W68SBV50771656
CONSTRUCTION PROJECT: ICE HARBOR DAM REWINDS AND TURBINE RUNNER REPLACEMENTS
PHYLLIS L BUERSTATTE 509-527-7211
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
01-Sep-2015
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________00700
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________6 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________27 Oct 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
USAED, WALLA WALLA - CONTRACTING DIV.
PHYLLIS L. BUERSTATTE
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
509-527-7802FAX:TEL: 509-527-7211 TEL: FAX:
W912EF-15-R-0044 111
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912EF-15-R-0044
Section 00010 - Solicitation Contract Form
ATTENTION TO OFFERORS
Offeror(s) may be asked to provide the following information for the Government’s use in the determination of offeror(s) responsibility, pursuant to FAR Part 9. Do not include it with your offer.
1. Current Balance Sheet and latest Profit and Loss Statement prepared from the most recent fiscal/calendar year and certified by an officer of the company.
2. The name of your banking institution, telephone number and the name of the individual to contact for a line-of-credit reference. (If you are the apparent low bidder, please contact your bank reference to let him/her know our office will be calling for financial information.)
Bank Institution ________________________________ Telephone Number ______________________________ Contact ________________________________________ Email Address __________________________________
3. Tax Identification Number ________________________
4. List of present work to include agency or firm name, address, telephone number, and email address of primary point of contact responsible for inspection and acceptance of the work. (Attach list) Will performance of the present work inhibit your ability to perform this contract? ___________
5. Offeror’s email address: ____________________________________
Return completed form with all attachments to:
Email: Phyllis.L.Buerstatte@usace.army.mil
OR
Physical/Mailing Address: Walla Walla District Corps of Engineers, 201 North Third Avenue, Walla Walla, WA 99362-1876.
mailto:Phyllis.L.Buerstatte@usace.army.mil
Section 00100 - Bidding Schedule/Instructions to Bidders
BID SCHEDULE
Walla Walla District Corps of Engineers Ice Harbor Turbine Installation and Rewind Units 1-3
The magnitude of construction is estimated to be between $25,000,000 and $100,000,000
ITEM DESCRIPTION QUANTITY U/M U/P AMOUNT
BASE ITEMS APPLICABLE TO ALL UNITS
1001 Mobilization And Demobilization 1 JOB XXXXX $________ 1002 Furnish Special Tools, Equipment
And Scaffolding
1 JOB XXXXX $________
1003 Furnish Spare RTDs And Relays 1 JOB XXXXX $________ 1004 Furnish Turbine Maintenance
Platform
1 JOB XXXXX $________
1005 Drain and Dispose of Dirty Oil from Tanks and Piping
Est.
17,500
GAL $________ $________
1006 Supply Clean Oil for Tank and Piping
Est. 9,500 GAL $________ $________
1007 Manufacture Prototype Coils And Perform Accelerated Life Test
1 JOB XXXXX $________
1008 Manufacture Prototype Coils And Perform Thermal Cycling Test
1 JOB XXXXX $________
1009 Furnish Generator Spare Parts 1 JOB XXXXX $________ 1010 Furnish Stator Core Materials And
Accessories for One Generating Unit Including Factory Tests
1 JOB XXXXX $________
1011 Perform Minor Stator Core Iron Repair
NTE 480 HR $________ $________
1012 Perform Special Field Tests 1 JOB XXXXX $________
1013 Disposal of Hydraulic and Lubricating Oil Units 4, 5 and 6
Est.
24,000
GAL $________ $________
1014 Provision of Hydraulic and Lubricating Oil Units 4, 5 and 6
Est.
24,000
GAL $________ $________
1015 Furnish Unit 2 Makup Oil Est. 750 GAL $________ $________
TOTAL BASE ITEMS APPLICABLE TO ALL UNITS $___________
BASE ITEMS APPLICABLE TO UNIT 2
2001 Phase 1 Thrust Bearing Inspection Unit 2 (Shoes, Runner, & Other)
1 JOB XXXXX $________
2002 Inspection Of Turbine And Generator Guide Bearings Unit 2
1 JOB XXXXX $________
2003 Replace Generator Air Coolers, Piping And Valves Unit 2
1 JOB XXXXX $________
2004 Replace Generator Cooling Water Air Operated Valves Unit 2
1 JOB XXXXX $________
2005 Construct Draft Tube Roof Fill Unit
1 JOB XXXXX $________
2006 Furnish Complete Set Of Stator Coils, Supplies And Accessories for a Complete New Winding Including Factory Testing Unit 2
1 JOB XXXXX $________
2007 Remove Existing Stator Winding, Install And Test New Stator Winding Unit 2
1 JOB XXXXX $________
2008 Inspect, Clean And Test Stator Core Unit 2
1 JOB XXXXX $________
2009 Inspect, Clean And Test Rotor Unit
1 JOB XXXXX $________
