W912EF21R0015 Amend 0002.pdf

PDF 823 KB Posted

Attached to
McNary Intake Gates and Isophase Bus Systems
Solicitation number
W912EF21R0015
Issued by

About this file

This document is a presolicitation notice for a construction contract to rehabilitate intake gates and isophase bus systems at McNary Dam in Oregon. The project involves rehabilitating 45 intake gates, including replacing seals, seal bars, anodes, and touch-up painting. It also requires inspecting sealing surfaces on 44 gates, providing 92 new hydraulic cylinders and support beams, and replacing the hydraulic power unit, headers, control systems, and approximately 26,000 gallons of hydraulic fluid. For the isophase bus system, the work includes replacing 15kV isophase and delta bus, synchronizing potential transformers, high-voltage disconnect switches, surge arresters, tubular bus segments, and performing transformer draining, filling and testing. The period of performance is estimated from December 2021 to May 2030. Work will occur in unit outage windows from 2023 to 2029. The total value is estimated between $25-100 million. The solicitation is expected to be issued on Beta.Sam.gov in June 2021 as a fixed-price contract.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W68SBV11532941

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the changes outlined below .

1. CONTRACT ID CODE PAGE OF PAGES

J 1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Jul-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF21R0015

X 9B. DATED (SEE ITEM 11)

16-Jun-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Jul-2021

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

HILLARY A. MORGAN

201 N. THIRD AVENUE

WALLA WALLA WA 99362

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF21R0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

Summary of Changes for McNary Intake Gates and Isophase Bus Systems (McDouble)(21R0015) Amendment 0002

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

FAR 52-211-10: Replaced “Tubular Bus and Lattice Isophase Inspections” with “Isophase Tubular Bus and Steel Lattice Structure Inspections” in items (2) and (3).

SECTION 00 21 00 - INSTRUCTIONS

Bid Schedule:

• CLINs 0050 and 0050AA through 0050AG: Revised title from “Tubular Bus and Lattice Isophase Inspections” with “Isophase Tubular Bus and Steel Lattice Structure Inspections”.

Specifications:

01 11 00.00 28 SUMMARY OF WORK

• 1.3k: Modified to only be a summary of the work rather than the full work requirements. Full work requirements moved to SECTION 26 25 01.00 26 Paragraph 3.1.2

• 1.3l: New paragraph added to summarize the Steel Lattice Inspections

01 12 16.00 26 WORK SEQUENCE

• 1.1 and 1.2: replaced all instances of “Tubular Bus and Lattice Isophase Inspections” with “Isophase Tubular Bus and Steel Lattice Structure Inspections”.

01 14 00.10 28 PROJECT SITE RESTRICTIONS

• 1.4: Replaced “Tubular Bus and Lattice Isophase Inspections” with “Isophase Tubular Bus and Steel Lattice Structure Inspections”.

• 1.15: Added sentence to end of first paragraph to clarify that only one intake gate can be placed/worked on in the Gate Repair Pit at a time.

• 1.18.2: Table under item d revised to include new Juneteenth holidays

01 22 00.00 28 MEASUREMENT AND PAYMENT

• 1.2.2.1: Removed last sentence from item d.

• 1.13: For 1.13 and 1.13.1 through 1.13.7, replaced all instances of “Tubular Bus and Lattice Isophase

Inspections” with “Isophase Tubular Bus and Steel Lattice Structure Inspections”.

26 25 01.00 26 BUS STRUCTURES AND INSTRUMENT TRANSFORMERS

• 1.3: SD-06 Submittal “Existing Tubular Bus Inspections” added (revised submittal register provided)

• 3.1.2: “Existing Tubular Bus Inspections” Added

• 3.1.2: Iso-Phase Bus Installation is now 3.1.3

• 3.1.3: Iso-phase Bus Field tests is now 3.1.4

• 3.1.4: Design and Manufacturing Coordination is now 3.1.5

• 3.10.3c: Revised item (1) in its entirety

Drawings:

• No changes

SECTION 00 21 00 - INSTRUCTIONS

The following have been modified:

Walla Walla District Corps of Engineers McNary Intake Gates and Isophase Bus Systems

The magnitude of construction is estimated to be between $25,000,000 and $100,000,000

ITEM DESCRIPTION QUANTITY U/M U/P

AMOUNT

INTAKE GATES WORK BASE ITEMS

PRE-MAIN UNIT OUTAGE CLINS

0001 Pre-Main Unit Outage Hydraulic System Work 1 JOB XXXXX $_________

0002 Rehabilitate Spare Intake Gate

0002AA Rehabilitate Spare Intake Gate (Gate) 1 JOB XXXXX $_________

0002AB Rehabilitate Spare Intake Gate (Hydraulic) 1 JOB XXXXX $_________

0003 Additional Intake Gate Paint Repair 50 EST* SF $_______ $_________

0004 New Hydraulic Fluid for Pre-Main Unit Outage Work 4205 EST GL $_______ $_________

STATION SERVICE UNIT ONE OUTAGE

CLINS

0005 First Station Service Outage

0005AA Rehabilitate First Station Service Unit (Gate) 1 JOB XXXXX $_________

0005AB Rehabilitate First Station Service Unit (Hydraulic) 1 JOB XXXXX $_________

0005AC New Hydraulic Fluid for First Station Service Unit Outage 385 EST GL $_______ $_________

0005AD Additional Intake Gate Paint Repair for First Station Service Unit Outage 50 EST SF $_______ $_________

