A02 - W912EK25A018 - L19 - BLANK COPY SOP_FOR CONTRACTOR AMND 0002.xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- Mississippi River Basin, Lock 19, Keokuk, IA, Nose Pier Replacement and Bulkhead Recesses
- Solicitation number
- W912EK25RA018SOL
About this file
This file is a Schedule of Prices (SOP) for the Mississippi River Basin Lock 19 Nose Pier Replacement and Bulkhead Recess project by the US Army Corps of Engineers Rock Island District. The contract includes a base bid and two options with a total estimated value between $25-$100 million. The base bid involves extending the river wall monolith upstream, including mobilization, hydrographic surveys, concrete removal, mechanical dredging, underwater rock excavation, precast concrete segment installation, and electrical work. Option 1 focuses on constructing a bulkhead recess in the land wall, while Option 2 involves constructing a bulkhead sill with drilled shafts, stay-in-place formwork, and tremie concrete placement.
The contract is classified under NAICS code 237990 with a size standard of $45 million, and is an unrestricted Lowest Price Technically Acceptable (LPTA) solicitation. The project has a base completion timeline of 638 consecutive calendar days, extendable to 973 days if Option 2 is awarded. Key contract details include the government's right to exercise Option 1 no later than 107 days after Notice to Proceed, and Option 2 within the same timeframe. The pricing schedule breaks down various construction activities into detailed line items, covering everything from mobilization and temporary facilities to concrete placement, reinforcing, and electrical work.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table 1
| ITEM NO. | SUPPLIES/SERVICES | QTY | UNIT | UNIT | ||
| PRICE | AMOUNT | |||||
| Base Bid - River Wall Extension and Bulkhead Recess | ||||||
| 0001 | Mobilization and Demobilization | 1 | JOB | XXXXXXX | $ | |
| 0002 | Temporary Construction Facilities | 1 | JOB | XXXXXXX | $ | |
| 0003 | Hydrographic Surveys | 1 | JOB | XXXXXXX | $ | |
| 0004 | Removal and Reinstallation of Appurtenances | 1 | JOB | XXXXXXX | $ | |
| 0005 | Mechanical Dredging | |||||
| 005AA | First 300 Cubic Yards | 300 | CY | $ | $ | |
| 005AB | Over 300 Cubic Yards | 150 | CY | $ | $ | |
| 0006 | Rock Excavation | |||||
| 006AA | First 550 Cubic Yards | 550 | CY | $ | $ | |
| 006AB | Over 550 Cubic Yards | 200 | CY | $ | $ | |
| 0007 | Underwater Concrete Demonstration | 1 | JOB | XXXXXXX | $ | |
| 0008 | Final Clearing of Silt | 1 | JOB | XXXXXXX | $ | |
| 0009 | Monolith 1-R Concrete Removal | 1 | JOB | XXXXXXX | $ | |
| Monolith 1-R Extension | ||||||
| 0010 | Precast Wall Segment Fabrication | 1 | JOB | XXXXXXX | $ | |
| 0011 | Precast Wall Panel Fabrication | 1 | JOB | XXXXXXX | $ | |
| 0012 | Precast Bulkhead Unit Fabrication | 1 | JOB | XXXXXXX | $ | |
| 0013 | Precast Installation | 1 | JOB | XXXXXXX | $ | |
