This document provides details for a federal contract opportunity to construct the Baumholder Army Lodge in Germany. The U.S. Army Corps of Engineers seeks to award a firm-fixed-price design-bid-build construction contract valued between $40-70 million. The scope of work includes building a 78-unit Army lodging facility, reception areas, fitness room, offices, and supporting site utilities and improvements. The performance period is approximately 1,100 calendar days from notice to proceed. The solicitation will be available for download on the System for Award Management website and is unrestricted with no set-aside requirements due to the overseas location. Interested offerors should monitor the website for additional details or amendments. The primary points of contact are the listed contracting personnel.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS IS A REQUEST FOR PROPOSAL (RFP) FOR THE CONSTRUCTION OF A NEW ARMY LODGING FACILITY AT THE UNITED STATES ARMY
GARRISON (USAG) RHEINLAND-PFALZ, BAUMHOLDER MILITARY COMMUNITY, GERMANY.
THE GOVERNMENT CONTEMPLATES THAT THIS SOLICITATION WILL RESULT IN SINGLE FIRM FIXED-PRICE DESIGN BID-BUILD CONTRACT
AWARD USING A BEST VALUE TRADE-OFF ACQUISITION METHOD.
A. The estimated Magnitude of Construction is betw een $40,000,000 and $70,000,000.
B. This RFP is solicited under full and open competition (unrestricted).
C. Aw ard of this contract w ill be made in Euro (EUR).
PHILLIP C GARRISON 3145702982
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
24-Feb-2023
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______7 calendar days and complete it w ithin ________1095 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________FAR 52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________05 May 2023 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
10:00 AM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912GB23R0025 57
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912GB23R0025
Section SF 30 - Block 14 Continuation Page (SF 30)
AMENDMENT 0001
The Purpose of this amendment is as follows.
1. Update Life Safety Drawings.
2. Add clause 52.232-27 Prompt Payment for Construction Contracts
3. Extend date for Projnet submissions to 28 March 2023 at 1500 CET.
4. Revise section 00 21 16. Changes are in blue text.
AMENDMENT 0003
The Purpose of amendment 0003 is to provide the following udated drawing/specifications..
BHLODGE_00_GENERAL_R1
1. G002
2. G003
3. G004
BHLODGE_01_LIFE SAFETY_R1
1. GI001
2. GI011
BHLODGE_01_CIVIL_R1
1. CU101
2. CU102
3. CU103
4. CU121
5. CU202
6. CU502
7. CU503
8. CU504
9. CU505
10. CU506
11. CU507
BHLODGE_04_ARCHITECTURE_R1
1. A501
2. A503
3. AE465
4. AE601
5. AF601
6. AF602
BHLODGE_06_MECHANICAL_R1
1. MI506
BHLODGE_08_ELECTRICAL_R1
1. E002
2. EL111
3. EL121
4. EL122
5. EL131
6. EL132
7. EL141
8. EL142
9. EL501
10. EL601
11. EL602
BHLODGE_09_TELECOM_R1
1. TS501
IFC_BH Lodge_Specs
1. 01 22 00 PRICE AND PAYMENT PROCEDURES
2. 01 22 00_Att1_ Price Schedule
3. 01 33 00 SUBMITTAL PROCEDURES
4. 01 45 05 CONTRACTOR PERSONNEL REQUIREMENTS
5. 09023 09023 PLASTERING and STUCCO WORK, THERMAL INSULATION SYSTEMS / PUTZ-
UND STUCKARBEITEN, WÄRMEDÄMMSYSTEME
6. 09036A FLOORING WORK / BODENBELAGARBEITEN
7. 09039 DRYWALL WORK / TROCKENBAUARBEUTEN
8. 32003 LANDSCAPING / LANDSCHAFTSBAUARBEITEN
9. 32004 LANDSCAPING - PLANTS / LANDSCHAFTSBAUARBEITEN - PFLANZEN
10. 32080 STREETS, PATHS, & PLAZAS / STRASSEN, WEGE, PLAETZE
11. 33009 DRAINAGE SEWER WORKS / ENTWÄSSERUNGSKANALARBEITEN
12. 34003A ANTI-TERRORISM FORCE PROTECTION - CRASH RATED ACTIVE VEHICLE BARRIERS
AND CONTROLS / FAHRZEUGBARRIEREN UND - STEUERUNGEN
13. 34003B ANTI-TERRORISM FORCE PROTECTION - AUTOMATED BARRIER GATE /
ELEKTRISCH ANGETRIEBENES AUTOMATISIERTES SCHRANKENTOR
14. 34003D MANUAL ARM BARRIER
Section 00 01 10 - Table of Contents
TABLE OF CONTENTS
SECTION: 00 01 00 – Table of Contents/Attachments SECTION: 00 10 00 – Solicitation SECTION: 00 21 16 – Instructions to Proposers SECTION: 00 45 00 – Representations and Certifications SECTION: 00 70 00 – Conditions of the Contract SECTION: 00 72 00 – General Conditions SECTION: 00 73 00 – Supplementary Conditions