INTAKE GATES MAIN UNIT OUTAGE

CLINS

0006 Main Unit Outage One

0006AA Rehabilitate First Main Unit of Main Unit Outage One (Gate) 1 JOB XXXXX $_________

0006AB Rehabilitate First Main Unit of Main Unit Outage One (Hydraulic) 1 JOB XXXXX $_________

0006AC Rehabilitate Second Main Unit of Main Unit Outage One (Gate) 1 JOB XXXXX $_________

0006AD Rehabilitate Second Main Unit of Main Unit Outage One (Hydraulic) 1 JOB XXXXX $_________

0006AE New Hydraulic Fluid for Main Unit Outage One 2300 EST GL $_______ $_________

0006AF Additional Intake Gate Paint Repair for Main Unit Outage One 150 EST SF $_______ $_________

0006AG Training 1 JOB XXXXX $_________

0006AH Spare Parts 1 JOB XXXXX $_________

0007 Main Unit Outage Two

0007AA Rehabilitate First Main Unit of Main Unit Outage Two (Gate) 1 JOB XXXXX $_________

0007AB Rehabilitate First Main Unit of Main Unit Outage Two (Hydraulic) 1 JOB XXXXX $_________

0007AC Rehabilitate Second Main Unit of Main Unit Outage Two (Gate) 1 JOB XXXXX $_________

0007AD Rehabilitate Second Main Unit of Main Unit Outage Two (Hydraulic) 1 JOB XXXXX $_________

0007AE New Hydraulic Fluid for Main Unit Outage Two 2300 EST GL $_______ $_________

0007AF Additional Intake Gate Paint Repair for Main Unit Outage Two 150 EST SF $_______ $_________

0008 Main Unit Outage Three

0008AA Rehabilitate First Main Unit of Main Unit Outage Three (Gate) 1 JOB XXXXX $_________

0008AB Rehabilitate First Main Unit of Main Unit Outage Three (Hydraulic) 1 JOB XXXXX $_________

0008AC Rehabilitate Second Main Unit of Main Unit Outage Three (Gate) 1 JOB XXXXX $_________

0008AD Rehabilitate Second Main Unit of Main Unit Outage Three (Hydraulic) 1 JOB XXXXX $_________

0008AE New Hydraulic Fluid for Main Unit Outage Three 2300 EST GL $_______ $_________

0008AF Additional Intake Gate Paint Repair for Main Unit Outage Three 150 EST SF $_______ $_________

0009 Main Unit Outage Four

0009AA Rehabilitate First Main Unit of Main Unit Outage Four (Gate) 1 JOB XXXXX $_________

0009AB Rehabilitate First Main Unit of Main Unit Outage Four (Hydraulic) 1 JOB XXXXX $_________

0009AC Rehabilitate Second Main Unit of Main Unit Outage Four (Gate) 1 JOB XXXXX $_________

0009AD Rehabilitate Second Main Unit of Main Unit Outage Four (Hydraulic) 1 JOB XXXXX $_________

0009AE New Hydraulic Fluid for Main Unit Outage Four 2300 EST GL $_______ $_________

0009AF Additional Intake Gate Paint Repair for Main Unit Outage Four 150 EST SF $_______ $_________

00010 Main Unit Outage Five

0010AA Rehabilitate First Main Unit of Main Unit Outage Five (Gate) 1 JOB XXXXX $_________

0010AB Rehabilitate First Main Unit of Main Unit Outage Five (Hydraulic) 1 JOB XXXXX $_________

0010AC Rehabilitate Second Main Unit of Main Unit Outage Five (Gate) 1 JOB XXXXX $_________

0010AD Rehabilitate Second Main Unit of Main Unit Outage Five (Hydraulic) 1 JOB XXXXX $_________

0010AE New Hydraulic Fluid for Main Unit Outage Five 2300 EST GL $_______ $_________

0010AF Additional Intake Gate Paint Repair for Main Unit Outage Five 150 EST SF $_______ $_________

0010AG Training 1 JOB XXXXX $_________

00011 Main Unit Outage Six

0011AA Rehabilitate First Main Unit of Main Unit Outage Six (Gate) 1 JOB XXXXX $_________

0011AB Rehabilitate First Main Unit of Main Unit Outage Six (Hydraulic) 1 JOB XXXXX $_________

0011AC Rehabilitate Second Main Unit of Main Unit Outage Six (Gate) 1 JOB XXXXX $_________

0011AD Rehabilitate Second Main Unit of Main Unit Outage Six (Hydraulic) 1 JOB XXXXX $_________

0011AE New Hydraulic Fluid for Main Unit Outage Six 2300 EST GL $_______ $_________

0011AF Additional Intake Gate Paint Repair for Main Unit Outage Six 150 EST SF $_______ $_________

00012 Main Unit Outage Seven

0012AA Rehabilitate First Main Unit of Main Unit Outage Seven (Gate) 1 JOB XXXXX $_________

0012AB Rehabilitate First Main Unit of Main Unit Outage Seven (Hydraulic) 1 JOB XXXXX $_________

0012AC Rehabilitate Second Main Unit of Main Unit Outage Seven (Gate) 1 JOB XXXXX $_________

0012AD Rehabilitate Second Main Unit of Main Unit Outage Seven (Hydraulic) 1 JOB XXXXX $_________

0012AE New Hydraulic Fluid for Main Unit Outage Seven 2300 EST GL $_______ $_________

0012AF Additional Intake Gate Paint Repair for Main Unit Outage Seven 150 EST SF $_______ $_________