2010 Lead Based Paint Removal Including Disposal Unit 2
Est. 1,500 SF $________ $________
2011 Painting Unit 2 1 JOB XXXXX $________
2012 Disposal of Hydraulic and Lubricating Oil Unit 2
Est. 4,500 GAL $________ $________
2013 Disposal of Hub/Shafting Water Unit 2
Est. 2,000 GAL $________ $________
2014 Provision of Hydraulic and Lubricating Oil Unit 2
Est. 4,500 GAL $________ $________
2015 Pre-Disassembly Watered Operational Testing Unit 2
1 JOB XXXXX $________
2016 Generating Unit Disassembly Unit 2 1 JOB XXXXX $________
2017 Generating Unit Reassembly Unit 2 1 JOB XXXXX $________
2018 Commissioning for Turbine Replacement and Generator Rewind Unit 2
1 JOB XXXXX $________
2019 Refurbish Wicket Gates Unit 2 1 JOB XXXXX $________
2020 Stay Vane/Ring Refurbishment and Extension Installation Unit 2
1 JOB XXXXX $________
2021 Refurbish Bottom Ring Unit 2 1 JOB XXXXX $________
2022 Furnish Wicket Gate Operating Mechanism Bushings and Bearing Plate Unit 2
1 JOB XXXXX $________
2023 Refurbish Miscellaneous Wicket Gate Operating Mechanism Components Unit 2
1 JOB XXXXX $________
2024 Line Boring and Installation of Wicket Gate Stem Bushings Unit 2
1 JOB XXXXX $________
2025 Refurbish/Replace Turbine Air Admission Valves Unit 2
1 JOB XXXXX $________
2026 Refurbish Operating Ring Unit 2 1 JOB XXXXX $________
2027 Refurbish Wicket Gate Servomotors Unit 2
1 JOB XXXXX $________
2028 Modification of Unit 2 For Fixed Blade Operation
1 JOB XXXXX $________
2029 Furnish and Install Turbine Water and Oil Piping Systems and Accessories Unit 2
1 JOB XXXXX $________
2030 Install Discharge Ring and Draft Tube Liner Transition Unit 2
1 JOB XXXXX $________
2031 Provide Electrical Equipment, Wiring, Removal, Installation Unit 2
1 JOB XXXXX $________
2032 Refurbish/Modify Intermediate Headcover Unit 2
1 JOB XXXXX $________
2033 Refurbish Outer Headcover Unit 2 1 JOB XXXXX $________
2034 Refurbish Turbine Shaft Unit 2 1 JOB XXXXX $________
2035 Refurbish Intermediate and Generator Shafts Unit 2
TOTAL BASE ITEMS APPLICABLE TO UNIT 2 $___________
BASE ITEMS APPLICABLE TO UNIT 3
3001 Phase 1 Thrust Bearing Inspection Unit 3 (Shoes, Runner, & Other)
1 JOB XXXXX $________
3002 Inspection Of Turbine And Generator Guide Bearings Unit 3
1 JOB XXXXX $________
3003 Replace Generator Air Coolers, Piping And Valves Unit 3
1 JOB XXXXX $________
3004 Replace Generator Cooling Water Air Operated Valves Unit 3
1 JOB XXXXX $________
3005 Construct Draft Tube Roof Fill Unit
1 JOB XXXXX $________
3006 Furnish Complete Set Of Stator Coils, Supplies And Accessories for a Complete New Winding Including Factory Testing Unit 3
1 JOB XXXXX $________
3007 Remove Existing Stator Winding, Install And Test New Stator Winding Unit 3
1 JOB XXXXX $________
3008 Inspect, Clean And Test Stator Core Unit 3
1 JOB XXXXX $________
3009 Inspect, Clean And Test Rotor Unit
1 JOB XXXXX $________
3010 Lead Based Paint Removal Including Disposal Unit 3
Est. 1,500 SF $________ $________
3011 Painting Unit 3 1 JOB XXXXX $________
3012 Disposal of Hydraulic and Lubricating Oil Unit 3
Est. 4,500 GAL $________ $________
3013 Disposal of Hub/Shafting Water Unit 3
Est. 2,000 GAL $________ $________
3014 Provision of Hydraulic and Lubricating Oil Unit 3
Est. 6,900 GAL $________ $________
3015 Pre-Disassembly Watered Operational Testing Unit 3
1 JOB XXXXX $________
3016 Generating Unit Disassembly Unit 3 1 JOB XXXXX $________
3017 Generating Unit Reassembly Unit 3 1 JOB XXXXX $________
3018 Commissioning for Turbine Replacement and Generator Rewind Unit 3
3019 Refurbish Wicket Gates Unit 3 1 JOB XXXXX $________
3020 Stay Vane/Ring Refurbishment and Extension Installation Unit 3
1 JOB XXXXX $________
3021 Refurbish Bottom Ring Unit 3 1 JOB XXXXX $________
3022 Furnish Wicket Gate Operating Mechanism Bushings and Bearing Plate Unit 3
1 JOB XXXXX $________
3023 Refurbish Miscellaneous Wicket Gate Operating Mechanism Components Unit 3
1 JOB XXXXX $________
3024 Line Boring and Installation of Wicket Gate Stem Bushings Unit 3
1 JOB XXXXX $________
3025 Refurbish/Replace Turbine Air Admission Valves Unit 3
1 JOB XXXXX $________
3026 Refurbish Operating Ring Unit 3 1 JOB XXXXX $________
3027 Refurbish Wicket Gate Servomotors Unit 3
1 JOB XXXXX $________
3028 Furnish and Install Turbine Water and Oil Piping Systems and Accessories Unit 3
1 JOB XXXXX $________
3029 Install Discharge Ring and Draft Tube Liner Transition Unit 3
1 JOB XXXXX $________
3030 Refurbish/Modify Intermediate Headcover Unit 3
1 JOB XXXXX $________
3031 Provide Electrical Equipment, Wiring, Removal, Installation Unit 3
1 JOB XXXXX $________
3032 Refurbish Turbine Shaft Unit 3 1 JOB XXXXX $________