Section 00 01 10 – Attachments
1. Past Performance Info Sheet
2. Past Performance Questionnaire
3. Commitment Letter Sample
4. BLA Template
5. BLG Template
6. Bidding Schedule
7. Corrected100pct_BH Lodge Specs
00 74 01 – SPECIAL CONDITIONS 10/21
00 74 02 – TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER 10/21
00 74 05 – NON UFGS TECHNICAL SPECIFICATIONS (NAU) 10/21
00 74 10 – SUPPLEMENTAL CONDITIONS FOR PROJECTS IN GERMANY 12/21
00 74 70 – ANTI-TERRORISM / OPERATIONS SECURITY REQUIREMENTS 06/22
01 11 00 – SUMMARY OF WORK 10/21
01 22 00 – PRICE AND PAYMENT PROCEDURES 05/22
01 30 01 – GENERAL REQUIREMENTS 10/21
01 32 01 – PROJECT SCHEDULE 05/22
01 33 00 – SUBMITTAL PROCEDURES 10/21
01 33 29 – SUSTAINABILITY REQUIREMENTS AND REPORTING 02/21
01 35 26 – SAFETY REQUIREMENTS 10/21
01 42 00 – SOURCES FOR REFERENCE PUBLICATIONS 10/21
01 45 00 – QUALITY CONTROL 10/21
01 45 01 – RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) 10/21
01 45 05 – CONTRACTOR PERSONNEL REQUIREMENTS 11/21
01 45 35 – SPECIAL INSPECTIONS 10/21
01 60 00 – COMPARABLE PRODUCT REQUIREMENTS 10/21
01 78 00 – CLOSEOUT PROCEDURES 10/21
01 78 23 – OPERATION AND MAINTENANCE DATA 10/21
01 91 00.15 10 – TOTAL BUILDING COMMISSIONING 05/19
8. BH Lodge Submittal Register
9. Drawings – General
10. Drawings – Life Safety
11. Drawings – Civil
12. Drawings – Structural
13. Drawings – Architectural
14. Drawings – Fire Protection
15. Drawings – Mechanical
16. Drawings – Plumbing
17. Drawings – Electrical
18. Drawings – Telcom
Section 00 10 00 - Solicitation
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Primary Facilities
FFP
FOB: Destination
PSC CD: Y1JZ
NET AMT
Site work
FFP
0002AA 1 Job Site Work inside the 5-foot line – NAF
FFP
0002AB 1 Job Site Work outside the 5-foot line – DPW
FFP
German Government Charge
FFP
0003AA 1 Job German Government Charge - NAF
FFP
0003AB 1 Job German Government Charge - DPW
FFP
0004 1 Job OPTION Option 1: Playground
FFP
The Government reserves the right to award the options up to 90 calendar days from contact award.
0005 1 Job OPTION Option 2: Commercial Laundry Equipment
FFP
The Government reserves the right to award the options up to 90 calendar days from contact award.
0006 1 Job OPTION Option 3: Prep Kitchen/Dining Equipment
FFP
The Government reserves the right to award the options up to 90 calendar days from contact award.
0007 1 Job OPTION Option 4: Kitchenettes
FFP
The Government reserves the right to award the options up to 90 calendar days from contact award.
0008 1 Job OPTION Option 5: Parking PV Carport
FFP
The Government reserves the right to award the options up to 90 calendar days from contact award.
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 1095 dys. ANP 1 U.S. ARMY CORPS OF ENGINEERS, EUROPE
CENAU-CT
KONRAD-ADENAUER RING 39
WIESBADEN 65187
(+49)611-9744-2600
WK4SF6
0002 N/A N/A N/A N/A
0002AA 1095 dys. ANP 1 U.S. ARMY CORPS OF ENGINEERS, EUROPE
CENAU-CT
KONRAD-ADENAUER RING 39
WIESBADEN 65187
(+49)611-9744-2600
0002AB 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0003 N/A N/A N/A N/A
0003AA 1095 dys. ANP 1 U.S. ARMY CORPS OF ENGINEERS, EUROPE
CENAU-CT
KONRAD-ADENAUER RING 39
WIESBADEN 65187
(+49)611-9744-2600
0003AB 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0004 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0005 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0006 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0007 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
0008 1095 dys. ANP 1 (SAME AS PREVIOUS LOCATION)
Section 00 21 00 - Instructions
CLAUSES INCORPORATED BY FULL TEXT
252.236-7008 CONTRACT PRICES - BIDDING SCHEDULES. (DEC 1991)
(a) The Government's payment for the items listed in the Bidding Schedule shall constitute full compensation to the Contractor for --
(1) Furnishing all plant, labor, equipment, appliances, and materials; and
(2) Performing all operations required to complete the work in conformity with the drawings and specifications.