INTAKE GATES POST-MAIN UNIT

OUTAGE CLINs

0013 Post-Outage Hydraulic System Work 1 JOB XXXXX $_________

0014 New Hydraulic Fluid for Post-Outage Work 4400 EST GL $_______ $_________

0015 Provide Spare Hydraulic Cylinders 1 JOB XXXXX $_________

0016 Second Station Service Outage

0016AA Rehabilitate Second Station Service Unit (Gate) 1 JOB XXXXX $_________

0016AB Rehabilitate Second Station Service Unit (Hydraulic) 1 JOB XXXXX $_________

0016AC New Hydraulic Fluid for Second Station Service Unit Outage 385 EST GL $_______ $_________

0016AD Additional Intake Gate Paint Repair for Second Station Service Unit Outage 150 EST SF $_______ $_________

INTAKE GATES BASE ITEMS TOTAL $____________

ISOPHASE BUS SYSTEM BASE ITEMS

ISOPHASE BUS SYSTEM WORK FOR

UNITS 1 AND 2

0017 Replace Line 1 230kV Disconnect Switch A490 and Grounding Switch 7516 1 JOB XXXXX $_________

Provide 480 Volt - 240/120 Volt Step-Down Transformer and 120 Volt Load Center at

MCC CQ12

1 JOB XXXXX $_________

0019 Modify Sections of Existing 230kV Tubular Bus at Line 1 1 JOB XXXXX $_________

0020 Replace 230kV Line 1 Surge Arresters on Existing Pedestals 1 JOB XXXXX $_________

0021 Replace 15kV Isophase Bus and Instrument Transformers for Main Units 1 and 2

0021AA

Replace 15kV Isophase Bus and Instrument Transformers from Delta 01 & 02 to Transformer T1

0021AB Replace 15kV Isophase Bus and Instrument Transformers from XJ01 to Delta 01 & 02 1 JOB XXXXX $_________

0021AC Replace 15kV Isophase Bus and Instrument Transformers from XJ02 to Delta 01 & 02 1 JOB XXXXX $_________

UNITS 3 AND 4

0022 Replace Line 2 230kV Disconnect Switch A491 and Grounding Switch 7517 1 JOB XXXXX $_________

Transformer and 120 Volt Load Center at

MCC CQ22

0024 Modify Sections of Existing 230kV Tubular Bus at Line 2 1 JOB XXXXX $_________

0025 Replace 230kV Line 2 Surge Arresters on

Replace 15kV Isolated-Phase Bus and Instrument Transformers For Main Units 3 and 4

0026AA

Transformers from Delta 03 & 04 to Transformer T2

0026AB Replace 15kV Isophase Bus and Instrument Transformers from XJ03 to Delta 03 & 04 1 JOB XXXXX $_________

0026AC Replace 15kV Isophase Bus and Instrument Transformers from XJ04 to Delta 03 & 04 1 JOB XXXXX $_________

UNITS 5 AND 6

Replace Line 3 and Line 4 230kV Disconnect Switches A492 and Grounding Switches 7518

Transformer and 120 Volt Load Center at

MCC CQ32

0029 Modify Sections of Existing 230kV Tubular Bus at Line 3 1 JOB XXXXX $_________

0030 Replace 230Kv Line 3 Surge Arresters on

Replace 15Kv Isolated-Phase Bus and Instrument Transformers for Main Units 5 and 6

0031AA

Transformers from Delta 05 & 06 to Transformer T3

0031AB Replace 15kV Isophase Bus and Instrument Transformers from XJ05 to Delta 05 & 06 1 JOB XXXXX $_________

0031AC Replace 15kV Isophase Bus and Instrument Transformers from XJ06 to Delta 05 & 06 1 JOB XXXXX $_________

UNITS 7 AND 8

0032 Replace Line 4 230kV Disconnect Switch A493 and Grounding Switch 7519 1 JOB XXXXX $_________

Transformer and 120 Volt Load Center at

MCC CQ42

0034 Modify Sections of Existing 230kV Tubular Bus at Line 4 1 JOB XXXXX $_________

0035 Replace 230kV Line 4 Surge Arresters on

Instrument Transformers for Main Units 7 and 8

0036AA

Transformers from Delta 07 & 08 to Transformer T4

0036AB Replace 15kV Isophase Bus and Instrument Transformers from XJ07 to Delta 07 & 08 1 JOB XXXXX $_________

0036AC Replace 15kV Isophase Bus and Instrument Transformers from XJ08 to Delta 07 & 08 1 JOB XXXXX $_________

UNITS 9 AND 10

0037 Replace Line 5 230kV Disconnect Switch A494 and Grounding Switch 7520 1 JOB XXXXX $_________

Transformer and 120 Volt Load Center at

MCC CQ52

0039 Replace 230kV Line 5 Surge Arresters on

Instrument Transformers for Main Units 9 and 10

0040AA

Transformers from Delta 09 & 10 to Transformer T5

0040AB Replace 15kV Isophase Bus and Instrument Transformers from XJ09 to Delta 09 & 10 1 JOB XXXXX $_________

0040AC Replace 15kV Isophase Bus and Instrument Transformers from XJ10 to Delta 09 & 10 1 JOB XXXXX $_________

UNITS 11 AND 12

0041 Replace Line 5 230kV Disconnect Switch A495 and Grounding Switch 7522 1 JOB XXXXX $_________

Transformer and 120 Volt Load Center at

MCC CQ62

0043 Replace 230kV Line 5 Surge Arresters on

Replace 15kV Isolated-Phase (Isophase) Bus and Instrument Transformers for Main Units 11 and 12

