This is Amendment 0006 to solicitation W912DS24B0015 for the Spring Creek North Ecosystem Restoration Project in Queens & Brooklyn, New York, issued by the US Army Corps of Engineers New York District on January 10, 2025.

The amendment makes one substantive change to specification section 31 00 10 part 2.1.1.1, revising the acceptable pH range for sand fill from 4.0-6.0 to 4.0-8.0. The amendment also includes Q&A responses addressing contractor inquiries about sand gradation requirements, hydrographic surveys, and placement tolerances. The government declined to modify the gradation specifications or placement tolerance requirements (+/-0.1ft for thin layer cap), noting the tolerance "is achievable and has been a standard on past projects." The government confirmed a hydrographic survey of Jamaica Bay will be provided to the awarded contractor. No drawings or other specifications were added, deleted or modified by this amendment.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Continuation Page for the purpose of this amendment.

Offeror must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 10-Jan-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS24B0015

X 9B. DATED (SEE ITEM 11)

19-Sep-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Jan-2025

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS24B0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS

The following have been added by full text:

AMENDMENT 06

Spring Creek North Ecosystem Restoration Project Queens & Brooklyn, New York

Amendment 0006

AMENDMENT 0006 for Spring Creek North Ecosystem Restoration Project Queens & Brooklyn, New York. W912DS24B0015.

TO BIDDERS:

The following changes shall be made to the drawings and specifications.

DRAWINGS:

1. The following DRAWINGS have been REVISED and REISSUED:

a. None

2. The following DRAWINGS have been REVISED but NOT REISSUED:

3. The following NEW DETAILS have been ADDED:

4. The following DRAWINGS have been DELETED:

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

a. None.

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

a. Specification section 31 00 10 part 2.1.1.1 Composition- pH range of 4.0 to 6.0 has been revised to pH range of 4.0 to 8.0.

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

(Questions that may be of general interest to all Bidders and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).

Questions and answers are issued to the bidders “For Information Only” and do not revise the solicitation, plans or specifications.)

Bidder Inquiry 01: Spec Section 31 00 10, Part 2, 2.1.1.1 Composition: We have reached out to multiple local suppliers and they can not meet the required gradation requirements. Please consider loosing the gradation specifications.

Government Response: The government will consider this but there are no changes to the specifications at this time.

Bidder Inquiry 02: Spec Section 31 00 10, Part 2, 2.1.1.1 Composition: If we must meet the gradation requirements for clean sand, please provide the suppliers that can meet the requirements.

Government Response: The government cannot specify suppliers for clean sand.

Bidder Inquiry 03: Has there been a hydrographic survey of Jamica Bay that you can provide, specifically the area identified for “Staging area for material delivery via Barge and on-site slurry plant” on drawing GC-401? We have concerns about the water depth and being able to deliver sand via barge to that location.

Government Response: A hydrographic survey will be provided to the awarded contractor.

Bidder Inquiry 04: Specification section 31 00 10 part 2.1.1.1 Composition - has a pH range of 4.0 to

6.0. Please consider raising the pH level to 9.0 for this material.

Government Response: The government will accept a pH range of up to 8.0 for the sand fill.

Bidder Inquiry 05: The required tolerance for the thin layer cap of +/-0.1ft is not possible in a marsh environment especially given the unknown settlement rate that may or may not occur during the 2 week tidal flushing events. Please consider expanding the allowable tolerance for the placement operations.

Government Response: The required tolerance is achievable and has been a standard on past projects.

ADDITIONAL INFORMATION TO BIDDERS

N/A