3033 Refurbish Intermediate and Generator Shafts Unit 3
1 JOB XXXXX $________
3034 Refurbish Blade Operating Mechanism Components Unit 3
TOTAL BASE ITEMS APPLICABLE TO UNIT 3 $___________
OPTIONAL BASE ITEMS APPLICABLE TO UNIT 1
4001 Phase 1 Thrust Bearing Inspection Unit 1 (Shoes, Runner, & Other) (Optional)
1 JOB XXXXX $________
4002 Inspection Of Turbine And Generator Guide Bearings Unit 1 (Optional)
1 JOB XXXXX $________
4003 Replace Generator Air Coolers, Piping And Valves Unit 1 (Optional)
1 JOB XXXXX $________
4004 Replace Generator Cooling Water Air Operated Valves Unit 1 (Optional)
1 JOB XXXXX $________
4005 Construct Draft Tube Roof Fill Unit 1 (Optional)
1 JOB XXXXX $________
4006 Furnish Complete Set Of Stator Coils, Supplies And Accessories for a Complete New Winding Including Factory Testing Unit 1 (Optional)
1 JOB XXXXX $________
4007 Remove Existing Stator Winding, Install And Test New Stator Winding Unit 1 (Optional)
1 JOB XXXXX $________
4008 Inspect, Clean And Test Stator Core Unit 1 (Optional)
1 JOB XXXXX $________
4009 Inspect, Clean And Test Rotor Unit 1 (Optional)
1 JOB XXXXX $________
4010 Lead Based Paint Removal Including Disposal Unit 1 (Optional)
Est. 1,500 SF $________ $________
4011 Painting Unit 1 (Optional) 1 JOB XXXXX $________
4012 Disposal of Hydraulic and Lubricating Oil Unit 1 (Optional)
Est. 6,500 GAL $________ $________
4013 Provision of Hydraulic and Lubricating Oil Unit 1 (Optional)
Est. 6,900 GAL $________ $________
4014 Pre-Disassembly Watered Operational Testing Unit 1 (Optional)
1 JOB XXXXX $________
4015 Generating Unit Disassembly Unit 1 (Optional)
4016 Generating Unit Reassembly Unit 1 (Optional)
1 JOB XXXXX $________
4017 Commissioning for Turbine Replacement and Generator Rewind Unit 1 (Optional)
1 JOB XXXXX $________
4018 Refurbish Wicket Gates Unit 1 (Optional)
1 JOB XXXXX $________
4019 Stay Vane/Ring Refurbishment and Extension Installation Unit 1 (Optional)
1 JOB XXXXX $________
4020 Refurbish Bottom Ring Unit 1 (Optional)
1 JOB XXXXX $________
4021 Furnish Wicket Gate Operating Mechanism Bushings and Bearing Plate Unit 1 (Optional)
1 JOB XXXXX $________
4022 Refurbish Miscellaneous Wicket Gate Operating Mechanism Components Unit 1 (Optional)
1 JOB XXXXX $________
4023 Line Boring and Installation of Wicket Gate Stem Bushings Unit 1 (Optional)
1 JOB XXXXX $________
4024 Refurbish/Replace Turbine Air Admission Valves Unit 1 (Optional)
1 JOB XXXXX $________
4025 Refurbish Operating Ring Unit 1 (Optional)
1 JOB XXXXX $________
4026 Refurbish Wicket Gate Servomotors Unit 1 (Optional)
1 JOB XXXXX $________
4027 Furnish and Install Turbine Water and Oil Piping Systems and Accessories Unit 1 (Optional)
1 JOB XXXXX $________
4028 Install Discharge Ring and Draft Tube Liner Transition Unit 1 (Optional)
1 JOB XXXXX $________
4029 Refurbish/Modify Intermediate Headcover Unit 1 (Optional)
4030 Provide Electrical Equipment, Wiring, Removal, Installation Unit 1 (Optional)
1 JOB XXXXX $________
4031 Refurbish Turbine Shaft Unit 1 (Optional)
1 JOB XXXXX $________
4032 Refurbish Intermediate and Generator Shafts Unit 1 (Optional)
1 JOB XXXXX $________
4033 Refurbish Blade Operating Mechanism Components Unit 1
TOTAL BASE ITEMS APPLICABLE TO UNIT 1 (OPTIONAL) $___________
OPTIONAL ITEMS APPLICABLE TO ALL UNITS
5001 Miscellaneous Parts And Materials (Optional)
NTE
$80,000
____ XXXXX $________
5002 Miscellaneous Welding (Optional) NTE
LB
5003 T&M: Provide Skilled Welding Hire (Optional)
NTE
HR
5004 T&M: Provide Skilled Machinist Hire (Optional)
5005 T&M: Provide Skilled Electrician Hire (Optional)
5006 T&M: Provide Skilled Painter Hire (Optional)
5007 T&M: Provide Skilled Millwright/Mechanic Hire (Optional)
5008 T&M: Provide Skilled General Laborer Hire (Optional)
5009 T&M: Provide Skilled Liquid Penetrant Testing (Optional)
5010 T&M: Provide Skilled Magnetic Particle Testing (Optional)
5011 T&M: Provide Skilled Ultrasonic Testing (Optional)
5012 Furnish Stator Core Materials and Accessories for One Generating Unit (Optional)
EA
5013 Perform Additional Interlaminar Insulation Test (Optional)
TOTAL OPTIONAL ITEMS APPLICABLE TO ALL UNITS $___________
ADDITIONAL OPTIONAL ITEMS APPLICABLE TO UNIT 1
6001 Phase 2 Inspection of Thrust Shoes for Unit 1 (Optional)
1 JOB XXXXX $________
6002 Phase 2 Inspection of Thrust Bearing Runner and Thrust Collar for Unit 1 (Optional)
1 JOB XXXXX $________
6003 Refurbish Thrust Bearing Runner Unit 1 (Optional)
1 JOB XXXXX $________
6004 Machine Backside of Thrust Bearing Shoes for Unit 1 (Optional)
1 JOB XXXXX $________
6005 Machine Babbitted Face of Thrust Bearing Shoes for Unit 1 (Optional)
