This document is an unofficial announcement from the Contract Specialist regarding Amendment 0010 for the Port Monmouth Hurricane and Storm Damage Reduction Project, Solicitation Number W912DS24B0014. The amendment is still under review and is expected to make changes to the drawings, specifications, and answer Requests for Information (RFIs). It will also extend the bid opening date from September 10 to at least a week later. If the RFIs are not approved by September 9, the amendment will solely extend the bid opening, and the RFIs will be answered in the next amendment.

The related federal contract opportunity is for the construction of the Phase II, Contract 4B components of the Port Monmouth Hurricane and Storm Damage Reduction Project in Middletown Township, New Jersey. The project scope includes the construction of 1,521 LF Floodwall, 1,040 LF Levee, 3,100 CY Contaminated non-hazardous material, 15,510 CY Haul and Dispose of excess/unsatisfactory material, 2,405 CY Borrow Material, 2 Road Closure gates, and 119,300 LF Steel H-Piles. This project will be acquired as a Small Business Set-Aside, and the Invitation for Bids (IFB) is expected to be issued on or about May 10, 2024, with bids due approximately 30 days later. The base period of performance is 1,300 calendar days from the Notice to Proceed (NTP) date.

View the file

Other files

File Type Posted
Unofficial Abstract.pdf PDF
W912DS24B0014 Amendment 0013.pdf PDF
32 93 00 Amend0013.pdf PDF
W912DS24B0014 Amendment 0012.pdf PDF
L-104 Amend0011.pdf PDF
31 00 00.pdf PDF
32 93 00.pdf PDF
G-003 Amend0011.pdf PDF
31 62 16.16.pdf PDF
L-107.pdf PDF
W912DS24B0014 Amendment 0011.pdf PDF
S-102 FLOODWALL PLAN OVERVIEW PART 2_Amendment 11 (2024-09-16).pdf PDF
S-001 STRUCTURAL GENERAL NOTES_Amendment 11 (2024-09-16).pdf PDF
S-103 FLOODWALL PLAN OVERVIEW PART 3_Amendment 11 (2024-09-16).pdf PDF
Unofficial Announcement 09 16 2024.docx DOCX document
S-522 STRUCTURAL STEEL SHEETING_Amendment 10 (2024-09-06).pdf PDF
W912DS24B0014 Amendment 0010.pdf PDF
S-303 CAMPBELL GATE TYPICAL FLOODWALL SECTIONS-_Amendment 10 (2024-09-06).pdf PDF
C-303.pdf PDF
C-103.pdf PDF
C-203.pdf PDF
C-302.pdf PDF
G-003.pdf PDF
S-302 TYPICAL FLOOD WALL SECTIONS_Amendment 10 (2024-09-06).pdf PDF
S-304 BROADWAY GATE TYPICAL FLOODWALL SECTIONS_Amendment 10 (2024-09-06).pdf PDF
W912DS24B0014 Amendment 0009.pdf PDF
Unofficial Announcement 09 03 2024.docx DOCX document
ES-114.pdf PDF
C-106.pdf PDF
C-503.pdf PDF
C-506.pdf PDF
L-104.pdf PDF
C-513.pdf PDF
C-512.pdf PDF
ES-109.pdf PDF
ES-110.pdf PDF
C-510.pdf PDF
C-519.pdf PDF
L-103.pdf PDF
S-102 FLOODWALL PLAN OVERVIEW PART 2_Amendment 7 (2024-08-23).pdf PDF
w912ds24b0014 amendment 0008.pdf PDF
Submittal Register.pdf PDF
S-001 STRUCTURAL GENERAL NOTES_Amendment 7 (2024-08-22).pdf PDF
Table of Contents.pdf PDF
02 61 13 Port Monmouth.pdf PDF
S-107 CAMPBELL CLOSURE GATE PLAN_Amendment 7 (2024-08-22).pdf PDF
W912DS24B0014 Amendment 0007.pdf PDF
Unofficial Announcement 08 23 2024.docx DOCX document
01 50 00 Amendment 0006.pdf PDF
31 62 16.16 Amendment 0006.pdf PDF
Show 40 more

Latest 50 of 82 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNOFFICIAL MESSAGE FROM THE CONTRACT SPECIALIST

September 7, 2024

Amendment 0010 is still being reviewed by our Office of Counsel.

The amendment makes some changes in the Drawings and Specifications, and answers the RFIs.

It will also extend the bid opening date from September 10 to at least a week or so.

If the RFIs are not approved by September 9, Amendment 0010 will solely extend the bid opening; and the RFIs will be answered in the next amendment.

Thank you very much for your continued patience.

The purpose of this message is to give you an idea of what is being planned by us (so that you can plan accordingly) before the official announcements are published.