(b) The Contractor shall include in the prices for the items listed in the Bidding Schedule all costs for work in the specifications, whether or not specifically listed in the Bidding Schedule.
Section 00 21 16 - Instructions to Proposers
INSTRUCTIONS TO OFFERORS
A. INTRODUCTION
1. The Unites States Army Corps of Engineers (USACE) Europe District (NAU) intends to award a stand-alone construction contract for the construction of the Army Lodging Facilities, Smith Barracks, Baumholder Military Community, Rhineland-Palatinate, Germany. The magnitude of construction is between $40,000,000 and $70,000,000. The period of performance is 1,095 calendar days after the Contractor receives the Notice to Proceed.
2. NOTE: When the word “Offeror” is encountered in the RFP, it is intended to mean a company seeking to do business with the Government that submits a proposal in response to this Solicitation. When the word “Government” is encountered, it is intended to mean USACE NAU. “Request for Proposal,” “RFP” and “Solicitation” are used synonymously throughout.
3. For the purposes of this Solicitation, the Government will utilize the Best Value Tradeoff Process for Source Selection in accordance with FAR 15.101-1 to determine best value. The Government will evaluate both technical aspects of the proposal and price. The Government intends to award a single C-type contract. See Section 00 22 16 for further details on the Government’s evaluation approach.
B. PRE-PROPOSAL CONFERENCE
The Government will hold a pre-proposal conference at the Rheinlander Community Club Conference Room, Smith Barracks BLDG, Fern Street 8085, 55774 Baumholder, Germany, on Wednesday, 15 March 2023 at 0900 hours Central European Time. Please be at the front gate no later than (NLT) 0740 to sign-in.
A site visit is planned immediately following the pre-proposal conference. If planning to attend the site visit, please complete the Installation Access Roster Request posted at SAM.gov and return to the Project Manager, Almur Whiting via email at almur.s.whiting@usace.army.mil and Contract Specialist, Phillip Garrison via e-mail at phillip.garrison@usace.army.mil by Close of Business 28 February 2023.
C. PROPOSAL SUBMISSION
1. To assure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Offerors are required to meet all Solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors. The Offeror shall submit in the proposal all requested information specified in this section of the Request for Proposal (RFP) at or before the exact time specified. Failure to meet a requirement may result in an Offeror being ineligible for award.
Copies of the RFP are available by INTERNET ACCESS ONLY. All RFP documents will be made available for viewing at the SAM website (http://www.sam.gov). All amendments will be made available for viewing in SAM. It shall be the Offeror’s responsibility to check the website for any amendments.
2. Requests for Information. Offerors are requested to review the plans and specifications in their entirety and review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry. The Government reserves the right to decline addressing certain questions. Further, no questions, unless in the Government’s interest, will be answered more than 20 calendar days after the solicitation date after 28 March 2023 at 1500 Central European Time (CET)..
3. Bidder Inquiries. Technical inquiries and questions relating to technical requirements, and proposal procedures are to be submitted via Bidder Inquiry in ProjNet at: https://www.projnet.org/projnet/ No Later Than the date shown below, in order that they may be given consideration or actions taken prior to receipt of offers. The Bidder Inquiry system is to be used to ask and receive answers to all non-proprietary questions. The project number is: W912GB23R0025. The bidder inquiry key is: 6H7ARU-29WK8Z
To submit and review inquiry items, prospective offerors and vendors will need to use the Bidder Inquiry Key presented above and follow the instructions listed below. A prospective vendor who submits a comment/question will receive an acknowledgement of their comment/question via email, followed by an answer to the comment/question after it has been processed by our technical team. All timely questions and approved answers will be made available through ProjNet. Only representatives of the Prime Contractor (no subcontractors) may submit RFI’s via ProjNet.
a. Registration for ProjNet Bidder Inquiry Access
1) If not already registered, go to Entering Bidder Inquiries in ProjNet Bidder Inquiry System below.
2) From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3) Identify the Agency. This should be marked as USACE.
4) Key. Enter the Bidder Inquiry Key listed above.
5) Email. Enter the email address you would like to use for communication.
6) Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
7) Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret
Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
8) Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
b. Entering Bidder Inquiries in ProjNet Bidder Inquiry System
1) For future access to ProjNet, you will not be emailed any type of password. You will utilize your Secret Question and Secret Answer to log in.