1 JOB XXXXX $________
6006 Refurbish Thrust Bearing Shoes Including Babbitting for Unit 1 (Optional)
1 JOB XXXXX $________
6007 Refurbish Thrust Bearing Collar for Unit 1 (Optional)
1 JOB XXXXX $________
6008 Refurbish Turbine Guide Bearing for Unit 1 (Optional)
1 JOB XXXXX $________
6009 Refurbish Generator Lower Guide Bearing Pads by Machining for Unit 1 (Optional)
1 JOB XXXXX $________
6010 Refurbish Generator Lower Guide Bearing Pads Including Babbitting for Unit 1 (Optional)
1 JOB XXXXX $________
6011 Refurbish Generator Upper Guide Bearing Pads by Machining for Unit 1 (Optional)
1 JOB XXXXX $________
6012 Refurbish Generator Upper Guide Bearing Pads Including Babbitting for Unit 1 (Optional)
1 JOB XXXXX $________
6013 Wicket Gate Additional Painting for Unit 1 (Optional)
2 EA $________ $________
6014 Stay Vane Additional Painting for Unit 1 (Optional)
2 EA $________ $________
6015 Generator Rotor Balancing for Unit 1 (Optional)
1 JOB XXXXX $________
6016 Remove Existing Stator Core, Install and Test New Stator Core for Unit 1 (Optional)
1 JOB XXXXX $________
6017 Refurbish Rotor Poles Unit 1
6018 Machine Stay Ring Flange Unit 1
(Optional)
1 JOB $________ $________
6019 Bore Wicket Gate Servomotor Cylinder Unit 1 (Optional)
2 EA $________ $________
6020 Chrome Plate Wicket Gate Servomotor Piston Rod Unit 1
2 EA $________ $________
TOTAL OPTIONAL ITEMS APPLICABLE TO UNIT 1 $___________
OPTIONAL ITEMS APPLICABLE TO UNIT 2
7001 Phase 2 Inspection of Thrust Shoes for Unit 2 (Optional)
1 JOB XXXXX $________
7002 Phase 2 Inspection of Thrust Bearing Runner and Thrust Collar for Unit 2 (Optional)
1 JOB XXXXX $________
7003 Refurbish Thrust Bearing Runner Unit 2 (Optional)
1 JOB XXXXX $________
7004 Machine Backside of Thrust Bearing Shoes for Unit 2 (Optional)
1 JOB XXXXX $________
7005 Machine Babbitted Face of Thrust Bearing Shoes for Unit 2 (Optional)
1 JOB XXXXX $________
7006 Refurbish Thrust Bearing Shoes Including Babbitting for Unit 2 (Optional)
1 JOB XXXXX $________
7007 Refurbish Thrust Bearing Collar for Unit 2 (Optional)
1 JOB XXXXX $________
7008 Refurbish Turbine Guide Bearing for Unit 2 (Optional)
1 JOB XXXXX $________
7009 Refurbish Generator Lower Guide Bearing Pads by Machining for Unit 2 (Optional)
1 JOB XXXXX $________
7010 Refurbish Generator Lower Guide Bearing Pads Including Babbitting for Unit 2 (Optional)
1 JOB XXXXX $________
7011 Refurbish Generator Upper Guide Bearing Pads by Machining for Unit 2 (Optional)
1 JOB XXXXX $________
7012 Refurbish Generator Upper Guide Bearing Pads Including Babbitting for Unit 2 (Optional)
1 JOB XXXXX $________
7013 Wicket Gate Additional Painting for Unit 2 (Optional)
2 EA $________ $________
7014 Stay Vane Additional Painting for Unit 2 (Optional)
2 EA $________ $________
7015 Generator Rotor Balancing for Unit 2 (Optional)
1 JOB XXXXX $________
7016 Remove Existing Stator Core, Install and Test New Stator Core for Unit 2 (Optional)
1 JOB XXXXX $________
7017 Refurbish Rotor Poles Unit 2
7018 Machine Stay Ring Flange Unit 2
(Optional)
1 JOB XXXXX $________
7019 Bore Wicket Gate Servomotor Cylinder Unit 2 (Optional)
2 EA $________ $________
7020 Chrome Plate Wicket Gate Servomotor Piston Rod Unit 2
TOTAL OPTIONAL ITEMS APPLICABLE TO UNIT 2 $___________
OPTIONAL ITEMS APPLICABLE TO UNIT 3
8001 Phase 2 Inspection of Thrust Shoes for Unit 3 (Optional)
1 JOB XXXXX $________
8002 Phase 2 Inspection of Thrust Bearing Runner and Thrust Collar for Unit 3 (Optional)
1 JOB XXXXX $________
8003 Refurbish Thrust Bearing Runner Unit 3 (Optional)
1 JOB XXXXX $________
8004 Machine Backside of Thrust Bearing Shoes for Unit 3 (Optional)
1 JOB XXXXX $________
8005 Machine Babbitted Face of Thrust Bearing Shoes for Unit 3 (Optional)
1 JOB XXXXX $________
8006 Refurbish Thrust Bearing Shoes Including Babbitting for Unit 3 (Optional)
1 JOB XXXXX $________
8007 Refurbish Thrust Bearing Collar for Unit 3 (Optional)
1 JOB XXXXX $________
8008 Refurbish Turbine Guide Bearing for Unit 3 (Optional)
1 JOB XXXXX $________
8009 Refurbish Generator Lower Guide Bearing Pads by Machining for Unit 3 (Optional)
1 JOB XXXXX $________
8010 Refurbish Generator Lower Guide Bearing Pads Including Babbitting for Unit 3 (Optional)
1 JOB XXXXX $________
8011 Refurbish Generator Upper Guide Bearing Pads by Machining for Unit 3 (Optional)
1 JOB XXXXX $________
8012 Refurbish Generator Upper Guide Bearing Pads Including Babbitting for Unit 3 (Optional)
1 JOB XXXXX $________
8013 Wicket Gate Additional Painting for Unit 3 (Optional)
2 EA $________ $________
8014 Stay Vane Additional Painting for Unit 3 (Optional)
2 EA $________ $________