0044AA

Transformers from Delta 11 & 12 to Transformer T6

0044AB Replace 15kV Isophase Bus and Instrument Transformers from XJ11 to Delta 11 & 12 1 JOB XXXXX $_________

0044AC Replace 15kV Isophase Bus and Instrument Transformers from XJ12 to Delta 11 & 12 1 JOB XXXXX $_________

UNITS 13 AND 14

0045 Replace Line 6 115kV Disconnect Switch B996 and Grounding Switch 7521 1 JOB XXXXX $_________

Transformer and 120 Volt Load Center at

MCC CQ72

0047 Replace 115kV Line 6 Surge Arresters on

Instrument Transformers for Main Units 13 and 14

0048AA

Transformers from Delta 13 & 14 to Transformer T7

0048AB Replace 15kV Isophase Bus and Instrument Transformers from XJ13 to Delta 13 & 14 1 JOB XXXXX $_________

0048AC Replace 15kV Isophase Bus and Instrument Transformers from XJ14 to Delta 13 & 14 1 JOB XXXXX $_________

0049 Isophase Bus System Training 1 JOB XXXXX $_________

0050 Isophase Tubular Bus and Steel Lattice Structure Inspections

0050AA Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 1 & 2 1 JOB XXXXX $_________

0050AB Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 3 & 4 1 JOB XXXXX $_________

0050AC Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 5 & 6 1 JOB XXXXX $_________

0050AD Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 7 & 8 1 JOB XXXXX $_________

0050AE Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 9 & 10 1 JOB XXXXX $_________

0050AF Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 11 & 12 1 JOB XXXXX $_________

0050AG Isophase Tubular Bus and Steel Lattice Structure Inspections for Units 13 & 14 1 JOB XXXXX $_________

0051 Transformer Bank Oil Draining, Processing, and Refilling Submittals 1 JOB XXXXX $_________

ISOPHASE BUS SYSTEM BASE ITEMS TOTAL $_____________

ISOPHASE BUS SYSTEM OPTIONAL ITEMS

0052 Transformer Bank T1 Transformer Tank Oil Draining, Processing, And Refilling 3 NTE* EA $_______ $_________

0053 Transformer Bank T2 Transformer Tank Oil Draining, Processing, And Refilling 3 NTE EA $_______ $_________

0054 Transformer Bank T3 Transformer Tank Oil

0055 Transformer Bank T4 Transformer Tank Oil

0056 Transformer Bank T5 Transformer Tank Oil

0057 Transformer Bank T6 Transformer Tank Oil

0058 Transformer Bank T7 Transformer Tank Oil

ISOPHASE BUS SYSTEM OPTIONAL ITEMS TOTAL $____________

SCHEDULE TOTAL (BASE + OPTIONAL ITEMS)

IMPORTANT See Section 01 22 00.00 28; MEASUREMENT AND PAYMENT; Paragraph; Retainage of Payment, for withholding of payment for final deliverables.

NTE*: Not to Exceed

EST* = Estimated Quantities identified as Estimated (“EST”) in the bid schedule are subject to FAR Clause 52.211-18, VARIATION IN ESTIMATED QUANTITY

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than the dates listed below.

(1) The Contractor shall complete all work for the McNary Intake Gates and Isophase Bus Systems by not later than April 30, 2030 with the exception of items (8) through (10) below.

(2) Onsite construction at McNary Dam may begin any time after the contractor receives Notice to Proceed (NTP), all preconstruction contract requirements are completed, and all required preconstruction submittals are approved, subject to restrictions outlined below. See SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS, SECTION 01 12 16.00 26 WORK SEQUENCE and SECTION 01 91 00.00 26 SYSTEM TESTING AND COMMISSIONING for additional information and restrictions related to the Isophase Tubular Bus and Steel Lattice Structure Inspections Windows, Pre-Main Unit Work Window, seven Main Unit Outage Work Windows, one Station Service Unit Outage Work Window, Post-Main Unit Outage Work Window, scheduling, and executing work on this Contract.

(3) Isophase Tubular Bus and Steel Lattice Structure Inspections Windows

a. The Contractor shall perform inspections associated with each adjacent pair of main units. The windows to perform and complete the inspections, to include submitting the inspection report, are:

a. Main Units 3&4 January 29, 2022 to May 7, 2022

b. Main Units 1&2 August 21, 2022 to November 3, 2022

c. Main Units 13&14 February 17, 2023 to May 02, 2023

d. Main Units 9&10 and 11&12 February 12, 2024 to April 26, 2024

e. Main Units 7&8 August 10, 2024 to October 23, 2024

f. Main Units 5&6 February 6, 2025 to April 21, 2025

(4) Pre-Main Unit Outage Work Window.

a. The Pre-Main Unit Outage Work Window will start January 23, 2023 and end May 14, 2023.

b. The Contractor shall complete all work for CLINs 0001 to 0005 during this window.

c. All parts required for Main Unit Outage Work Window 1 shall be on-site by the end of this work window.

