W912DY-21-R-0005_Attachment 13_Division 01 Specs.pdf

PDF 2 MB Posted

Attached to
W912DY21R0005 FRR Phase 1 Federal contract opportunity
Solicitation number
W912DY
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This is a solicitation for a Firm-Fixed Price Construction Multiple Award Task Order Contract to provide Facility Repair and Renewal services at government installations and facilities located throughout the contiguous United States, non-contiguous United States territories, and various overseas locations. The services include facility repair, renovation, conversion, alteration, additions, construction, and equipment procurement and installation. The contract is a two-phase design-build effort requiring the contractor to survey problem areas, evaluate and recommend solutions, develop work plans, and provide repair, renewal, and construction efforts to support the design solution. Task orders will provide a quick response for facility repair, renovation, conversion, alteration, additions, construction, and equipment procurement and installation at government sites on an as-needed basis. The agency is the Department of the Army Corps of Engineers Engineering Support Center Huntsville.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FRR MATOC

DIVISION 01 SPECIFICATIONS

W912DY-21-R-0005

Table of Contents

01 11 00 Summary of Work 01 14 00 Work Restrictions 01 30 00 Administrative Requirements 01 32 01.00 10 Project Schedule 01 32 16.00 20 Small Project Construction Project Schedules 01 33 00 Submittal Procedures 01 33 16.00 10 Design Data (Design After Award) 01 35 26 Government Safety Requirements 01 42 00 Sources for Reference Publications 01 45 00.00 10 Quality Control 01 45 00.15 10 Resident Management System Contractor Mode 01 50 00 Temporary Construction Facilities and Controls 01 57 19 Temporary Environmental Controls 01 58 00 Project Identification 01 74 19 Construction Waste Management and Disposal 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data 01 78 24.00 10 Facility Data Requirements 01 91 00.15 10 Total Building Commissioning

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with

Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Site Investigation Report, G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The objective is to award a Firm-Fixed Price (FFP) Construction Multiple

Award Task Order Contract (MATOC) with design/build capabilities in support of the Facility Repair & Renewal (FRR) Program. The FRR program provides rapid response for facility repair, renovation, conversion, and alteration;

and facility subsystem additions, construction, equipment procurement/installation at Government installations and facilities at the locations listed in Section 1.2.2.

Due to the need for expeditious repairs, this will be a Two-Phase

Design-Build construction contract. Services include facility repair, renovation, conversion, alteration, additions, construction, and equipment procurement installation at Government installations and facilities. The

Contractor is required to survey the problem areas, evaluate and recommend solutions, develop and implement work plans in a timely manner within negotiated costs, and provide the repair/renewal/construction efforts to support the design solution. Task Orders under this MATOC are intended to provide quick response for facility repair, renovation, conversion, alteration, additions, construction, and the procurement / installation of equipment at Government installations and facilities.

The Contractor shall complete all work and services under this contract in accordance with schedules that are established in each task order. Work will vary from site to site and will require extensive knowledge of facilities repair and renewal (FRR) projects. Submittal dates will be included in the individual task orders. These dates identify when information is due in the issuing Government office and other addresses identified in the individual task orders. The types and numbers of submittals and dates and places for review meetings shall be established by each task order under this contract.

1.2.2 Locations

The work is to be performed at the following locations, approximately as indicated: Contiguous United States to include the District of Columbia;

SECTION 01 11 00 Page 2

Non-Contiguous United States including Alaska, Hawaii, U.S. Territories;

Kuwait, Qatar, United Arab Emirates (UAE), Yemen, Iraq, Saudi Arabia, Egypt, Afghanistan, Indonesia, Japan, Korea, Cuba, Azores, Germany, Kwajalein, Spain, Italy, Israel, Poland, Turkey, Greenland, England, Belgium, the Netherlands, Diego Garcia, Shemya Island, Australia, and the

Ascension Island. The exact location will be shown by the Contracting

Officer.

1.3 OCCUPANCY OF PREMISES

Depending on project location and/or work to be performed, building(s) may/may not be occupied during performance of work under this Contract.

Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with

Installation requirements for locating and marking underground utilities.[

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 48 hours prior to starting excavation work.

1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT (IF APPLICABLE, WILL BE

IDENTIFIED IN THE TASK ORDER)

Pursuant to Contract Clause FAR 52.245-1 Government Property, the

Government will furnish the following materials and equipment for installation by the Contractor:

DESIGNATION NO. DESCRIPTION QUANTITY

SECTION 01 11 00 Page 3

Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 ACTIVITIES UNDER FACILITY REPAIR AND RENEWAL (FRR) PROJECTS

The activities to be performed by the Contractor under this contract and subsequent task orders are described in general terms below (this list is not all-inclusive). The specific tasks and task elements to be performed will be identified in each task order. Generally, costs associated with each task element will be negotiated and agreed upon prior to start of effort on the task order; however, upon direction of the Contracting

Officer by issuance of a time-and-materials (T&M) order, the Contractor shall immediately start the first task element and usually the order will be negotiated to a firm-fixed price as soon as possible. The Contracting

Officer reserves the right to modify duties and time periods in the tasks.