8015 Generator Rotor Balancing for Unit 3 (Optional)
1 JOB XXXXX $________
8016 Remove Existing Stator Core, Install and Test New Stator Core for Unit 3 (Optional)
1 JOB XXXXX $________
8017 Refurbish Rotor Poles Unit 3
8018 Machine Stay Ring Flange Unit 3
(Optional)
1 JOB $________ $________
8019 Bore Wicket Gate Servomotor Cylinder Unit 3 (Optional)
2 EA $________ $________
8020 Chrome Plate Wicket Gate Servomotor Piston Rod Unit 3
TOTAL OPTIONAL ITEMS APPLICABLE TO UNIT 3 $___________
OPTIONAL ITEMS TOTAL $___________
SCHEDULE TOTAL $___________
IMPORTANT See Section 01 22 00.00 28; MEASUREMENT AND PAYMENT; Paragraph; Retainage of Payment, for withholding of payment for final deliverables.
NTE = Not To Exceed Est = Estimated
Quantities identified as Estimated (“Est”) in the bid schedule are subject to FAR Clause 52.211-18, VARIATION IN ESTIMATED QUANTITY, located in Section 00700.
LABOR HOUR AND TIME & MATERIALS LINE ITEMS: Contract Line Items # 1011, and 5001 through 5011 are labor hour or time-and-materials line items. The extended amount for each of these items is the established ceiling price. Without a modification pursuant to FAR Clause 52.243-3, Changes -- Time-and-Materials or Labor-Hours (Sep 2000), the Contractor exceeds the ceiling at his own risk.
LOCAL INSTRUCTIONS
REQUIRED LIABILITY INSURANCE PURSUANT TO FAR 28.306
In accordance with the clause 52.228-5 Insurance – Work on a Government Installation, the Contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance:
(i) Coverage complying with state laws governing insurance requirements pertaining to Workmen’s Compensation and Employers” Liability Insurance.
(ii) Bodily injury liability insurance with minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
(iii) Automobile bodily injury and property damage liability with minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury liability; and $20,000 per occurrence for property damage liability shall be required.
(iv) The coverage required under Longshore and Harbor Workers Compensation Act, if applicable.
(v) The Insurance Certificate will name the Walla Walla District, U.S. Army Corps of Engineers, 201 N. Third Avenue, Walla Walla, Washington 99362 as the Certificate Holder.
ENVELOPE(S), PURSUANT TO FAR 14.201-5
Envelope (s) shall be plainly marked with the following information:
Solicitation No. __________________________________ Opening Date ___________________________________ Number of each amendment which has been received
EXTENT OF SMALL DISADVANTAGED BUSINESS CONCERN PARTICIPATION IN
SUBCONTRACTING.
If a large business is selected for this contract, it must comply with FAR 52.219-9, Small Business Subcontracting Plan, regarding the requirement for a subcontracting plan on the portion of the work it intends to subcontract. The agency subcontracting goals are: a minimum of 42.5 percent of the Contractor’s intended subcontract amount be placed with small businesses, including 18 percent with small disadvantaged businesses; a minimum of 5.0 percent of the intended subcontract amount shall be placed with woman-owned small businesses; a minimum of 9.0 percent with HUBZone small businesses; a minimum of 3.0 percent with veteran-owned small businesses; and a minimum of 4.5% percent placed with service-disabled veteran-owned small businesses.
CONTRACTOR RESPONSIBILITY, PREAWARD SURVEY
In order to determine a contractor’s responsibility for purposes of contract award the contractor is required to provide a statement regarding previous experience and past performance in performing comparable work, information related to the business organization, financial resources, and/or plant to be used in performing the work.
(See the Attention to Bidders form included in this solicitation.) In accordance with FAR 9.104-1, to be determined responsible, a prospective contractor must –
(a) Have adequate financial resources to perform the contract, or the ability to obtain them;
(b) Be able to comply with the required or proposed delivery or performance schedule, taking into consideration all existing commercial and governmental business commitments;
(c) Have a satisfactory performance record. (A prospective contractor shall not be determined responsible or non-responsible solely on the basis of a lack of relevant performance history except as provided in FAR 9.104-2);
(d) Have a satisfactory record of integrity and business ethics;
(e) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them;
(f) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and
(g) Be otherwise qualified and eligible to receive an award under applicable laws and regulations.