(5) Main Unit Outage Work Windows.

a. There will be seven (7) main unit outage work windows for the performance of this contract. Main Units will be taken out of service in adjacent pairs (Main Units 1 & 2; Main Units 3 & 4; Main Units 5 & 6; Main Units 7 & 8; Main Units 9 & 10; Main Units 11 & 12; Main Units 13 & 14). The following is the order the pair of units will be taken out of service and the start and end dates for the 7 outages:

MAIN UNIT OUTAGE WORK WINDOWS START and END DATES

i. Work Window 1: Main Units 3 and 4 May 15, 2023 – November 20, 2023

ii. Work Window 2: Main Units 13 and 14 May 13, 2024 – November 18, 2024

iii. Work Window 3: Main Units 11 and 12 May 12, 2025 – November 17, 2025

iv. Work Window 4: Main Units 9 and 10 May 11, 2026 – November 16, 2026

v. Work Window 5: Main Units 7 and 8 May 17, 2027 – November 22, 2027

vi. Work Window 6: Main Units 5 and 6 May 15, 2028 – November 20, 2028

vii. Work Window 7: Main Units 1 and 2 May 14, 2029 – November 19, 2029

b. The Main Unit Outage Work Window 1 will start on the date listed above in paragraph (5)a. and the

Government will start to unwater the first unit provided all Pre-Main Unit Outage work is completed and all parts required for Main Unit Outage Work Window 1 are on-site.

c. For Main Unit Outage Work Windows 2 through 7, the outage will start on the date listed in subparagraph (5)a. above. The Government will start to unwater the first unit provided the rehabilitation work on the intake gate from the previous outage has been completed and all parts required for that Main Unit Outage Work Window are on-site.

d. During Main Unit Outage Work Window 3, in addition to Main Units 11 and 12 being off-line, Main Units 9 and 10 will be off-line from September 1-30, 2025. During the Unit 9 and 10 outage, the Contractor shall perform all disconnect switch replacement work associated with all 4 units.

e. During Main Unit Outage Work Window 5, in addition to Main Units 7 and 8 being off-line, Main Units 5 and 6 will be off-line from September 1-30, 2027. During the Unit 5 and 6 outage, the Contractor shall perform all disconnect switch replacement work associated with all 4 units.

f. At the completion of each of the 7 Main Unit Outages, the Contractor is required to successfully complete all work and commissioning for the Intake Gates and the Isophase Bus System. The one exception to this is completing the rehabilitation of the third intake gate from the second main unit for that outage.

a. For Main Unit Outage Work Window 1, gate rehabilitation shall be performed and completed by the Station Service Unit One Outage Work Window completion date.

b. For Main Unit Outage Work Windows 2 through 6, the gate rehabilitation shall be completed not later than 60 days from the completion of operational commissioning for the Intake Gates for that outage.

c. For Main Unit Outage Work Window 7, the gate rehabilitation shall be performed and completed by the Post-Main Unit Outage Work Window completion date.

(6) Station Service Unit One Outage Work Window.

a. The Station Service Unit One Outage Work is authorized to start as soon as a bulkhead is available from the successful completion of gate commissioning for the second unit for Main Unit Outage Work Window 1.

b. The Contractor shall complete all work, including commissioning, on the Station Service One gate and complete rehabilitation only on the gate located in the gate repair pit at the end of Main Unit Outage Work Window 1 by February 22, 2024.

(7) Post-Main Unit Outage Work Window.

a. Post-Main Unit Outage Work is authorized to start as soon as a bulkhead is available from the successful completion of gate commissioning for the second unit for Main Unit Outage Work Window 7. All Post- Main Unit Outage Work shall be completed by April 30, 2030.

b. Station Service Unit Two Outage work is authorized to start as soon as a bulkhead is available from the successful completion of gate commissioning for the second unit for Main Unit Outage Work Window 7.

All work shall be completed, to include commissioning of the remaining gate from work completed under Main Unit Outage Work Window 7 and the Station Service Unit Two gate, by April 30, 2030.

(8) The Contractor shall complete final cleanup and demobilization by not later than 30 calendar days after completion of work in (7) above.

(9) The Contractor shall submit the updated final O&M manuals for work window 7 by not later than 30 days after substantial completion of work in (7) above. See SECTION 01 78 00.00 28 OPERATION AND MAINTENANCE DATA for additional information.

(10) The Contractor shall deliver the final spare parts and submit final as-built drawings and Contractor prepared shop drawings for Post-Main Unit Outage Work Window by not later than 30 days after substantial completion of work in (7) above. The Contractor shall submit Record Drawings for Outage Window 7 pair of units by not later than 30 days from receiving Government approval of the final as-built drawings. See SECTION 01 78 00.00 28 CLOSEOUT SUBMITTALS for additional information.

The completion date listed in item (1) above is based on the assumption that the successful offeror will receive the notice to proceed by December 10, 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of Clause)

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

General Decision Number: OR20210077 06/18/2021

Superseded General Decision Number: OR20200077

State: Oregon

Construction Type: Heavy

County: Umatilla County in Oregon.

