This presentation provides details on a draft request for proposals for a fish passage facility at the Howard A. Hanson Dam. The U.S. Army Corps of Engineers Seattle District and Tacoma Public Utilities are seeking pre-construction services and integrated design-build services for the construction of a new downstream fish passage facility. Firms will collaborate with the design team on constructability, cost estimates, and construction sequencing during the pre-construction phase. A firm-fixed-price contract with economic price adjustment is contemplated. The evaluation criteria include past performance, pre-construction approach, construction management approach, small business commitment, and price. The site visit overview and detail maps provide location information for the dam and proposed fish passage areas. Interested offerors are requested to submit questions by January 5th, 2024 via the ProjNet website.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HOWARD A HANSON DAM
ADDITIONAL WATER STORAGE PROJECT
FISH PASSAGE FACILITY
DRAFT RFP PRESENTATION TO INDUSTRY
NOVEMBER 2023
US Army Corps of Engineers, Seattle Tyler Patterson, Tacoma Water Nancy Chin, Project Manager Michael Peele, Technical Lead John Solomon, Contracting Officer Gregory Cook, Contract Specialist Alex Marcinkiewicz, Contract Specialist Sarah Kivela, Assistant Project Manger
USACE considers procurement integrity a priority throughout this process, including in these early pre-solicitation exchanges. The draft RFP is subject to change.
We anticipate informal exchanges of information continuing throughout the acquisition. The exchanges will become more formal as we move into the solicitation phase. Upon issuing the Solicitation, the Procurement Integrity Act applies, and the exchanges become formal.
If you share proprietary or confidential information, please identify it so we can take steps to appropriately manage and protect the information.
USACE is in listening mode. Our Project Delivery Team will use your shared knowledge and information to help us with acquisition planning drafting the RFP.
Please submit your questions/inquiries regarding the draft RPM and/or this event via ProjNet [www.projnet.org].
PROCUREMENT INTEGRITY
PRESENTATION TOPICS
*All information is preliminary and subject to change.
• Purpose
• Overview of Draft RFP
• Questions for Industry and Instructions
• Upcoming Site Visit
• Next Steps
TACOMA WATER PROJECT SPONSORSHIP
Mission: Provide clean, reliable water to the region
Tacoma Water, Public Utilities:
117 square miles of service area 290 employees Service to ~ 1 million people Facilities within 4 miles downriver from HAHD
Water Supply:
Green River is 90-95% of drinking water source Up to 150 MGD from Green River 48 MGD from local wells
Primary Operational Concerns During Construction:
Aquatic and terrestrial invasive species Hazardous spills Security and safety of facility and watershed Road use and maintenance
BACKGROUND
Location: 35 miles SE of Seattle at River Mile 64 on Green River
Congressionally Authorized Purposes:
Flood Risk Management and Conservation (1950) Water Supply and Ecosystem Restoration (1999)
Fish Passage:
Upstream: Sponsor trap/haul (complete) Downstream: Authorized in Additional Water Storage Project with Tacoma Public Utilities
RFP:
Pre-Construction Services Construct a New State of the Art Downstream Fish Passage Facility for outmigrating juvenile salmon
1. Draft Firm-Fixed-Price with Economic Price Adjustment utilizing Integrated Design and Construction delivery method
2. Draft Instructions to Offerors with Price Schedule
3. Draft Proposal Elements and Evaluation Criteria
4. Draft Statement of Work for Pre-Construction Services
5. Draft Specifications
6. Draft Attachments
DRAFT RFP ELEMENTS
Purpose: DRAFT RFP provided to obtain input prior to the RFP solicitation
DRAFT RFP ELEMENT #1: CONTRACT TYPE
Draft Firm-Fixed-Price with Economic Price Adjustment utilizing Integrated Design and Construction (IDaC) delivery method Section 00 72 00
Integrated Design and Construction
Design
Firm-Fixed-Price Construction FinishPre-Construction ServiceProposal
Traditional FFP Administration
Issue RFP to Convert Option
DRAFT RFP ELEMENT #2: DRAFT INSTRUCTIONS
Draft Instructions to Offerors with Price Schedule Section 00 10 00
• Factor 1: Past Performance
• Factor 2: Pre-Construction Services
• Factor 3: Construction Management Approach
• Factor 4: Small Business Commitment
• Factor 5: Cost/Price
DRAFT RFP ELEMENT #3: PROPOSAL ELEMENTS
Draft Evaluation Criteria Factors Section 00 22 16
(Best Value Trade-off)
Collaborate with the design team and provide feedback:
• Constructability
• Means and methods
• Market conditions
• Cost estimates
• Construction sequencing
DRAFT RFP ELEMENT #4: STATEMENT OF WORK
Pre-construction services: Section 01 00 00
DRAFT RFP ELEMENT #4: STATEMENT OF WORK
Critical for early Intake/Bulkhead Effort?