BIDDER INQUIRY:
Bidder/Offeror Solicitation Questions:
All inquiries regarding this solicitation are to be submitted via Bidder Inquiry. Telephone and email inquiries will not be accepted. Bidder Inquiry is a web-site that allows bidders to post questions regarding the solicitation and view all questions by other bidders and responses by USACE. Bidder Inquiry can be accessed through ProjNet at (https://www.projnet.org)
To submit and review inquiry items, prospective vendors will need to use the Bidder Inquiry Key presented below and follow the instructions listed below the key for access. A prospective vendor who submits a comment /question will receive an acknowledgement of their comment/question via email. Another email to the same address will notify the prospective vendor once the reply is available for viewing.
TIMING OF BIDDER INQUIRIES: Bidders are encouraged to submit their bidder inquiries promptly. The Government will make every effort to answer all bidder inquiries; however, the closer to the bid or proposal due date an inquiry is received, the less likely it is that a timely response can be provided.
The Bidder Inquiry Key is: 9FNN7X-BIUR3F
Specific Instructions for ProjNet Bid Inquiry Access:
1. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
2. Identify the Agency. This should be marked as USACE.
3. Key. Enter the Bidder Inquiry Key listed above.
4. Email. Enter the email address you would like to use for communication.
5. Click Continue. A page will then open saying that a user account was not found and will ask you to create one using the provided form.
6. Enter your First Name, Last Name, Company, City, State, Phone, Email, Secret Question, Secret Answer, and Time Zone. Make sure to remember your Secret Question and Answer as they will be used from this point on to access the ProjNet system.
7. Click Add User. Once this is completed you are now registered within ProjNet and are currently logged into the system.
Instructions for Entering Questions:
1. After you are logged in click on the "post new inquiry", it is on the left side of the window under the Word "Submit" a.) This is the window where you will enter your questions https://www.projnet.org/ b.) Comment Classification: Click on the down arrow to the right of the words “Please select from below”, select “Public” c.) Discipline: This is where you select who this question should be directed to. Example; if the question is about an electrical drawing or specification select: “Electrical” from the pull down list.
d.) Sheet. Enter the sheet number of the drawing you are asking about.
e.) Detail. Enter the detail name of the detail shown on the drawing that you are asking about.
f.) Specification. Enter the Specification number and paragraph number.
g.) File. Use this if you are going to attach a pdf file.
h.) Question. Enter your question here.
Specific Instructions for Future ProjNet Bid Inquiry Access:
1. For future access to ProjNet, you will not be provided any type of password. You will utilize your Secret Question and Secret Answer to log in.
2. From the ProjNet home page linked above, click on Quick Add on the upper right side of the screen.
3. Identify the Agency. This should be marked as USACE.
4. Key. Enter the Bidder Inquiry Key listed above.
5. Email. Enter the email address you used to register previously in ProjNet.
6. Click Continue. A page will then open asking you to enter the answer to your Secret Question.
7. Enter your Secret Answer and click Login. Once this is completed you are now logged into the system.
For questions about the ProjNet Bidder Inquiry, please contact the Call Center help desk toll free at 1-800- 428-HELP, which operates from 8AM to 5PM (Central US time zone). Bidder inquiry help questions can also be emailed to the helpdesk at staff@rcesupport.com.
mailto:staff@rcesupport.com
EVALUATION FACTORS FOR AWARD
A. INTRODUCTION
This Source Selection Plan (SSP) defines the criteria, organization and policies to be used in selecting a contractor to install and commission three hydraulic turbine runners (fixed and adjustable) with associated water passage components and stator winding replacements at the Ice Harbor Lock and Dam powerhouse on the Snake River in Washington State.
B. BACKGROUND AND OBJECTIVES
One fixed and two adjustable blade hydraulic turbine runners with associated water passage components will be supplied to the Ice Harbor Lock and Dam for installation in turbine Units 2, 3 and 1 respectively. The stator windings will be replaced in each of these three units as well.
The supplied runners and components will be provided to the successful offeror as Government furnished property (GFP) for installation and commissioning. Additional supplies, materials, parts and components will be provided by the successful offeror and installed as required to complete the runner installations, stator winding replacements and commissioning.
C. ACQUISITION STRATEGY
This is a competitive acquisition for the single award of a firm fixed-priced contract. Award will be made to the best overall proposal that is determined to be the most beneficial to the Government. The selection for this procurement will be based on the evaluation of four (4) factors: Technical which includes four (4) subfactors; Cost/Price; Past Performance; and Small Business Participation.
SECTION II
SOLICITIATION PROVISIONS
A. BASIS FOR AWARD.
The award will be made based on the best overall (i.e., best value-tradeoff) proposal that is determined to be the most beneficial to the Government, with appropriate consideration given to the four (4) evaluation factors: Technical, Price, Past Performance and Small Business Participation. All subfactors of Factor I, Technical, are equal in importance to each other.
Factor I, Technical, is more important than Factor III, Past Performance. Factor III, Past Performance is more important than Factor IV, Small Business Participation. When combined, the non-price factors (Factors I, III, and IV) are significantly more important than Factor II, Price.
As proposals become more equal in their technical (non-price) merit, the evaluated price becomes more important in determining the best value proposal.
B. FACTORS AND SUB-FACTORS TO BE EVALUATED.
The following evaluation factors and sub-factors will be used to evaluate each proposal. Award will be made to the offeror whose proposal is most advantageous to the Government based upon an integrated assessment of the evaluation factors and sub-factors described below.
1. FACTOR I Technical - The technical evaluation will be comprised of four (4) Sub-Factors.
Risk assesses the degree to which the offeror’s proposed technical approach for the requirements of the solicitation may cause disruption of schedule, increased price, degradation of performance, the need for increased Government oversight, or the likelihood of unsuccessful contract performance. Risk will be evaluated as one aspect of the technical evaluation, inherent in the technical evaluation factor or subfactor ratings.