HEAVY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/01/2021 1 04/02/2021 2 06/18/2021

CARP0001-038 06/01/2020

Rates Fringes

CARPENTER (Excluding Form Work)............................$ 41.75 18.30

MILLWRIGHT.......................$ 43.26 18.75

* ELEC0112-004 06/01/2021

Rates Fringes

ELECTRICIAN......................$ 50.00 22.93

ENGI0701-040 01/01/2020

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 45.90 15.35

GROUP 1A....................$ 48.06 15.35

GROUP 1B....................$ 50.22 15.35

GROUP 2.....................$ 43.99 15.35

GROUP 3.....................$ 42.84 15.35

GROUP 4.....................$ 41.01 15.35

GROUP 5.....................$ 39.77 15.35

GROUP 6.....................$ 36.55 15.35

POWER EQUIPMENT OPERATORS CLASSIFICATIONS

GROUP 1: CRANE: Helicopter Operator, when used in erecting work; Whirley Operator, 90 ton and over; LATTICE BOOM CRANE: Operator 200 tons through 299 tons, and/or over 200 feet boom; HYDRAULIC CRANE: Hydraulic Crane Operator 90 tons through 199 tons with luffing or tower attachments;

GROUP 1A: HYDRAULIC CRANE: Hydraulic Operator, 200 tons and over (with luffing or tower attachment); LATTICE BOOM CRANE: Operator, 200 tons through 299 tons, with over 200 feet boom;

GROUP 1B: LATTICE BOOM CRANE: Operator, 300 tons through 399 tons with over 200 feet boom; Operator 400 tons and over

GROUP 2: CRANE: Cableway Operator, 25 tons and over;

HYDRAULIC CRANE: Hydraulic crane operator 90 tons through 199 tons (without luffing or tower attachment);

TOWER/WHIRLEY OPERATOR: Tower Crane Operator; Whirley Operator, under 90 tons; LATTICE BOOM CRANE: 90 through 199 tons and/or 150 to 200 feet boom; HYDRAULIC CRANE:

Hydraulic crane operator, 50 tons through 89 tons (with luffing or tower attachment); Rubber tired scraper with tandom scrapers; Loader 120,000 lbs and above; BLADE: Auto Grader; Blade Operator-Robotic; Bulldozer over 120,000 lbs and above;

GROUP 3: HYDRAULIC CRANE: Hydraulic crane operator, 50 tons through 89 tons (without luffing or tower attachment);

LATTICE BOOM CRANES: Lattice Boom Crane-50 through 89 tons (and less than 150 feet boom); Rubber Tired Scraper: with tandom scrapers; self loading, paddle wheel, auger type, finish and/or 2 or more units; Loader 60,000 lbs and less than 120,000 lbs; Bulldozer over 70,000 lbs up to and including 120,000 lbs;

GROUP 4: CRANE: Hydraulic Crane Operator, under 50 tons;

LATTICE BOOM CRANE OPERATOR: Lattice Boom Crane Operator, under 50 tons; TRACKHOE/BACKHOE-ROBOTIC: track and wheel type, up to and including 20,0000 lbs. with any or all attachments; BLADE: Blade Operator; Tractor operator with boom attachment; DRILLING: Churm Drill and Earth Boring Machine Operator; Directional Drill Operator over 20,000 lbs pullback; CRANE: Chicago boom and similar types; Boom type lifting device, 5 ton capacity or less; Rubber-Tired Scraper, single engine, single scraper; Compactor-Self Propelled; Loaders 25,000 lbs and less than 60,000 lbs;

Bulldozer over 20,000 lbs and more than 100 horse up to 70,000 lbs; Screed; Compactor with blade; Mechanic

GROUP 5: TRACKHOE/BACKHOE HYDRAULIC: Track type up to and including 20,000 lbs, Wheel type (Ford, John Deer, Case Type); Boom truck operator; DRILLING: Churm Drill and Earth Boring Machine Operator; Directional Drill Operator less than 20,000 lbs pullback; Loaders, rubber tired type , less than 25,00 lbs; Forklift over 5 ton, Bulldozer 20,000 lbs or 100 horses or less; Roller; Compactor without blade

GROUP 6: LOADERS: (less than 1 cu yd.); Oiler; Grade Checker; Crane oiler; Forklift; Roller (non-asphalt)

Zone Differential (add to Zone 1 rates):

Zone 2 - $3.00 Zone 3 - $6.00

For the following metropolitan counties: MULTNOMAH;

CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA;

CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS

INDICATED:

All jobs or projects located in Multnomah, Clackamas and Marion Counties, West of the western boundary of Mt. Hood National Forest and West of Mile Post 30 on Interstate 84 and West of Mile Post 30 on State Highway 26 and West of Mile Post 30 on Highway 22 and all jobs or projects located in Yamhill County, Washington County and Columbia County and all jobs or porjects located in Clark & Cowlitz County, Washington except that portion of Cowlitz County in the Mt.

St. Helens ""Blast Zone"" shall receive Zone I pay for all classifications.

All jobs or projects located in the area outside the identified boundary above, but less than 50 miles from the Portland City Hall shall receive Zone II pay for all classifications.

All jobs or projects located more than 50 miles from the Portland City Hall, but outside the identified border above, shall receive Zone III pay for all classifications.

For the following cities: ALBANY; BEND; COOS BAY; EUGENE;

GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG

All jobs or projects located within 30 miles of the respective city hall of the above mentioned cities shall receive Zone I pay for all classifications.

All jobs or projects located more than 30 miles and less than 50 miles from the respective city hall of the above mentioned cities shall receive Zone II pay for all classifications.

All jobs or projects located more than 50 miles from the respective city hall of the above mentioned cities shall receive Zone III pay for all classifications.