2) From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3) Identify the Agency. This should be marked as USACE.
4) Key. Enter the Bidder Inquiry Key listed above.
5) Email. Enter the email address you used to register previously in ProjNet.
6) Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7) Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
8) Follow online screen instructions to enter specific bidder inquiries for the project.
The Bidder Inquiry System will be unavailable for new inquires after the date shown in the paragraph above in order to ensure adequate time is allotted to form an appropriate response and change the solicitation, if necessary.
Offerors are requested to review the RFP in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The ProjNet call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). For questions and comments please call the Help Center 1-217-367-3273 or 1- 800-428-HELP (4357) or e-mail staff@projnet.info.
4. General Proposal Submission Requirements.
c. Electronic Proposals. In an effort to reduce paperwork and costs, ALL RESPONSES TO THIS ANNOUNCEMENT SHALL BE SUBMITTED ELECTRONICALLY. Hand carried delivery or USPS/UPS/FedEx delivery of hard copies and/or CD-ROMs are not authorized. Facsimile submission is not authorized. Electronic submissions shall be via email to both the Contract Specialist, Phillip Garrison, at phillip.c.garrison@usace.army.mil and the Contracting Officer, Ryan Shoemaker, at ryan.s.shoemaker@usace.army.mil. It is the responsibility of the Offeror to ensure receipt.
d. File Size Limitations. Offerors are advised that the file size limitation is 10MB due to email server restrictions. If needed, Offerors are advised to break the files down into smaller sections and deliver in separate emails. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
e. File Names. To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention: Each filename shall begin with the Solicitation number, followed by the word “RESPONSE,” followed by your firm’s name, and finally a brief file description. EXAMPLES:
(1) “Firmname W912GB23R0025 RESPONSE Volume I.pdf”
(2) “Firmname W912GB23R0025 RESPONSE Volume I Schedule.XER”
(3) “Firmname W912GB23R0025 RESPONSE Volume II.pdf”
f. File Organization, Formatting, and other instructions. Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 point or larger and font text shall be legible. Pages shall be letter or A4 sized--larger page sizes (such as 11x17 foldouts, etc.)
will be counted as two pages. Offerors shall prepare proposals in the English language. Proposals shall be in a narrative format, organized and titled so that each section of the proposal follows the order and format of the factors. Information presented should be organized so as to pertain to only the evaluation factor in the section that the information is presented. Proposals shall completely and adequately address the requirements of this Solicitation. Offerors are reminded that elaborate corporate marketing information, formatting, special reproduction techniques, etc., are not necessary.
Failing to submit attachments or failing to complete the proposal properly may result in rejection of the offer without further evaluation. Information pertaining to more than one evaluation factor should be repeated in each section for each factor. Electronic files shall be Microsoft Windows compatible. Files shall be submitted in their native format (i.e., doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. If the electronic files are of a size at which they must be compressed (zipped), they shall be compressed into one zipped folder.
g. Submission & Deadline. Interested parties shall submit responses no later than the date specified on the solicitation document. The time and date of proposal receipt will be the delivery time and date recorded of email receipt on the Government’s server. The time the electronic submission is sent by the interested party is not determinative. Do not assume that electronic submission will occur instantaneously. Offerors should time their submission with prudence by not waiting until the last day—this will allow for unexpected delays in the transmittal process and troubleshooting.
Offerors are encouraged to keep a copy of the delivery and/or read confirmation for their record but shall also request confirmation. Be advised that proposals received after the submission deadline will be considered late and as such will be processed in accordance with FAR 15.208. It is the responsibility of the Offeror to ensure receipt.
h. Any information, presented in a proposal that the Offeror wants safeguarded from disclosure to other parties must be identified and labeled in accordance with the requirements of Provision “FAR 52.215-1, Instructions to OfferorsCompetitive Acquisition (Jan 2004),” subparagraph (e). The Government will endeavor to honor the restrictions against release requested by Offerors, to the extent permitted under United States law and regulations.
SPECIAL NOTICE: System for Award Management. Please take notice that the System for Award Management (SAM, www.sam.gov) requires that firms submit an "original, signed notarized letter identifying the authorized Entity Administrator for the entity associated with the Data Universal Numbering System (DUNS) number before the registration will be activated." This applies to all new entity registrations and all entity registration renewals, effective 29 April 2018. Further information behind this new requirement is posted to the General Services Administration's (GSA) announcement page at https://www.gsa.gov/samupdate. Please also refer to Federal Service Desk's (FSD) instructions on how to comply with this new requirement. NOTE: the instructions are different for domestic (U.S. based) and international (not U.S. based) firms. Offerors are reminded that this Solicitation includes the provision FAR 52.204-7 SAM and the resulting award will include the clause FAR 52.204-13 SAM Maintenance. These provisions/clauses require all contractors to register and maintain an active SAM entity registration in order to be eligible for contract awards, as prescribed by the regulation at FAR Subpart 4.11. In order to eligible for the contract award resulting from this Solicitation, Offerors are advised to take immediate action to ensure your SAM entity registration is current and/or will be current at the time of proposal receipt by this contracting office.
