This document is an amendment to a solicitation for the construction of an electrical distribution system upgrade project at a naval support activity in Bahrain. The project scope involves constructing a more resilient medium-voltage distribution system to provide increased resiliency, security, and flexibility to critical facilities by lessening the impacts of outages and fluctuations. Revisions include updated specifications, drawings, and terms and conditions. The solicitation is seeking to award a design-build-bid contract for the electrical system upgrade referenced as P-974. The issuing agency is the U.S. Army Corps of Engineers Engineering District Middle East.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
474977
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SEE SF 30 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 28-Jan-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912ER22R0008
X 9B. DATED (SEE ITEM 11)
20-Oct-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
28-Jan-2022
CODE
US ARMY CORPS OF ENGINEERS-CETAM-CT
MIDDLE EAST DISTRICT
P.O. BOX 2250
WINCHESTER VA 22604-1450
W912ER 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ER22R0008
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
CONTINUATION PAGE
1. Specifications: Revised sections are replaced in their entirety. Revisions to the specification pages are shown on the pages in the following manner: New text is underlined and deleted text is shown using strikeout. The amendment number appears in the bottom margin on all pages of the revised sections.
Volume 2 of 4
Table of Contents – replaced in its entirety.
Section 01 33 00
Submittal Register – replaced in its entirety.
Section 01 50 00
Paragraph 2.2.3, pages 3-4 Paragraph 3.5, page 6
Section 01 91 00.15
Paragraph 1.2, page 1 Paragraph 1.5.1 and 1.5.1.a-c, pages 2 and 3 Paragraph 1.7.2.b, page 6
Section 07 60 00
Paragraph 2.2.1, page 5 Paragraph 3.1.16, page 12 Paragraph 3.1.17, pages 12 and 13 Paragraph 3.5.1, pages 17 and 19
Volume 3 of 4
Section 09 67 23
Paragraph 1.2, page 1 Paragraph 2.1.a-e, page 3
Volume 4 of 4
Section 33 40 00
Paragraph 2.1.1, page 4 Paragraph 3.2.1, page 7 Paragraph 3.2.2, page 7 Paragraph 3.3.1, page 7 Paragraph 3.4, pages 8-9 Paragraph 3.8.1.1.1, page 12 Paragraph 3.8.1.2, page 12 Paragraph 3.8.2.1.1, page 13 Paragraph 3.8.3.3.1, page 14
W912ER22R0008
2. Drawings. Revisions to the following drawings are identified by a triangle placed on the drawing near each revision and a "cloud" drawn around both the triangle and change.
G-011 G-012 C-001
CD001
CS501
CS505
CS506
CU401
CU701
Site A A-111 A-503 A-504
3. All other terms and condition remain unchanged.