IRON0029-013 07/01/2020

IRONWORKER (Reinforcing and Structural)......................$ 39.10 29.75

LABO0737-005 06/01/2020

Rates Fringes

Laborers: (Mason Tender-Cement/Concrete)..........$ 32.71 15.40

LABO0737-031 06/01/2020

Rates Fringes

Laborers:

GROUP 1.....................$ 31.83 15.40

GROUP 2.....................$ 33.01 15.40

LABORER CLASSIFICATIONS

GROUP 1: Asphalt Spreader

GROUP 2: Grade Checker

PAIN0055-022 07/01/2020

Rates Fringes

PAINTER

BRUSH, ROLLER AND SPRAY.....$ 25.94 13.34

PLUM0598-007 06/01/2019

Rates Fringes

Plumbers and Pipefitters.........$ 50.47 32.17

SUOR2009-075 11/23/2009

CARPENTER (Form Work Only).......$ 23.50 9.27

CEMENT MASON/CONCRETE FINISHER...$ 21.13 8.90

LABORER: Common or General......$ 21.05 4.38

LABORER: Fence Erection.........$ 23.88 7.45

LABORER: Flagger................$ 19.31 5.31

LABORER: Pipelayer..............$ 20.52 4.51

LINE CONSTRUCTION: Groundman....$ 31.36 7.27

OPERATOR: Bobcat/Skid Steer/Skid Loader................$ 22.77 7.90

OPERATOR: Broom/Sweeper.........$ 32.31 6.43

OPERATOR: Excavator.............$ 30.12 6.23

OPERATOR: Paver (Asphalt, Aggregate, and Concrete).........$ 27.59 2.96

TRUCK DRIVER: Dump Truck........$ 23.79 5.95

TRUCK DRIVER: Off the Road Truck............................$ 31.81 6.33

TRUCK DRIVER: Water Truck.......$ 26.12 6.53

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

(End of Summary of Changes)

McNary Intake Gates and Isophase Bus Systems (McDouble) W912EF21R0015 amend 0002

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15.00 28 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 28 GENERAL REQUIREMENTS

01 11 00.00 28 SUMMARY OF WORK

01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS

01 12 16.00 26 WORK SEQUENCE

01 14 00.10 28 PROJECT SITE RESTRICTIONS

01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY

(OPSEC)

01 20 00.00 20 PRICE AND PAYMENT PROCEDURES

01 22 00.00 28 MEASUREMENT AND PAYMENT

01 32 01.00 28 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 28 CONTRACTOR QUALITY CONTROL

01 51 00.00 28 TEMPORARY UTILITIES

01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS

01 57 20.00 28 ENVIRONMENTAL PROTECTION

01 78 00.00 28 CLOSEOUT SUBMITTALS

01 78 23.00 28 OPERATION AND MAINTENANCE DATA

01 91 00.00 26 SYSTEMS TESTING AND COMMISSIONING

DIVISION 03 - CONCRETE

03 60 00.01 26 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND

MINOR EQUIPMENT FOUNDATIONS

DIVISION 05 - METALS

05 00 00.01 26 INTAKE GATE STRUCTURE REHABILITATION

05 05 23.17 26 WELDING (STEEL), FABRICATION, AND MACHINE WORK

05 50 03.01 26 METALWORK FABRICATION, MACHINE WORK, AND MISCELLANEOUS

PROVISIONS

05 50 04.01 26 METALS: MISCELLANEOUS, STANDARD ARTICLES, SHOP FABRICATED

ITEMS

05 56 09.00 26 INTAKE GATE SEALS

DIVISION 09 - FINISHES

09 97 02.13 26 PAINTING - HYDRAULIC STRUCTURES

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

DIVISION 26 - ELECTRICAL

26 05 00.00 26 BASIC ELECTRICAL MATERIALS AND METHODS FOR ISOPHASE

SYSTEMS

26 05 01.00 26 BASIC ELECTRICAL MATERIALS AND METHODS FOR INTAKE GATES

26 05 19.00 26 INSULATED WIRE AND CABLE FOR ISOPHASE SYSTEMS

PROJECT TABLE OF CONTENTS Page 1

26 05 19.01 26 INSULATED WIRE AND CABLE FOR INTAKE GATES

26 05 26.00 26 GROUNDING AND GROUND TESTING

26 05 33.00 26 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 25 01.00 26 BUS STRUCTURES AND INSTRUMENT TRANSFORMERS

26 42 14.01 26 CATHODIC PROTECTION BY SACRIFICIAL ANODES

DIVISION 33 - UTILITIES

33 56 53.00 26 REHABILITATION OF OIL STORAGE TANKS

33 75 10.00 26 HIGH VOLTAGE GROUP-OPERATED DISCONNECT SWITCHES AND

GROUNDING SWITCHES

33 78 26.00 26 HIGH VOLTAGE SURGE ARRESTERS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 05 40.14 26 HYDRAULIC POWER SYSTEMS FOR CIVIL WORKS STRUCTURES

35 05 40.15 26 HYDRAULIC FLUID

DIVISION 40 - PROCESS INTERCONNECTIONS

40 05 13.96 26 WELDING: PIPING AND PRESSURIZED SYSTEMS

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.75 26 NEW SUPPORT BEAMS

DIVISION 48 - ELECTRICAL POWER GENERATION

48 19 23.60 26 (OPTIONAL) CLASS II GSU POWER TRANSFORMER OIL DRAINING

AND FILLING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00.00 28

SUMMARY OF WORK

PART 1 GENERAL

1.1 DEFINITIONS

1.2 SUMMARY OF WORK FOR INTAKE GATES

1.3 SUMMARY OF WORK FOR ISOPHASE BUS SYSTEMS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

-- End of Section Table of Contents --

SECTION 01 11 00.00 28 Page 1

SECTION 01 11 00.00 28

SUMMARY OF WORK

PART 1 GENERAL

This section provides a general overview of the work required under the Contract and may therefore not be inclusive of all work required. Detailed requirements are provided in other technical specification sections and drawings. In the case of discrepancy or omission, the requirements of the detailed sections and drawings shall govern.