Instructions for domestic entities (located in the U.S. or its outlying areas): https://fsd.gov/fsd-gov/answer.do?sysparm_kbid=d2e67885db0d5f00b3257d321f96194b&sysparm_search=kb0013183.
Instructions for international entities (not located in the U.S. or its outlying areas): https://www.fsd.gov/fsd-gov/answer.do?sysparm_kbid=dbf8053adb119344d71272131f961946&sysparm_search=KB0013221
EVALUATION FACTORS FOR AWARD
A. BASIS FOR AWARD
The Government will utilize the Best Value Tradeoff Process for Source Selection in accordance with FAR 15.101-1 to determine best value. This process permits tradeoffs among cost or price and non-cost factors. Award will be made to the Offerors proposing the combination most advantageous to the Government based upon an integrated assessment of the proposals received, including the evaluation factors described in paragraph C of this section. The Government considers it to be in its best interest to allow award to other than the lowest priced Offeror or other than the highest technically rated Offeror.
The non-price factors, when combined are significantly more important than the price factor.
Factor 1: Past Performance, Factor 2: Management Approach, and Factor 3: Technical Approach Narrative and Schedule are of equal importance.
B. PROPOSAL AND RELATED EVALUATION FACTORS
The Government Source Selection Team (SST) will evaluate proposals according to the factors listed below.
Offerors are required to provide data addressing all stated factors in a clear and understandable format. Proposals that do not clearly address all factors may be considered unacceptable and may not receive further consideration.
Factor 1: Past Performance Factor 2: Management Approach Factor 3: Technical Approach Narrative and Schedule
Factor 4: Price
1. VOLUME I – NON-PRICE
a. Section A - Executive Summary. Include a one (1) page cover letter and any applicable fully-executed JV agreements and fully executed teaming agreements. The Executive Summary shall not exceed ten
(10) pages in total.
i. The cover letter shall be in accordance with FAR 52.215-1(c)(2), including:
(1) The Solicitation number.
(2) The Offeror’s name, address, and phone/email contact information.
(3) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the Solicitation and agreement to furnish any or all items upon which prices are offered.
(4) Names, titles, and telephone / email contact information of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this Solicitation.
(5) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent’s authority.
ii. JV agreements shall include the following:
(1) A copy of their JV agreement in English, signed by all parties of the JV.
(2) A detailed statement outlining the following in terms of percentages, where appropriate:
(a) The relationship of the JV parties in terms of business ownership, capital contribution, and profit distribution or loss sharing.
(b) The management approach of the JV in terms of who will conduct, direct, supervise and control the project and have custody and control of the assets of the JV and perform the duties necessary to complete the work.
(c) The structure of the JV and decision-ranking responsibilities of the JV parties in terms of who will control the manner and method of performance of the work.
(d) Identification of the key personnel having authority to legally bind the JV to subcontracts and state who will provide or contract for the labor and materials for the
JV.
(e) Identification of party maintaining the JV bank accounts for the payment of all expenses and the deposits of all receipts, keep the books and records, and pay applicable taxes for the JV.
(f) Identification of party furnishing the facilities, such as office supplies and telephone service.
(g) Identification of party having overall control of the JV.
(3) Other sections of the proposal shall identify, where appropriate, whether key personnel are employees of the individual JV parties and identify the party, or hired as employees of the
JV.
(4) A statement in the agreement that each member of the JV will be jointly and severally liable for any obligations under the contract.
(5) A complete and legally binding document with all the information required under this section titled “JVs” shall be included.
iii. Other formal teaming agreements (also see C. EVALUATION APPROACH, 2. TEAMING
ARRANGEMENTS) shall include the following:
(1) A copy of their teaming agreement in English, signed by all parties of the team.
b. Section B - Factor 1, Past Performance.
SUBMISSION REQUIREMENTS:
Offerors shall submit a minimum of two (2) and a maximum of five (5) projects substantially complete or completed within the last ten (10) years (from the RFP issue date) which are similar to this project in size and scope. Projects completed more than ten (10) years before the solicitation issue date may be considered for evaluation purposes but may lessen the overall relevancy rating for that project.