At the completion of each approved task order, the results, documented and conceptual, become the property of the Government.

3.1.1 Element 1 Site Investigation

Upon direction of the Contracting Officer, a site investigation shall be initiated. Prior to any site investigation, a site survey/visit proposal and an abbreviated accident prevention plan (AAPP) shall be submitted, within five working days after the acceptance of the site survey proposal by the Contracting Officer or receipt of a unilateral T&M task order, the

Contractor shall start a site survey. Within five working days after the conclusion of the site survey, unless otherwise identified in the individual task order or directed by the Contracting Officer, the

Contractor shall prepare and submit to the Contracting Officer, a site survey report. The site survey report shall identify any needed project related information/data that was not available.

3.1.1.1 Site Survey

Visit the site, building, or area as directed or indicated in the task order. Provide visual digital media documenting the proposed facility, repair, and rehabilitation (FRR) action project with emphasis on the particular items to be removed/recovered. Unless stated otherwise in a task order, the site investigation shall involve the following as a minimum:

a. Investigate each of the problem areas stated in the task order.

Investigate and analyze any obvious code or accreditation violations.

b. Review existing as-built drawings, maintenance records, and other pertinent documentation as required to fulfill the requirements of the task order.

SECTION 01 11 00 Page 4

c. Interview on-site maintenance personnel and staff as required to fulfill the requirements of the task order.

d. Gather data required to prepare a site description, a hazard and risk analysis, a site control document, and a site disruption plan, which itemizes actual, probable and potential interruptions to installation operations along with recommendations to reduce the effects of unavoidable interruptions.

e. Develop a basis during the visit to prepare budget cost proposals for the FRR action elements listed in the task order.

f. Operate existing systems/equipment, as applicable, under the direction of installation personnel in order to isolate and evaluate problem areas.

g. Investigate and document the presence or absence of asbestos/lead-based paint in the proposed work areas and surrounding areas with the goal of preparing an abatement plan.

To accomplish this the Contractor shall interview facility personnel and review existing documentation as required. At the completion of the documentation review, the Contractor shall conduct an on-site investigation of the proposed work area in conjunction with facility personnel to visually locate and identify asbestos/lead-based paint insulation or surface coverings, which cannot be proven to be non-asbestos, shall be considered to be asbestos and treated accordingly. If no asbestos/lead-based paint is encountered or presumed present, the

Contractor shall so certify in writing.

3.1.1.2 Site Investigation Report

Prepare and submit a Site Investigation Report documenting the site investigation. Include meeting minutes; site conditions, all data gathered, customer requirements and Scope clarifications. Include a synopsis which defines all design alternatives evaluated as well as the results. Present the Report in a three ring binder(s) and submit as a stand alone document, or as a part of the work plan as required by the task order. The Site

Investigation Report shall include (as a minimum, or as defined in the Task

Order) individual sections for each of the topics defined below.

a. Site Description. Provide a brief description of the site under investigation, including a complete summary of safety and health hazards anticipated on site.

b. Site Information. Provide a list of people contacted during the visit, as well as any relevant information obtained.

c. Hazard Assessment and Risk Analysis. Provide a complete description of the work to be performed with a complete summary of hazards anticipated. Identify the safety and health hazards that may be encountered for each task or site operation to be performed. Each task/operation is to be discussed separately.

Material Safety Data Sheets (MSDS) for each hazardous substance discovered or brought on site shall be documented.

d. Problem Areas. Include a narrative description of each problem area (related to FRR action) that was investigated during the

SECTION 01 11 00 Page 5 visit. Also include a list of any code or accreditation violations in these areas. Indicate areas investigated which warrant further study and those, which do not warrant further efforts.

e. Disruption Plan. Develop and submit a site disruption plan, signed off by installation personnel, which identifies actual, probable, and potential interruptions to installation operation with corrective actions.

f. Asbestos and/or Lead-Based Paint Abatement (Removal/Encapsulation) Plan. The report shall contain an abatement plan and schedule for the abatement of any asbestos and/or lead-based paint in the work and surrounding area, both identified by type, percent and location. This plan shall contain recommendations for in-place or removal abatement procedures. The plan shall be monitored throughout the FRR action effort.

