A.02.16 19R4000 Appendix D 12-3-2019 .pdf
PDF 168 KB Posted
- Attached to
- Ft. Jackson Cemetery Expansion Federal contract opportunity
- Solicitation number
- W912HP19R4000
About this file
This document contains a checklist for final crypt inspection at Fort Jackson National Cemetery in Columbia, South Carolina. The checklist includes verifying grid markers, storm line inlets, cleanouts, crypt numbering, irrigation system functionality, sod establishment, tree and shrub planting, delivery of maintenance manuals and as-built drawings, site furnishings, hydrant equipment, and signage installation.
The related federal contract opportunity is solicitation number W912HP19R4000 for the Fort Jackson Cemetery Expansion project. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Charleston for expanding burial crypt capacity at Fort Jackson National Cemetery.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FORT JACKSON NATIONAL CEMETERY GRAVESITE EXPANSION PHASE II
Columbia, SC
Appendix D
QAR Final Crypt Inspection Checklist
FORT JACKSON NATIONAL CEMETERY GRAVESITE EXPANSION PHASE II
Columbia, SC
Appendix E Page 1 of 1
CHECKLIST FOR FINAL INSPECTION
For
CRYPT PROJECTS
• Verify grid markers have survey crosshairs. Measure at random from crosshairs to crosshairs to verify design distances.
• Verify each storm line inlet is installed per drawings.
• Verify each cleanout is installed per drawing.
• Randomly verify that a crypt number is numbered correctly.
• Test each irrigation zone. Ensure each throws over the headstone. Ensure each head is installed per detail.
• Verify each irrigation box. Ensure water-proof plastic protector is installed at terminations.
• Verify sod is established and green.
• Inspect each tree or shrub to ensure they are lively, and planted per plant detail.
• Ensure maintenance manuals are delivered.
• Ensure As-built drawings are delivered.
• Ensure 20 lids, 3 lid lifting devices, 3 shelf lifting devices are delivered per specifications.
• Verify vase stations (site furnishings) are installed per drawings. Is laminar flow device installed on each hydrant? Is flower vase regulation labeled per approved submittal?
• Verify signage is installed per drawings.