Substantially complete is defined as project completion of at least 80% of the awarded contract scope/amount. Projects considered similar in size will have an award amount at or above $25,000,000.00. Projects considered similar in scope will be vertical multi-story construction projects.
Projects that contain the features below may be considered more relevant:
i. New lodging facilities construction.
ii. Other new vertical construction, such as apartment building and multi-family housing.
iii. Projects demonstrating working on sites having restricted access, such as military installations.
iv. Projects that demonstrate work in Germany.
v. Projects that demonstrate working for the United States Government Department of Defense.
vi. Projects demonstrating working with proposed Key Subcontractors, team members and/or the proposed JV Partners.
If the Offeror wants the Government to consider a Teaming Arrangement for its past performance; it shall identify all such entities in its Factor 1 proposal and provide at least one qualifying sample project from each such entity. For a Joint Venture (JV) Offeror, it is not required to have experience working as JV; the members of the JV may submit experience on behalf of the Offeror. NOTE: the provided projects should reflect the same or significantly similar scope of work that will be performed by that entity under this Contract.
Past performance completed as/by a subcontractor will be considered Not Relevant and will not be reviewed.
NOTE: Where a project was awarded as a task order or delivery order under an Indefinite Delivery / Indefinite Quantity type contract, Offerors are cautioned to submit information specific to the task or delivery order rather than the base contract.
The Offeror should complete a Past Performance Information Sheet provided as an attachment to this RFP or a similar document for each project. Past Performance Information Sheets or a similar document shall not exceed four (4) pages per project.
If more than five (5) projects are submitted by an Offeror, the Government will only review the first five
(5) projects. The projects will be reviewed in the order in which they are received in Offeror’s submitted proposal.
For each project submitted under Factor 1, Offerors shall include completed Contractor’s Performance Assessment Reporting System (CPARS) record or completed Past Performance Evaluation Questionnaire Form. If available, a completed record from the CPARS will be accepted for evaluation under this factor. An interim completed CPARs rating will be considered if a final record is not available. If a completed CPARS record is not available at all, Offerors shall complete and provide a Past Performance Questionnaire (PPQ) Form, provided as an RFP Attachment.
PPQ Instructions: The Offeror shall complete Blocks 1-4 of the provided Past Performance Questionnaire and have the Contracting Activity and the Technical Representative responsible for the past/current contract complete the remainder of the PPQ. Offeror shall ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with the proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact via email no later than the closing date of this RFP.
Also include copies of performance recognition documents received for the Factor 1 projects such as awards and/or award fee determinations. Offerors shall provide a copy of any Cure Notices or Show Cause Letters received by the Offeror for each submitted project and a description of any corrective action implemented by the Offeror. The Offerors shall indicate if any of the contracts listed were terminated and the type and reasons for the termination.
EVALUATION CRITERIA:
The Government will first evaluate the relevancy of recent past performance identified in the proposal in response to the Submission Requirements paragraph above. By using the criteria above, the Government will determine how relevant a past project is when compared to the scope, size, and magnitude of effort and complexities of the solicited project. A relevancy rating will be assigned to each submitted project using the Past Performance Relevancy Ratings table below.
Past Performance Relevancy Ratings:
Rating Definition
Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant
Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
The SST will next review how well the offeror performed on those projects. The Government reserves the right to check any or all cited references to verify supplied information and to assess owner satisfaction. In addition to the information submitted by the Offeror, the Government may review any other sources of relevant information for evaluating past performance, including similar projects other than those submitted by the Offeror. The Government will, at a minimum, review past performance information retrieved through the Contractor Performance Assessment Reporting System (CPARS), using all CAGE/Unique Entity Identifier numbers identified in the offeror’s proposal. Other sources may include, but are not limited to, past performance information retrieved from inquiries of owner representative(s), Federal Awardee Performance and Integrity System (FAPPIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
The Government will assign a final, overall Performance Confidence rating, using the ratings in the Performance Confidence Assessment table below. The Government will review all past performance information collected and determine the quality of the offeror’s performance, general trends, and usefulness of the information and incorporate this information into the performance confidence assessment. The past performance confidence assessment rating is based on the offeror’s overall record of recency, relevancy, and quality of performance.
Note: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). The Offeror will be assigned a “neutral” past performance with a performance risk of “unknown”. A “Neutral (unknown) Confidence” will be assigned under the Performance Confidence Assessment evaluation. If an Offeror has no relevant past performance history, the Offeror must affirmatively state that it possesses no relevant directly related or similar past performance.
Performance Confidence Assessments:
Rating Definition
Substantial Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.
Satisfactory Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.
Neutral (Unknown) Confidence
No recent/relevant performance record is available or the Offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
The offeror may not be evaluated favorably or unfavorably on the factor of past performance.
Limited Confidence
Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.