| 0014 | Reinforcing | 450 | LB | $ | $ | |
| 0015 | Armor | 3600 | LB | $ | $ | |
| 0016 | Concrete Placement | 1250 | CY | $ | $ | |
| 0017 | Checkpost Installation | 2 | EA | $ | $ | |
| 0018 | Protection Plate Assembly | 1 | JOB | XXXXXXX | $ | |
| 0019 | Electrical | 1 | JOB | XXXXXXX | $ | |
| TOTAL OF AMOUNTS - BASE BID | ||||||
| (ITEM NOS. 0001 THROUGH 0019, INCL.) | $ | |||||
| Option 1 - Land Wall Bulkhead Recess | ||||||
| 0101 | Mobilization and Demobilization | 1 | JOB | XXXXXXX | $ | |
| 0102 | Temporary Construction Facilities | 1 | JOB | XXXXXXX | $ | |
| 0103 | Removal and Reinstallation of Appurtenances | 1 | JOB | XXXXXXX | $ | |
| 0104 | Dewatering Structure | 1 | JOB | XXXXXXX | $ | |
| 0105 | Bulkhead Recess Assembly Fabrication | 1 | JOB | XXXXXXX | $ | |
| 0106 | Protection Plate Assembly | 1 | JOB | XXXXXXX | $ | |
| 0107 | Bulkhead Recess Assembly Installation | 1 | JOB | XXXXXXX | $ | |
| 0108 | Electrical Routing and Ductbank | 1 | JOB | XXXXXXX | $ | |
| TOTAL OF AMOUNTS - OPTION 1 | ||||||
| (ITEM NOS. 0101 THROUGH 0108 INCL.) | $ | |||||
| Option 2 - Upstream Bulkhead Sill and Bulkhead Test Fit | ||||||
| 0201 | Mobilization and Demobilization | 1 | JOB | XXXXXXX | $ | |
| 0202 | Temporary Construction Facilities | 1 | JOB | XXXXXXX | $ | |
| 0203 | Hydrographic Surveys | 1 | JOB | XXXXXXX | $ | |
| 0204 | Final Clearing of Silt | 1 | JOB | XXXXXXX | $ | |
| Drilled Shafts | ||||||
| 0205 | Drilling in Rock | 161 | LF | $ | $ | |
| 0206 | Casing | 40 | LF | $ | $ | |
| 0207 | Structural Steel | 87100 | LB | $ | $ | |
| 0208 | Reinforcing | 12500 | LB | $ | $ | |
| 0209 | Concrete Placement | 63 | CY | $ | $ | |
| 0210 | Stay-in-place formwork Fabrication | 1 | JOB | $ | $ | |
| 0211 | Stay-in-place Formwork Installation | 1 | JOB | $ | $ | |
| 0212 | Bulkhead Retrieval and Return | 1 | JOB | XXXXXXX | $ | |
| 0213 | Bulkhead Test Fit | 1 | JOB | XXXXXXX | $ | |
| TOTAL OF AMOUNTS - OPTION 2 | ||||||
| (ITEM NOS. 0201 THROUGH 0213, INCL.) | $ | |||||
| TOTAL OF AMOUNTS - BASE BID, OPTION 1 AND OPTION 2 (ITEM NOS. 0001 THROUGH 0213, INCL.) | $ |
JOB = LUMP SUM EA = EACH LF= LINEAR FEET CF = CUBIC FEET CY= CUBIC YARD LB= POUND
REFER TO FAR 52.211-8 FOR MORE INFORMATION.
| (1) OFFER MUST PRICE ALL LINE ITEMS. |
| (2) FAILURE TO COMPLETE AND RETURN ALL REQUIRED SUBMISSIONS COULD RENDER YOUR BID NON-RESPONSIVE. |
| (3) ALL PRICING TO INCLUDE DELIVERY FEES |
THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE OPTION 1 NO LATER THAN 107 DAYS AFTER NOTICE TO PROCEED AND OPTION 2 NO LATER THAN 107 DAYS AFTER NOTICE TO PROCEED
IF OPTION 1 IS EXERCISED, THE CONTRACT WILL NOT BE EXTENDED; IF OPTION 2 IS EXERCISED, THE CONTRACT WILL BE EXTENDED TO 973 DAYS AFTER NOTICE TO PROCEED.
MAXIMUM CONTRACT DURATION WITH ANY COMBINATION OF AWARDED OPTIONS IS 973 DAYS AFTER NOTICE TO PROCEED.
File details come from the government source that posted it. Updated .