W81G6760757786
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to make changes to the Performance Work Statement and the pricing schedule.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-16-R-0005
X 9B. DATED (SEE ITEM 11)
20-May-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Aug-2016
CODE
CONTRACTING DIVISION
USACE - ST. PAUL
180 5TH STREET E SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES-16-R-0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
AMENDMENT 5
-- Replace Section 5.2.3 Trails with the following:
5.2.3 Trails: Perform routine inspection, maintenance, and repair of tank trails and road crossings for tanks, to include, grading, filling, and tree and branch removal. Trail surface maintenance will use existing material that has been displaced by military traffic or storm event. Fill material will be required only as needed if material cannot be recovered at the site. Maintenance is expected to be performed prior to scheduled major military exercises and if warranted after severe storm events. A map illustrating the tank trails is available for review in the Technical Library (TL 5-4). The contractor shall coordinate with Directorate of Plans, Training, Mobilization and Security (DPTMS) to forecast and plan maintenance requirements. Major trail reconstructions are completed by other contract.
-- Section 5.4.2 Culvert, Dam, and Bridge Debris Clearing requirement has been moved to Section 5.10 as a potential RFP SO. This shifts the Section 5 PRS numbering accordingly and eliminates X005 from the pricing schedule.
-- Section 5.2.4.1 Culvert and Ditching Maintenance has been renumbered to 5.2.4.
-- New Section 5.2.4 Culvert and Ditching Maintenance PRS number shifts from 09-A to 08-A.
-- Section 5.3 Snow and Ice Removal PRS numbers shift from 10-A, 10-B, 10-C, 10-D, 10-E, and 10-F to 09-A, 09-B, 09-C, 09-D, 09-E-, and 09-F.
-- Section 5.3.1 Runway, Taxiway, and Apron Snow Removal PRS numbers shift from 11-A and 11-B to 10-A and 10-B.
-- Section 5.4.1 Grass Cutting PRS numbers shift from 12-A, 12-B, and 12-C to 11-A, 11-B, and 11-C.
-- Section 5.4.2 Turf Repair and Maintenance PRS number shifts from 13-A to 12-A.
-- Section 5.5 Brush Cutting, Chipping, and Debris Removal PRS number shifts from 14-A to 13-A.
-- Section 5.6 Barrier Placement PRS number shifts from 15-A to 14-A.
-- Section 5.8 Hazardous Material Spill Cleanup and Disposal PRS numbers shift from 16-A and 16-B to 15-A and 15-B.
-- Section 5.10 Request for Proposal (RFP) Service Orders now also includes Culvert, Dam, and Bridge Debris Clearing.
SECTION B - SUPPLIES OR SERVICES AND PRICES
CLIN 0005
The CLIN type priced has been deleted.
The CLIN description has changed from Culvert, Dam, Bridge Clearing to (Unused / Unpriced CLIN).
The CLIN extended description Not Sept for base year (1 month phase in period) has been deleted.
The pricing detail quantity 11.00 has been deleted.
The unit of issue Months has been deleted.
The MILSTRIP W81G6760757786 has been deleted.
CLIN 1005
The CLIN description has changed from Culvert, Dam, Bridge Clearing to (Unused / Unpriced CLIN).
The pricing detail quantity 12.00 has been deleted.
The option status has changed from Option to No Status.
CLIN 2005
The CLIN description has changed from Culvert, Dam, Bridge Clearing to (Unused / Unpriced CLIN).
The pricing detail quantity 12.00 has been deleted.
CLIN 3005
The CLIN description has changed from Culvert, Dam, Bridge Clearing to (Unused / Unpriced CLIN).
The pricing detail quantity 12.00 has been deleted.
CLIN 4005
The CLIN description has changed from Culvert, Dam, Bridge Clearing to (Unused / Unpriced CLIN).
The pricing detail quantity 12.00 has been deleted.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule Item has been deleted from CLIN 0005:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
POP 01-SEP-2016 TO
31-AUG-2017
N/A FORT MCCOY (DPW)
DIRECTORATE OF PUBLIC WORKS
2171 S 8TH AVENUE
FORT MCCOY WI 54656
FOB: Destination
The following Delivery Schedule Item has been deleted from CLIN 1005:
POP 01-SEP-2017 TO
31-AUG-2018
N/A FORT MCCOY (DPW)
DIRECTORATE OF PUBLIC WORKS
2171 S 8TH AVENUE
The following Delivery Schedule Item has been deleted from CLIN 2005:
POP 01-SEP-2018 TO
31-AUG-2019
N/A FORT MCCOY (DPW)
DIRECTORATE OF PUBLIC WORKS
2171 S 8TH AVENUE
The following Delivery Schedule Item has been deleted from CLIN 3005:
POP 01-SEP-2019 TO
31-AUG-2020
N/A FORT MCCOY (DPW)
DIRECTORATE OF PUBLIC WORKS
2171 S 8TH AVENUE
The following Delivery Schedule Item has been deleted from CLIN 4005:
POP 01-SEP-2020 TO
31-AUG-2021
N/A FORT MCCOY (DPW)
DIRECTORATE OF PUBLIC WORKS
2171 S 8TH AVENUE
(End of Summary of Changes)