No Confidence Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will be able to successfully perform the required effort.
c. Section C - Factor 2, Management Approach.
The Offeror shall provide a Management Approach, which shall include at a minimum:
i. One (1) organizational chart and a narrative description of the Offeror’s overall structure and management of the project team from the Offeror’s Headquarters to the Offeror’s site office(s).
The Offeror shall arrange the chart by organizational levels and locations, depicting lines of authority. The chart should show the interrelationship between the contract management team and on-site project teams. The chart should include a clear description of each firm’s roles and responsibilities for any teaming or joint venture arrangements. Describe the proposed management structure for the team, describing how the project will be managed and the authorities and delegations of authority within the team. The hierarchy of the organization chart shall show the Project Manager as the highest level of authority for key personnel on the project and shall be subordinate to an officer of the Prime Contractor.
The chart and narrative must:
identify all offices involved in this contract identify position(s) to communicate with the U.S. government identify all positions by title, organization, and physical location, including subcontractors and consultants include lines of reporting and technical areas of responsibility under the contract clearly show the lines of authority of the Offeror’s Project Manager, Project
Superintendent(s), CQC System Manager(s), Quality Control Representative(s) and Site Safety and Health Officer(s), including all JV Partners and subcontractors, when applicable
ii. Discuss how the Offeror will ensure consistent quality across the team. Discuss quality control lines of authority between subcontractors and prime.
iii. Discuss how the Offeror will ensure consistent safety across the team. Discuss safety lines of authority between subcontractors and prime.
iv. Discuss the Offeror’s plan to obtain, retain, coordinate, and manage subcontractors. Include any established relationships with organizations qualified for work within the scope of this RFP, including number of projects that have been completed together and/or number of years of partnering. Identify the significant aspects of the work that are to be self-performed and those that will be subcontracted. Identify the nature and overall percent of work that will be performed by the Prime Contractor and all key sub-contractors. The Offeror shall describe the authorities delegated to project managers and field personnel. The Offerors are reminded of the requirements of 52.236-1, Performance of Work by the Contractor.
v. Discuss knowledge of construction and permitting requirements in Germany to include coordination with local authorities. host nation standards and regulations to meet final acceptance of the project after construction.
vi. The Offeror’s management and onsite staff’s ability to communicate in German and English.
vii. The Offerors should identify any additional and/or unique management advantages their proposal provides to the Government. Greater weight will be given to each of the following when assessing Offeror’s relevant experience:
Contractor’s staff that have on-site decision-making authority to include, but not limited to, negotiations, resolution of issues, resources, and the level of authority delegated to address issues
Organizational relationships which have been used on other projects that are same or similar to the scope of this RFP
Proposals that provide a description of relationship/contractual agreement with proposed subcontractors
Depth and breadth of technical experience and qualifications as it relates to the responsibilities of proposed key personnel
Key personnel experience working for the Prime contractor and with other key personnel Prime contractor key personnel and key subcontracting team experience working in the area of responsibility covered under the RFP.
The Management Approach, excluding the organizational chart, shall not exceed ten (10) pages.
Management Approach submissions exceeding ten (10) pages will not be read or evaluated beyond the first ten (10) pages. Pages shall be letter or A4 sized--larger page sizes (such as 11x17 foldouts, etc.) will be counted as two pages.
EVALUATION CRITERIA:
The Offeror’s Management Approach will be evaluated for completeness, reasonableness, risk, and logic. The Government will evaluate whether and to what extent the Management Approach:
i. Clearly defines the planned organization structure and presents a logical, viable approach to perform the work described in the RFP documents and achieve the desired quality.
ii. Delineates lines of authority appropriately including the relationship between the headquarters’ office and the site office, including all involved with the management of the contract including subcontractors and JV partners (where applicable) and identifies which personnel are identified to communicate with the Government.
iii. Comprehensively describes the duties, roles, major responsibilities, and authorities for key personnel, including roles of authorities for subcontractors and JVs.
iv. Whether the Offeror demonstrates a thorough knowledge of construction and permitting requirements in Germany to include coordination with host nation authorities host nation standards and regulations to meet final acceptance of the project after construction.
v. Whether the Offeror demonstrates a thorough understanding of certification and registration requirements for companies in Germany and the ability to meet the requirements along with the demonstrated ability to communicate in German and English.
For this factor, Offerors will be assigned a combined technical/risk rating from the following table, based on the evaluation of the Offeror’s proposal in accordance with the requirements of the Solicitation:
NON-PRICE FACTOR COMBINED TECHNICAL/RISK RATINGS
Color Rating Description
Blue Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one significant strength, and risk of unsuccessful performance is low.