1.1 DEFINITIONS

In these Specifications, the word "provide" means to "furnish" and "install" inclusive of any other activities such as design, fabrication, and testing or any other activity to make the equipment or system ready for use.

1.2 SUMMARY OF WORK FOR INTAKE GATES

The work covered by this contract for the Intake Gates portion includes the following:

a. Rehabilitate 45 intake gates including work to replace the seals, seal bars, seal hardware, replace anodes, and perform touch up painting.

b. Inspect sealing bar surfaces for 44 intake gate slots.

c. Provide 92 new hydraulic cylinders: 90 cylinder assemblies to be installed in gates plus two additional cylinder assemblies that will be placed into long term storage as spares.

d. Provide 45 new support beams for 45 intake gates.

e. Provide a new hydraulic power unit, including new motor starters, breakers, and other electrical and control components.

f. Provide new high and low pressure hydraulic fluid header piping system.

g. Provide new 47 new flexible hose assemblies: 44 sized for main units and 3 sized for station service units.

h. Provide 14 new main unit control consoles and 2 station service unit control consoles, inclusive of all new electrical and control components.

i. Replace the accumulator tanks located at the control console for each unit. Add one additional accumulator tank per unit to provide back-up mechanical energy storage.

j. Provide approximately 26,000 gallons of new hydraulic fluid.

k. Rehabilitate the 4 existing oil storage tanks and transfer piping, including the installation of four off-line oil filtration systems..

SECTION 01 11 00.00 28 Page 2

l. Rehabilitate the existing gate position indicating system.

m. Inspect and rehabilitate gate dog system, including replacing components, for 44 intake gate slots and verifying the elevation of each gate dog..

n. Add emergency gate closure switches to the control room main unit switchboards.

o. Provide cable and conduit for system power, controls and annunciation.

p. Remove and dispose of existing:

1) Intake gate seals, seal bars, anodes, and hardware

2) 90 hydraulic cylinders

3) 45 support beams

4) Hydraulic power unit

5) High and low pressure headers

6) Flexible hose assemblies for 44 intake gate slots

7) 14 main unit control consoles and 2 station service unit control consoles

8) Approximately 26,000 gallons of hydraulic fluid.

9) Electrical and control equipment associated with the above items.

q. Provide as-built drawings, operations manual, training, and operations and maintenance manual, and spare parts as specified.

1.3 SUMMARY OF WORK FOR ISOPHASE BUS SYSTEMS

The work covered by this contract for the Isophase Bus Systems portion includes the following:

a. Replace existing 15kV 4,000 amp copper isophase bus including in-line current transformers and 2,500 amp copper delta isophase bus with new 15kV aluminum isophase bus rated 5,000 amp including in-line current transformers and new aluminum delta isophase rated 3,000 amp from the main unit generator barrels to the GSU transformer banks. All bus must be able to pass through existing floor openings. The GSU transformer banks must be partially moved out of their vaults, requiring temporary removal of the radiators, then reinstalled, moved back in place and tested under supervision of an approved field engineer to facilitate isophase bus replacement.

b. Replace seven (7) existing 15kV 3-phase synchronizing potential transformer cubicles with potential transformers with fourteen (14) new 15kV 3-phase synchronizing potential transformer cubicles with potential transformers, complete with wiring to the Control Room via the S-boards.

SECTION 01 11 00.00 28 Page 3

c. Replace the existing 230kV tubular aluminum bus segments for all phases, phase A, phase B, and phase C, at Lines 1 through 4 with new reconfiguration, including slip fittings and end caps. The vertical segment is to be replaced with a 30-degree "crow's foot" assembly to distribute the static weight loads on the horizontal segment.

d. Replace seven (7) existing manual group-operated disconnect switches and six (6) manually-operated ground switches with seven (7) new motorized group-operated disconnect switches (MOD's) equipped with surge suppression resistors and seven (7) manual ground switches, including Kirk key interlocks, and electrical interlocks. The first six sets of switches are 230kV, the seventh set of switches is 115kV.

The first five 230kV disconnect/ground switches have larger than standard phase spacing requiring each phase to be mounted separately.

e. Provide (7) 480 volt - 240/120 volt step-down transformers and 120 volt load centers near existing 480 volt motor control centers (MCC's) to provide power and control for the new MOD's. Provide new 2-pole 480 volt breakers in the MCC's to power the step-down transformers. The new bucket required to be compatible with existing MCC will be required, field verify and match existing.

f. Provide new wire and cable connections to existing pistol grip control switches with red and green position indication lights for the seven new MOD switches, both locally at each S board and in the Control Room on the SC board. The pistol grip control switches will be supplied and installed by others but not wired.

g. Replace the (3) 115kV and (18) 230kV surge arresters on the deck behind the GSU transformers.

h. Perform field acceptance testing and commissioning of the seven (7) transformer banks and all new installed equipment.

i. Provide as-built drawings, operations manual, training, and operations and maintenance manual, and spare parts as specified.

j. Optional draining: - Entire tank of up to 21 transformers may need to be drained, refilled, and tested, in the event of a radiator isolating valve failing while draining the radiators for transformer movement.

k. High-Voltage Tubular Bus Visual Inspection: Prior to removing the high voltage disconnect switches and/or high voltage tubular bus segments, pPerform a visual inspection of the entire tubular bus system from GSU transformer bushings to the line connection including horizontal sections on both sides of the disconnect switch.