Abatement shall be carried out in a manner, which minimizes the cost and impact on the FRR action; i.e., encapsulating lead-based paint and/or asbestos containing equipment and areas where possible instead of removing the materials. If the abatement will be handled by others, then a conclusive statement shall be included specifically stating the responsible party who will be performing the abatement. If there is no lead based paint and/or asbestos, then include a statement such as, "No lead based paint or asbestos is involved." No FRR action effort shall begin until the work area is abated of hazardous material, or is certified asbestos/lead-based paint free.

g. Preliminary Studies. Include any preliminary studies, feasibility studies, life cycle cost analysis, or any other reports, documentation, or general information used in decision making, preliminary design, or design alternates. Life cycle cost studies shall be performed in accordance with National Institute of Technology and Standards Handbook 135 utilizing Department of

Energy Escalation Rates and other applicable data as specified in the task order or directed by the Contracting Officer.

h. Proposed Work Plan. Clearly define the scope of work to be included in the work plan. Define the recommendations for resolving each problem area that was investigated. Include any drawings/sketches/schedules, which may be applicable to the proposed FRR action. Describe any equipment/system to be supplied as part of the FRR action.

i. Cost Proposals. The Site Investigation Report shall include a final cost proposal for the preparation of the work plan and a budget cost proposals for the performance of the FRR Action.

3.1.2 Element 2 Work Plan (Design)

The work plan (design) shall be developed by the Contractor in accordance with the level of effort specified by the task order. The complexity of the work plan for an FRR action on a major project such as replacement of major equipment, rehabilitation or renewal of large or complex facilities, etc. may consist of detailed drawings, specifications, schedules, etc.

while a work plan for an FRR action on a minor project such as a motor or pump replacement may consist of simple sketches, catalog cuts, a simple schedule, etc. Regardless of the size of the FRR action project the work

SECTION 01 11 00 Page 6 plan shall provide adequate detail to effectively carry out the FRR action process. Submit as specified in Section 01 33 10.05 20 DESIGN SUBMITTAL

PROCEDURES.

3.1.3 Element 3 FRR Action

Begin work on the FRR action of the facility or installation in accordance with the approved work plan or as otherwise directed by the Contracting

Officer following the approved work schedule.

3.2 LEVEL OF EFFORT

The type and magnitude of task order projects will vary greatly; the contractor is expected to prepare the level of design and documentation appropriate to the size and complexity of the project.

-- End of Section --

SECTION 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/11

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

1.2 SUBMITTALS

used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with

Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G, [ ]

List required submittals here; G[, [ ]]

][1.3 SPECIAL SCHEDULING REQUIREMENTS

a. [ ] must be ready for operation as approved by Contracting Officer before work is started on [ ] which would interfere with normal operation.

b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:

(1) [ ]

(2) [ ]

c. The [ ] will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.

d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of [15] [ ] calendar days prior to the desired date of interruption.

SECTION 01 14 00 Page 2

]1.4 CONTRACTOR ACCESS AND USE OF PREMISES

1.4.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.4.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.4.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.4.2 Working Hours

Regular working hours must consist of an [8 1/2 hour] [[ ] hour] period

[established by the Contracting Officer], between [7 a.m. and 3:30 p.m.,]

[[ ] a.m. and [ ] p.m.,] Monday through Friday, [and 7 a.m. to 3:30 p.m. on Saturday] [[ ] a.m. and [ ] p.m.], excluding Government holidays.

1.4.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application [15] [ ] calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.

During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.[ Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.]

[1.4.4 Exclusionary Period

No work must be performed during the period [ ] to [ ], inclusive, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.

][1.4.5 Occupied Building[s]

The Contractor shall be working [in an existing building] [around existing buildings] which [is][are] occupied.[ Do not enter the building[s] without

SECTION 01 14 00 Page 3 prior approval of the Contracting Officer.]

[ The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.

][Provide dust covers or protective enclosures to protect existing work that remains, and Government material located in the [ ] during the construction period.

] [Relocate movable furniture [approximately [6 feet] [ ] away from the

Contractor's working area] [as required to perform the work], protect the furniture, and replace the furniture in [its] [their] original location[s] upon completion of the work.][ Leave attached equipment in place, and protect [it] [them] against damage, or temporarily disconnect, relocate, protect, and reinstall [it] [them] at the completion of the work.]

[ The Government will remove [and relocate] other Government property in the areas of the building[s] scheduled to receive work.

]]1.4.6 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and [ ] are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.[ Such interruptions are further limited to [ ] hours. This time limit includes time for deactivation and reactivation.]

[ d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

][][1.5 SECURITY REQUIREMENTS

[ Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

]]PART 2 PRODUCTS

Not Used

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements

Manual used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with

View Location Map; G, Progress and Completion Pictures; G,

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.

