A02 - W912EK25A018 - L19 - BLANK COPY SOP_FOR CONTRACTOR.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Mississippi River Basin, Lock 19, Keokuk, IA, Nose Pier Replacement and Bulkhead Recesses
Solicitation number
W912EK25RA018SOL
Issued by

About this file

This file is a pricing schedule for a U.S. Army Corps of Engineers contract for the Mississippi River Basin Lock 19 Nose Pier Replacement and Bulkhead Recesses project in Keokuk, Iowa. The solicitation (W912EK25RA018SOL) is an unrestricted, Lowest Price Technically Acceptable (LPTA) procurement with an estimated value between $25-$100 million and a base contract duration of 638 consecutive calendar days, extendable to 973 days if Option 2 is awarded.

The contract consists of a base bid and two options, involving complex marine construction work. The base bid includes river wall extension, involving mobilization, hydrographic surveys, mechanical dredging, rock excavation, concrete work, precast wall segment fabrication, and electrical installations. Option 1 focuses on constructing a land wall bulkhead recess, while Option 2 involves building a bulkhead sill with drilled shafts, structural steel work, and bulkhead test fitting. The government reserves the right to exercise Option 1 within 107 days and Option 2 within 258 days after the Notice to Proceed, with a maximum contract duration of 973 days. The project is classified under NAICS code 237990 with a size standard of $45 million.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

ITEM NO.SUPPLIES/SERVICESQTYUNITUNIT
PRICEAMOUNT
Base Bid - River Wall Extension and Bulkhead Recess
0001Mobilization and Demobilization1JOBXXXXXXX$
0002Temporary Construction Facilities1JOBXXXXXXX$
0003Hydrographic Surveys1JOBXXXXXXX$
0004Removal and Reinstallation of Appurtenances1JOBXXXXXXX$
0005Mechanical Dredging
005AAFirst 300 Cubic Yards300CY$$
005ABOver 300 Cubic Yards150CY$$
0006Rock Excavation
006AAFirst 550 Cubic Yards550CY$$
006ABOver 550 Cubic Yards200CY$$
0007Underwater Concrete Demonstration1JOBXXXXXXX$
0008Final Clearing of Silt1JOBXXXXXXX$
0009Monolith 1-R Concrete Removal1JOBXXXXXXX$
Monolith 1-R Extension
0010Precast Wall Segment Fabrication1JOBXXXXXXX$
0011Precast Wall Panel Fabrication1JOBXXXXXXX$
0012Precast Bulkhead Unit Fabrication1JOBXXXXXXX$
0013Precast Installation1JOBXXXXXXX$
0014Reinforcing450LB$$
0015Armor3600LB$$
0016Concrete Placement1250CY$$
0017Checkpost Installation2EA$$
0018Protection Plate Assembly1JOBXXXXXXX$
0019Electrical1JOBXXXXXXX$
TOTAL OF AMOUNTS - BASE BID
(ITEM NOS. 0001 THROUGH 0019, INCL.)$
Option 1 - Land Wall Bulkhead Recess
0101Mobilization and Demobilization1JOBXXXXXXX$
0102Temporary Construction Facilities1JOBXXXXXXX$
0103Removal and Reinstallation of Appurtenances1JOBXXXXXXX$
0104Dewatering Structure1JOBXXXXXXX$
0105Bulkhead Recess Assembly Fabrication1JOBXXXXXXX$
0106Protection Plate Assembly1JOBXXXXXXX$
0107Bulkhead Recess Assembly Installation1JOBXXXXXXX$
0108Electrical Routing and Ductbank1JOBXXXXXXX$
TOTAL OF AMOUNTS - OPTION 1
(ITEM NOS. 0101 THROUGH 0108 INCL.)$
Option 2 - Upstream Bulkhead Sill and Bulkhead Test Fit
0201Mobilization and Demobilization1JOBXXXXXXX$
0202Temporary Construction Facilities1JOBXXXXXXX$
0203Hydrographic Surveys1JOBXXXXXXX$
0204Final Clearing of Silt1JOBXXXXXXX$
Drilled Shafts
0205Drilling in Rock105LF$$
0206Casing40LF$$
0207Structural Steel87100LB$$
0208Reinforcing12500LB$$
0209Concrete Placement63CY$$
0210Stay-in-place formwork Fabrication1JOB$$
0211Stay-in-place Formwork Installation1JOB$$
0212Bulkhead Retrieval and Return1JOBXXXXXXX$
0213Bulkhead Test Fit1JOBXXXXXXX$
TOTAL OF AMOUNTS - OPTION 2
(ITEM NOS. 0201 THROUGH 0213, INCL.)$
TOTAL OF AMOUNTS - BASE BID, OPTION 1 AND OPTION 2 (ITEM NOS. 0001 THROUGH 0213, INCL.)$

JOB = LUMP SUM EA = EACH LF= LINEAR FEET CF = CUBIC FEET CY= CUBIC YARD LB= POUND

REFER TO FAR 52.211-8 FOR MORE INFORMATION.

(1) OFFER MUST PRICE ALL LINE ITEMS.
(2) FAILURE TO COMPLETE AND RETURN ALL REQUIRED SUBMISSIONS COULD RENDER YOUR BID NON-RESPONSIVE.
(3) ALL PRICING TO INCLUDE DELIVERY FEES

THE GOVERNMENT RESERVES THE RIGHT TO EXERCISE OPTION 1 NO LATER THAN 107 DAYS AFTER NOTICE TO PROCEED AND OPTION 2 NO LATER THAN 258 DAYS AFTER NOTICE TO PROCEED

IF OPTION 1 IS EXERCISED, THE CONTRACT WILL NOT BE EXTENDED; IF OPTION 2 IS EXERCISED, THE CONTRACT WILL BE EXTENDED TO 973 DAYS AFTER NOTICE TO PROCEED.

MAXIMUM CONTRACT DURATION WITH ANY COMBINATION OF AWARDED OPTIONS IS 973 DAYS AFTER NOTICE TO PROCEED.

File details come from the government source that posted it. Updated .