sets of digital photographs each set on a separate CD-R/DVD-R, cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Photographs for each month shall be in a separate monthly directory and each file shall be named to indicate its location and/or work portrayed. All file names shall include a date designator. Photographs shall be provided for unrestricted use by the Government.

1.7 MINIMUM INSURANCE REQUIREMENTS

Unless larger minimum limits are otherwise specified in contract clauses and pursuant to FAR 28.307-2, the Contractor shall procure and maintain during the entire period of his/her performance under this contract the following minimum insurance:

a. Workers' compensation and employers' liability insurance in compliance with applicable state statutes, with a minimum employers' liability coverage of $100,000.

b. Comprehensive general liability insurance for bodily injury in the minimum limits of $500,000 per occurrence.

c. Comprehensive automobile liability insurance covering the operation of all automobiles used in connection with the performance of the contract in the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrences for property damage (FAR Clause 52.228-5 Insurance-Work on a Government Installation).

1.8 PRECONSTRUCTION CONFERENCE

After award of the contract, but prior to commencement of any work at the site, meet with the COR to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the project schedule, shop drawings, and other submittals, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work shall also attend.

Section 01 30 00 Page 7

1.9 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the USACE Charleston District, the FJNC (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process.

The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

1.10 AVAILABILITY OF CADD DRAWING FILES

If drawings provided in the Scope of Work were prepared solely for this referenced project in CADD and are available to the COR, the following applies:

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CADD drawing files are not construction documents.

Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between any signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

Section 01 30 00 Page 8

1.11 CONTRACTOR VERIFICATION OF CONTRACT SURVEY DATA

During initial site layout and before existing conditions are disturbed the Contractor shall verify, in writing, the basic survey data provided on the contract drawings. Verification shall be initiated from the point shown on the contract drawings or from the contract drawing reference point designated by the COR and shall include, as a minimum, benchmark elevations, horizontal control points, and sufficient spot checks of critical elevations to ensure that the survey data adequately reflects existing conditions. The Contractor shall not proceed with construction until survey verification is provided to the COR. Before an existing benchmark referenced on the contract drawings is disturbed the Contractor shall establish a new benchmark which has been approved by the COR.

Benchmarks which are destroyed without authorization from the COR must be replaced at the Contractor's expense, as prescribed in FAR Clause 52.236-17, Layout of Work. The Contractor shall refer to FAR Clauses 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigation and Conditions Affecting the Work, for additional requirements.

Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1.12 ELECTRONIC MAIL…