SECTION 01 30 00 Page 2

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.6 SUPERVISION

1.6.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.6.2 Superintendent Qualifications

The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10

QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.

1.6.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRE-FACILITY REPAIR AND RENEWAL (FRR) CONFERENCE

This conference will be held at the location specified by the Contracting

Officer, or authorized representative. The purpose of this pre-FRR action conference is to enable the Contracting Officer, or authorized

SECTION 01 30 00 Page 3 representative, to outline the procedures that will be followed by the

Government in its administration of the contract and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the

Government's supervision and inspection of contract work, security requirements, regulations, etc. The Contracting Officer, or authorized representative, may invite installation, using service, engineering, and/or security personnel as well as other involved Government personnel to attend this conference.

1.7.1 Discussion Items

The following is a list of items for discussion during this conference.

This is not considered to be a complete listing.

a. Authority of the Contracting Officer, or authorized representative, and procedures for administering the contract.

b. Contractor labor standards provisions.

c. Contract modification and administration procedures.

d. Payment estimate data and procedures.

e. Contractor insurance requirements.

f. Contractor performance evaluation.

1.7.2 Installation Rules and Regulations

Regardless of whether site of the work is on a military reservation or on a civilian installation associated with the military, all rules and regulations issued by the Commanding Officer/Director covering general safety, security, sanitary requirements, pollution control, work hours, storage areas, utility availability and use, utility interruptions, site conditions, environmental compliance, clean up, conduct and dress, work in areas with others, excavation permits, access to work areas, traffic regulations, as well as any other pertinent information requested by the

Contractor or provided by the authorized installation technical representative shall be observed by the Contractor. Information regarding these requirements may be obtained by contacting the authorized installation technical representative, who will provide such information or assist in obtaining same from appropriate authorities.

1.7.3 Work Hours and Government Holidays

Specific work hours will be set for each task order. Standard work hours should be set at preliminary teleconference or by Contracting Officer. If not set prior, standard work hours should be between 0800-1700 unless otherwise set by Contracting Officer. Note that government employees may not be accessible during the following government holidays: New Years Day, Martin Luther King Birthday, President's Day, Memorial Day, Independence

Day, Labor Day, Columbus Day, Veteran's Day, Thanksgiving Day, and

Christmas Day.

1.8 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members

SECTION 01 30 00 Page 4 are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter

Experts, the Installation, the Contractor and Subcontractors, and the

Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.8.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and

Government personnel.

The Initial Partnering session should be a part of the Pre-Construction

Meeting. Partnering sessions will be held at a location agreed to by the

Contracting Officer and the Contractor (typically a conference room provided by the Resident Engineer office or the Contractor). The Initial

Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the

Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.

1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.

Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all

Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

SECTION 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

SECTION 01 32 01.00 10 Page 2

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to

FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical

Path Method (CPM) of network calculation to generate all Project

Schedules. Prepare each Project Schedule using the Precedence Diagram

Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

SECTION 01 32 01.00 10 Page 3

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original

Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Design and Permit Activities

Include design and permit activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period. Provide at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work.

Also include review and correction periods associated with each item.

3.3.4 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.5 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

SECTION 01 32 01.00 10 Page 4

a. Submission, review and acceptance of SD-01 Preconstruction Submittals

(individual activity for each).

b. Submission, review and acceptance of design packages.

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.6 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: acceptance, design reviews, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed

(NTP) for phasing requirements.

SECTION 01 32 01.00 10 Page 5

3.3.7 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange

Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template

SDEF compatible schedule backup file is available on the QCS web site:

http://rms.usace.army.mil.

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.7.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.7.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government

Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

http://rms.usace.army.mil/

SECTION 01 32 01.00 10 Page 6

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.7.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.7.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification

Number Code.

3.3.7.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item

Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.7.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are design phase, procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.7.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to design, design submittal, design reviews, review conferences, permits, construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.7.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the

Definable Feature of Work to which the activity belongs based on the approved QC plan.

SECTION 01 32 01.00 10 Page 7

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY

CONTROL. An activity can have only one Feature of Work Code.

3.3.8 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.8.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled

"NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.8.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End

Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the

"End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate

Government activities to support a Contractor's early completion.

3.3.8.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.8.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.8.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.9 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a

7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as

SECTION 01 32 01.00 10 Page 8 applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days (based on location) as provided in each task order.

Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.10 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP

Acknowledged" may have no predecessor logic, and the last activity -"End

Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.11 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the

Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the

Contractor's schedule.

3.3.12 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the

Narrative Report and in the periodic schedule update meetings.

3.3.13 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.14 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.15 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

SECTION 01 32 01.00 10 Page 9

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.16 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

3.3.17 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for…