Subfactor A: Technical Work Plan and Capabilities Subfactor B: Hydraulic Turbine Runner Installation Experience
Subfactor C: Unit Stator Winding Replacement and Commissioning Subfactor D: Management, Quality Control and Schedule
Evaluation of the offeror’s proposal shall address each subfactor as it applies to the scope of work. A detailed explanation of the criteria for the evaluation is set forth in the Evaluation Approach, Paragraph C of this section. During evaluations of each proposal, the Government will assign each subfactor an adjectival rating and write a narrative evaluation reflecting the identified findings.
2. FACTOR II Price - The resulting award will be a firm-fixed price contract. Price reasonableness will be utilized in the evaluation of the proposal.
3. FACTOR III Past Performance - Each offeror’s current and past performance will be reviewed to determine relevancy and confidence.
4. FACTOR IV Small Business Participation - The extent of Small Business Participation will be evaluated for unrestricted acquisitions.
C. EVALUATION APPROACH.
All proposals will be evaluated by the Source Selection Evaluation Board (SSEB).
1. The overarching evaluation approach for all factors and subfactors is as follows:
a. Adequacy of Response. The proposal will be evaluated to determine whether the offeror’s methods and approach have adequately and completely considered, defined, and satisfied the requirements specified in the RFP. The proposal will be evaluated to determine the extent to which each requirement has been addressed in the proposal in accordance with the proposal submission section of the RFP. Marginal levels of overall detail could indicate a lack of understanding concerning the requirements and may result in the entire factor receiving an unfavorable rating.
2. Factor I Technical - This factor is comprised of the following subfactors:
a. Subfactor A: Technical Work Plan and Capabilities
This subfactor evaluates the offeror’s understanding of the required scope of work and evaluates the offerors capabilities and availability of resources necessary to complete all requirements. The offeror should propose a work plan which clearly defines:
1) Major tasks and outlines all work necessary to complete those tasks.
2) Clearly present the critical path to complete all major tasks.
3) Discuss how work to complete one task may impact or be impacted by work to complete other tasks.
4) Clearly distinguish between work that will be completed on-site versus work that will be completed off-site.
5) Identify any critical assumptions and uncertainties that may impact the completion of work and to identify methods to check assumptions and address uncertainties.
6) Document capabilities and availability of resources necessary to complete all required major tasks.
7) List of all major pieces of equipment and specialty tools necessary and available to complete all major tasks.
8) List any specialty work crews or individuals required to complete unique or special tasks.
b. Subfactor B: Hydraulic Turbine Runner Installation Experience
This subfactor evaluates the offeror’s experience with turbine runner replacements and other work of similar size and scope of that required by this contract. Minimum experience shall be at least one example of each of the six elements identified below performed within the past ten years. The evaluation will focus on the offeror’s documentation of experience with the following:
1) Assembly of large (at least 200" dia) adjustable blade runners.
2) Replacements of large adjustable blade propeller (Fixed and/or Adjustable blade) turbine runners (at least 200” dia).
3) Replacement of large diameter discharge rings for propeller type units (at least 200” dia).
4) Alignment of larger vertical units.
5) New and/or refurbished hydro-turbine commissioning.
6) In-place and shop machining of large turbine components such as the discharge ring and head covers.
c. Subfactor C: Unit Stator Winding Replacement and Commissioning
This subfactor evaluates the experience, approach and capabilities of each offeror and the quality of their proposed technical approach to replace Unit stator core and stator windings as specified in the requirements. The evaluation will focus on the offeror’s documentation of experience with the following:
1) Design of replacement stator windings and stator cores of at least 50 MW.
2) Provide a complete description of the stator core details (i.e. manufacturing process, materials).
3) Provide a complete description of the stator winding and accessories to include:
i. Coil insulation system (including strand, turn and groundwall insulation material and thickness, cross sectional dimensions and manufacturing process)
ii. Designed dielectric stress of the groundwall insulation at rated voltage
iii. Ground wall insulation application method (hand-wound, machine wound with/without scarf joint, etc.).
4) Identify the location and name(s) of the owning interest in the lamination manufacturing facility (the manufacturing experience of this facility in fabricating lamination shall be documented).
5) Identify the location and name(s) of the owning interest in the winding manufacturing facility (the manufacturing experience of this facility in fabricating stator windings of this size shall be documented).
6) Present guaranteed combined I2R (R corrected to 75 deg. C), and stray load loss, for their proposed winding in “kW” at 108,948 kVA, 13.8 kV, and 0.95 power factor.
7) Present guaranteed core loss for proposed core in “kW” at 108,948 kVA, 13.8 kV, and 0.95 power factor
8) Describe technical approach and installation process. Include a description of the stator core and stator winding installation process as well as details on the side packing system; wedging system including type, dimensions, and materials of wedges, total number of wedges per slot, number of check wedges per slot and end wedge securing method; spring deflection measurement method, brazing method and quality control procedures.
d. Subfactor D: Management, Quality Control and Schedule
This factor will evaluate the offeror’s proposed management and quality team experience and capabilities, and will evaluate proposed schedules necessary to complete the requirements of this contract.
1) Identify key management structure and team for completion of all contract requirements to include:
Resume that describes the experience and responsibility of key personnel with projects of similar type, size and complexity as that required for this contract.
2) Demonstrate the commitment of the offeror to maintain continuity of key management personnel through the completion of the project.