• Modifying existing cofferdam
• Subject to reservoir fluctuations
• Limited work period for low pool
~Nov 1 to Mar 1
• Current concept utilizes precast concrete blocks grouted in place during low pool periods
Pre-construction services: Example
• Seasonal Reservoir Conditions Section 01 14 10
• Permits 01 57 19
• Decontamination of Equipment and Supplies 01 57 19-A
DRAFT RFP ELEMENT #5: SPECIFICATIONS
Site-specific information
• Solicitation will contain table of contents
• Technical specifications will be developed during the pre-construction services
DRAFT RFP ELEMENT #5: SPECIFICATIONS
Technical Specifications
DRAFT RFP ELEMENT #6: ATTACHMENTS
Draft Plans and Final RFP Attachments
• Watch sam.gov for updated draft drawings
• See Questions to Industry for Primes Written Response directly to GOVT due January 5th. Primes will have an opportunity for 1x1 engagement with GOVT in January 2024
NEXT STEPS
• Hanson Dam Site Visit – Pre-Registration required by December 4th
• Inquiries submit via www.projnet.org Bidder Inquiry Key is: 4M4T85-UNCM3X http://www.projnet.org/
Notes:
• All attendees required to bring
Government issued Identification
• Time of tour(s) will be determined once attendee list is finalized
• Number of attendees per company may be limited
• Dress for the weather and bring water
• Cell phone service is not available at site
• Active tour anticipated to be 2 hours
• Questions can be sent via www.projnet.org
PRE-REGISTER NO LATER THAN DECEMBER 4TH
Join us December 13th for an Industry Site Visit at Howard A. Hanson Dam!
35873 SE Green River Headworks Rd, Ravensdale, WA 98051
Registration email must be formatted as follows:
TO: sarah.m.kivela@uace.army.mil and alex.r.marcinkiewicz@usace.army.mil SUBJECT: Industry Day/Site Visit Attendance
COMPANY NAME:
NUMBER OF ATTENDEES TO VISIT:
ATTENDEE FULL NAME (FIRST MIDDLE LAST):
*Foreign Nationals are subject to advanced security screening. Please indicate in registration for further coordination.
mailto:sarah.m.kivela@uace.army.mil mailto:gregory.a.cook@usace.army.mil
HAHD SITE VISIT OVERVIEW MAP
HAHD SITE VISIT DETAIL MAP
DOWNSTREAM FISH PASSAGE
Fixed Multiport Collector
Deceleration Tunnel
Outlet Structure Stilling BasinExisting
Tunnel
Existing Bridge
Intake/Cofferdam
Existing Outlet
THANK YOU
Contact Information:
Contract Specialist Alex Marcinkiewicz alex.r.marcinkiewicz@usace.army.mil
Contract Specialist Gregory Cook gregory.a.cook@usace.army.mil mailto:alex.r.marcinkiewicz@usace.army.mil mailto:gregory.a.cook@usace.army.mil
Bidder Inquiry Key is:
4M4T85-UNCM3X
PROJNET.ORG INQUIRY
| Howard A Hanson Dam�additional water storage project�fish passage facility�DRAFT RFP PRESENTATION TO INDUSTRY�NOVEMBER 2023 |
| Procurement integrity |
| Presentation topics |
| Tacoma water project sponsorship |
| background |
| DRAFT RFP elements |
| DRAFT RFP element #1: contract type |
| DRAFT RFP element #2: Draft instructions |
| DRAFT RFP element #3: proposal elements |
| DRAFT RFP element #4: statement of work |
| DRAFT RFP element #4: statement of work |
| DRAFT RFP element #5: Specifications |
| DRAFT RFP element #5: Specifications |
| DRAFT RFP element #6: attachments |
| Next steps |
| Pre-register no later than December 4th |
| HAHD Site visit Overview Map |
| HAHD Site visit detail Map |
| Downstream fish passage |
| Thank you |
| Projnet.org inquiry |
File details come from the government source that posted it. Updated .