Purple Good Proposal indicates a thorough approach and understanding of the requirements and contains at least one strength or significant strength, and risk of unsuccessful performance is low to moderate.
Green Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements, and risk of unsuccessful performance is no worse than moderate.
Yellow Marginal Proposal has not demonstrated an adequate approach and understanding of the requirements, and/or risk of unsuccessful performance is high.
Red Un-acceptable Proposal does not meet requirements of the solicitation and, thus, contains one or more deficiencies and is unawardable, and/or risk of performance is unacceptably high.
The adjectival ratings, defined below, are not separate ratings, but will be used to define the levels of risk in the aforementioned table:
NON-PRICE FACTOR TECHNICAL RISK RATING
Adjectival Rating
Description
Low Proposal may contain weakness/weaknesses which have low potential to cause disruption of schedule, increased cost, or degradation of performance. Normal contractor emphasis and normal Government monitoring will likely be able to overcome any difficulties.
Moderate
Proposal contains a significant weakness or combination of weaknesses which may have a moderate potential to cause disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close Government monitoring will likely be able to overcome any difficulties.
High
Proposal contains a significant weakness or combination of weaknesses which is likely to have high potential to cause significant disruption of schedule, increased cost, or degradation of performance. Special contractor emphasis and close Government monitoring will unlikely be able to overcome any difficulties.
Unacceptable Proposal contains a deficiency or a combination of significant weaknesses that causes an unacceptable level of risk of unsuccessful performance.
d. Section D - Factor 3, Technical Approach Narrative and Schedule –
The Offeror should provide a plan describing their proposed approach to executing the work required by the RFP documents. The plan shall consist of (1) a Technical Approach Narrative and
(2) Schedule. For the purposes of this factor only, the Offeror shall use the date of 14 Aug 2023 for Notice to Proceed (NTP) and prepare the schedule assuming that all base line items and options will be awarded on that date.
The Technical Approach Narrative shall include:
i. Describe the offerors overall plan for executing the work from NTP to final completion.
The plan should specifically address:
All work to be performed during winter months (all years of the contract). Include a description of any special measures which the offeror intends to take to mitigate the impacts of cold and inclement weather conditions which may be encountered during the winter time period.
Measures intended to reduce impact to on-going operations at Baumholder Military Community.
The offerors plan for executing construction of this project.
ii. Identify long lead-time items and describe steps to be taken to ensure they will be available on site timely.
iii. Identification of large equipment (including any proposed construction cranes, and batch plants) to be used to perform the work along with the source (self-owned, subcontractor, etc.).
iv. Identification of up to five (5) main risks identified by the Offeror in their schedule, along with mitigation measures.
v. Clearly identify any constraints on the schedules presented (e.g., labor or material availability, permits, weather, etc.).
The Technical Approach Narrative shall not exceed ten (10) pages. Technical Approach Narrative submissions exceeding 10 pages will not be read or evaluated beyond the first 10 pages.
The Schedule must include both a Schedule and a Schedule Narrative consisting of the following:
i. A schedule prepared in Primavera P6 and submitted in PDF format specifically-tailored to the project contemplated by this solicitation. The schedule shall include all of the major portions of work, including submittals, reviews and approval periods.
ii. A description of activities along the critical path of the schedule and all activities with less than one week of float with their relation to the critical path.
iii. Explanation of how durations were determined and logic developed.
The Technical Approach Narrative and Schedule will be evaluated as one factor. The Offeror’s Technical Approach Narrative and schedule for the project will be evaluated for completeness, logic, reasonableness, and risk associated with the proposed schedule as compared to the Solicitation requirements. As part of the evaluation, the Government will assess:
i. Whether and to what extent the narrative and schedule correlate and support one another
ii. How well the proposed schedule meets the contractual milestone dates and performance requirements defined in Specification Section 01 11 00 Summary of Work
iii. The strength of understanding of the project scope, and restrictions which must be considered in the schedule (e.g., durations of activities, long lead items, critical milestones, logic of proposed phasing, etc.).
iv. The realism of the schedule
The Government may use independent judgment concerning logic, constraints, and typical construction durations.
Full compliance with Specification Section 01 32 01 Project Schedule (NAU) is not required, however the Government will evaluate the schedule (PDF Schedule) to assess conformance with the solicitation requirements.
NOTE: Do NOT include any cost or pricing information in the Schedule.
For this factor, Offerors will be assigned a combined technical/risk rating from the following table, based on the evaluation of the Offeror’s proposal in accordance with the requirements of the Solicitation:
NON-PRICE FACTOR COMBINED TECHNICAL/RISK RATINGS
Color Rating Description
Blue Outstanding Proposal demonstrates an exceptional approach and understanding of the requirements and contains multiple strengths and/or at least one…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .