IDaC Profit Formula and Scenario Tool.xlsx

XLSX spreadsheet 20 KB Posted

Attached to
Draft RFP for Howard A. Hanson Dam Fish Passage Facility Federal contract opportunity
Solicitation number
W912DW24R0004
Issued by
Department of the Army Corps of Engineers Engineering District Seattle

About this file

This announcement provides information for a draft request for proposal for the Howard A. Hanson Dam Fish Passage Facility project. The U.S. Army Corps of Engineers seeks industry feedback on draft documents and plans to use an Early Contractor Involvement-Integrated Design and Construction delivery method. A virtual industry day will take place on November 29th, 2023, from 10:00 AM to 12:00 PM Pacific Time, and an in-person site visit is scheduled for December 13th, 2023. Interested parties must register by November 28th. One-on-one sessions between contractors and the government will also occur in early 2024 to clarify questions. The agency aims to improve the draft documents before a final RFP and select a contractor to work collaboratively with the government during design and establish a firm fixed price for subsequent construction. No proposals are being requested at this time in response to the draft documents.

View the file

Other files for this federal contract opportunity

Other files attached to Draft RFP for Howard A. Hanson Dam Fish Passage Facility, newest first.
File Type Posted
HAHD_RFP Attach 1 - Design Schedule.pdf PDF
HAHD_RFP Attach 2 - Plan Sheet List.pdf PDF
HAHD_RFP Attach 4 - DDR.pdf PDF
HAHD_RFP Attach 6 - Draft Div01 Specifications.pdf PDF
HAHD_RFP Attach 12 - 401 Cert.pdf PDF
HAHD_RFP Attach 5 - Construction Spec TOC.pdf PDF
Price Schedule_EPA Items (Draft).docx DOCX document
HAHD_RFP Attach 3 - Concept Drawings.pdf PDF
HAHD_RFP Attach 8 - Geotech BDIRs.pdf PDF
HAHD_RFP Attach 10 - USFWS_2022_BIOP.pdf PDF
HAHD_RFP Attach 11 - NMFS 2019 BIOP.pdf PDF
HAHD_RFP Attach 14 - Bulkhead Inspection SOW.pdf PDF
FY25HAHDFPF One on One Session Instructions (Rev1_Final).pdf PDF
FY25 HAHDFPF- One on One Session Instructions (Final).pdf PDF
FY25-HAHDFPF_00-COMPILATION_35PERCENT_DDR.pdf PDF
W912DW24R0004- HAHD FPF_GOVERNMENT QUESTIONS TO INDUSTRY (19DEC23).docx DOCX document
Attendance of December 13 Site Visit. List.xlsx XLSX spreadsheet
Industry Day Attendance List 29Nov23.xlxs.xlsx XLSX spreadsheet
Industry Day Attendance List 29Nov23.xlxs.xlsx XLSX spreadsheet
HHD FPF Industry Draft RFP Presentation November 2023.pdf PDF
W912DW24R0004- HAHD FPF_Draft RFP_Revision 1 (Reduced).pdf PDF
W912DW24R0004- HAHD FPF_PROJNET INQUIRIES INSTRUCTIONS.docx DOCX document
W912DW24R0004- HAHD FPF_GOVERNMENT QUESTIONS TO INDUSTRY.docx DOCX document
W912DW24R0004- HAHD FPF_Draft RFP_Reduced.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Example Profit Scenario

THIS IS ONLY AN EXAMPLE OF HOW THE IDaC CLAUSE FORMULA WORKS USING THE INPUTS GIVEN BY THE GOVERNMENT IN THE SOLICITATION AND AN OFFEROR'S FICTITIOUS PROPOSAL

Step 1 - Initial Competed Price at Award

Initial Target Cost (ITC) (Given as CCL)$500,000,000.00
Initial Target Profit (ITPr)$45,000,000.009%
Initial Target Price (ITP)$545,000,000.00
Initial Share Ratio (Contractor's Share)50%
Contract Ceiling Price (CCP) % above Target Cost$575,000,000.00115%
Firm Share Ratio Under
Firm Share Ratio Over
Minimum Firm Target Profit Floor3%
Maximum Firm Target Profit Ceiling12%
FIRM TARGET PRICE CALCULATIONS
Step 2 - Production Point
Firm Target Cost$500,000,000.00
Delta$0.00
Contractor Share of Delta$0.00`
Firm Target Profit$45,000,000.009.00%
Firm Profit No Less than Minimum Profit (Floor)$15,000,000.003.00%
Firm Profit No More than Maximum (Ceiling)$60,000,000.0012.00%
Firm Target Price$545,000,000.00
Step 3 - Negotiate Final Construction Price (FFP) using the calculated Firm Target Price as basis
**In no circumstance may the Final Construction Price exceed the Construction Contract Ceiling Price established in the contract**Final Construction Price (FFP) Negotiated:
(CANNOT EXCEED THE ESTABLISHED CCP)$
FIRM TARGET PRICE CALCULATIONS (COST UNDERRUN SCENARIO)
Step 2 - Production Point
Firm Target Cost$450,000,000.00
Delta$50,000,000.00
Contractor Share of Delta$25,000,000.00
Firm Target Profit$70,000,000.0015.56%
Firm Profit No Less than Minimum Profit (Floor)$13,500,000.003.00%
Firm Profit No More than Maximum (Ceiling)$54,000,000.0012.00%
Firm Target Price$504,000,000.00
Step 3 - Negotiate Final Construction Price (FFP) using the calculated Firm Target Price as basis
Final Construction Price (FFP) Negotiated:
(CANNOT EXCEED THE ESTABLISHED CCP)$
FIRM TARGET PRICE CALCULATIONS (COST OVERRUN SCENARIO)
Step 2 - Production Point
Firm Target Cost$550,000,000.00
Delta($50,000,000.00)
Contractor Share of Delta($25,000,000.00)
Firm Target Profit$20,000,000.003.64%
Firm Profit No Less than Minimum Profit (Floor)$16,500,000.003.00%
Firm Profit No More than Maximum (Ceiling)$66,000,000.0012.00%
Firm Target Price$570,000,000.00
Step 3 - Negotiate Final Construction Price (FFP) using the calculated Firm Target Price as basis
Final Construction Price (FFP) Negotiated:
(CANNOT EXCEED THE ESTABLISHED CCP)$

Step 1 Initial Target Cost Step 2 Firm Target Cost Step 3 FFP or Off-Ramp Established by RFP Proposed By Contractor Proposed By Contractor Negotiated

FFP

Example Calculation of a Cost Underrun Example Calculation of a Cost Overrun

File details come from the government source that posted it. Updated .