Project Manager, Project Site Superintendent, Installation Supervisor (for windings) and Construction Quality Control Manager.
3) Description of the offeror’s Quality Control Program given the requirements in Specification 01 45 04.00 28.
4) Provide a schedule that identifies the planned activities, order of tasks, task dependencies and durations proposed to successfully accomplish the entire project from notice to proceed to final commissioning for each unit. A baseline schedule will be prepared by the Government and used for comparison purposes. For proposal purposes only, the offeror should use the arbitrary, non-binding Notice to Proceed date of 12 Feb 2016.
The Technical Factor Ratings, excerpted below focus on the strengths, deficiencies, weaknesses, risks and uncertainties of the offeror’s proposal. The rating depicts how well the offeror’s proposal meets the Technical subfactor requirements.
Rating Description Outstanding Proposal meets requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.
Good Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low.
Acceptable Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance.
Risk of unsuccessful performance is no worse than moderate.
Marginal Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.
Unacceptable Proposal does not meet requirements and contains one or more deficiencies. Proposal is not awardable.
3. Factor II - Price - The contract will be a Firm Fixed-Price Contract. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s). The Government will evaluate offers for award purposes by evaluating the prices proposed in the Bid Schedule. The Offeror must provide a price proposal by completing the Bid Schedule as instructed in Section 00100.
Firm Fixed Price Requirements
a. The RFP requires firm-fixed-price contract line items. A price reasonableness approach will be utilized by the Government to determine that the proposed prices offered are fair and reasonable and that a “buy-in” or unbalanced pricing between CLINs is not occurring.
b. The Government will examine price proposals for artificially low unit prices. Offers found to be unreasonably high, unrealistically low (an indication of “buy – in”), or unbalanced, may be considered unacceptable and may be rejected on that basis.
4. Factor III - Past Performance - The Government will evaluate the offeror’s record of past and current performance to ascertain the probability of successfully performing the required efforts of the scope of work.
a. Evaluation of past performance shall be in accordance with this plan utilizing the forms and questionnaires set forth in Appendix D.
b. The Government will focus its inquiries on the offeror’s (and major subcontractors’) record of performance as it relates to all solicitation requirements, including price, schedule, performance and management of subcontractors. Major subcontractors are defined as members of an offeror’s overall team who are expected to perform ten (10) percent or more of the proposed effort. A significant achievement, problem, or lack of relevant data in any element of the work can become an important consideration in the evaluation process. Therefore, offerors will be reminded to include the most current and relevant past efforts (within the past six years) in their proposal. Absent any current and relevant past performance history or when the performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned, the offeror will be assigned an “unknown confidence rating” and its proposal will not be evaluated either favorably or unfavorably on past performance. The Government may use data provided by the offeror in its proposal and data obtained from other sources, including data in Government files or data obtained through interviews with personnel familiar with the contractor and their current and past performance under Federal, State or Local government or commercial contracts for same or similar services as compared to the North American Industry Classification System NAICS 237990, Other Heavy and Civil Engineering Construction. Data used in conducting performance risk assessments shall not extend past six years prior to the issue date of the RFP, but may include performance data generated during the past six years without regard to the contract award date.
c. Offerors shall submit all Government and/or commercial contract numbers and descriptions for the prime offeror and each major subcontractor in performance or awarded during the past six years, from the issue date of this RFP, which are relevant to the efforts required by this RFP. The Government may consider a wide array of information from a variety of sources, but is not compelled to rely on all of the information available.
d. The past performance factor considers each offeror’s demonstrated current and relevant past record of performance in supplying products and services that meet the contract requirements. There are two aspects to the past performance evaluation: relevancy and performance confidence assessment.
(i) RELEVANCY: The Government will conduct a performance assessment based on the relevancy of the Offeror's current and past performance, as well as that of its major subcontractors, as it relates to the probability of successful accomplishment of the required effort. These efforts include all aspects of schedule, performance and customer support, including the Offeror’s submitted subcontracting plan for this project and the Offeror’s record of: 1) Conforming to specifications and standards of good workmanship; 2) Maintaining program execution within price; 3) Adherence to contract schedules, including the administrative aspects of performance; 4) Ability to resolve technical and manufacturing problems quickly and effectively; 5) Businesslike concern for the interest of its customers; 6) Establishing and maintaining adequate management of subcontractors; and 7) Compliance with subcontracting plans submitted on previous projects.
Past Performance Relevancy Ratings
Rating Definition
Very Relevant Current/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.
Relevant Current/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.
Somewhat Relevant Current/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.
Not Relevant Current/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.
(ii) PERFORMANCE CONFIDENCE ASSESSMENT: The final step is for the team to arrive at a single consensus performance confidence assessment for the offeror, selecting the most appropriate rating from the chart below. This rating considers the assessed quality of the relevant/current efforts gathered (documented results from Past Performance Questionnaires, interviews, CPARS, and other sources form the support and basis for this assessment). Ensure the rationale for the conclusions reached are included.
Performance Confidence Assessments
Rating Definition
Substantial Confidence Based on the offeror’s relevant performance record, the Government has a high expectation that the offeror will successfully perform the required effort.
Satisfactory Confidence Based on the offeror’s relevant performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort.
Limited Confidence Based on the offeror’s relevant performance record, the Government has a low expectation that the offeror will successfully perform the required effort.
No Confidence Based on the offeror’s relevant performance record, the Government has no expectation that the offeror will be able to successfully perform the required effort.
Unknown Confidence (Neutral) No relevant performance record is available or the offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.
5. Factor IV - Small Business Participation: All offerors (both large and small…