This document is a section of the specification for the earthwork requirements of the Port Monmouth Phase II Contract 4B project in New Jersey. The key details are:

The project involves the construction of 1,521 LF of floodwall, 1,040 LF of levee, and other site work. Excavation and backfill requirements are specified, including classifications of common excavation, rock excavation, and borrow materials. Detailed specifications are provided for the select granular, gravel, and earth fill materials to be used. Compaction, testing, and placement requirements are defined, including for the levee toe drain construction. The document also covers shoring, dewatering, and final grading and site restoration work.

View the file

Other files

File Type Posted
Unofficial Abstract.pdf PDF
W912DS24B0014 Amendment 0013.pdf PDF
32 93 00 Amend0013.pdf PDF
W912DS24B0014 Amendment 0012.pdf PDF
L-104 Amend0011.pdf PDF
32 93 00.pdf PDF
G-003 Amend0011.pdf PDF
31 62 16.16.pdf PDF
L-107.pdf PDF
W912DS24B0014 Amendment 0011.pdf PDF
S-102 FLOODWALL PLAN OVERVIEW PART 2_Amendment 11 (2024-09-16).pdf PDF
S-001 STRUCTURAL GENERAL NOTES_Amendment 11 (2024-09-16).pdf PDF
S-103 FLOODWALL PLAN OVERVIEW PART 3_Amendment 11 (2024-09-16).pdf PDF
Unofficial Announcement 09 16 2024.docx DOCX document
S-522 STRUCTURAL STEEL SHEETING_Amendment 10 (2024-09-06).pdf PDF
W912DS24B0014 Amendment 0010.pdf PDF
S-303 CAMPBELL GATE TYPICAL FLOODWALL SECTIONS-_Amendment 10 (2024-09-06).pdf PDF
C-303.pdf PDF
C-103.pdf PDF
C-203.pdf PDF
C-302.pdf PDF
G-003.pdf PDF
S-302 TYPICAL FLOOD WALL SECTIONS_Amendment 10 (2024-09-06).pdf PDF
S-304 BROADWAY GATE TYPICAL FLOODWALL SECTIONS_Amendment 10 (2024-09-06).pdf PDF
Unofficial Announcement 09 07 2024.docx DOCX document
W912DS24B0014 Amendment 0009.pdf PDF
Unofficial Announcement 09 03 2024.docx DOCX document
ES-114.pdf PDF
C-106.pdf PDF
C-503.pdf PDF
C-506.pdf PDF
L-104.pdf PDF
C-513.pdf PDF
C-512.pdf PDF
ES-109.pdf PDF
ES-110.pdf PDF
C-510.pdf PDF
C-519.pdf PDF
L-103.pdf PDF
S-102 FLOODWALL PLAN OVERVIEW PART 2_Amendment 7 (2024-08-23).pdf PDF
w912ds24b0014 amendment 0008.pdf PDF
Submittal Register.pdf PDF
S-001 STRUCTURAL GENERAL NOTES_Amendment 7 (2024-08-22).pdf PDF
Table of Contents.pdf PDF
02 61 13 Port Monmouth.pdf PDF
S-107 CAMPBELL CLOSURE GATE PLAN_Amendment 7 (2024-08-22).pdf PDF
W912DS24B0014 Amendment 0007.pdf PDF
Unofficial Announcement 08 23 2024.docx DOCX document
01 50 00 Amendment 0006.pdf PDF
31 62 16.16 Amendment 0006.pdf PDF
Show 40 more

Latest 50 of 82 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Port Monmouth Phase II Contract 4B NJ

Amendment 11

PORTMONPIICT4B

SECTION 31 00 00 Page 1

SECTION 31 00 00

EARTHWORK

PART 1 GENERAL

1.1 MEASUREMENT PROCEDURES

1.1.1 Excavation

The unit of measurement for excavation and borrow will be the cubic yard, computed by the average end area method from cross sections taken before and after the excavation and borrow operations, including the excavation for ditches, gutters, and channel changes, when the material is acceptably utilized or disposed of as herein specified. The measurements will include authorized excavation of rock (except for piping trenches that is covered below), authorized excavation of unsatisfactory subgrade soil, and the volume of loose, scattered rocks and boulders collected within the limits of the work; allowance will be made on the same basis for selected backfill ordered as replacement. The measurement will not include the volume of subgrade material or other material that is scarified or plowed and reused in-place, and will not include the volume excavated without authorization or the volume of any material used for purposes other than directed. The volume of overburden stripped from borrow pits and the volume of excavation for ditches to drain borrow pits, unless used as borrow material, will not be measured for payment. The measurement will not include the volume of any excavation performed prior to the taking of elevations and measurements of the undisturbed grade.

1.1.2 Piping Trench Excavation

Measure trench excavation by the number of linear feet along the centerline of the trench and excavate to the depths and widths specified for the particular size of pipe. Replace unstable trench bottoms with a selected granular material. Include the additional width at manholes and similar structures, the furnishing, placing and removal of sheeting and bracing, pumping and bailing, and all incidentals necessary to complete the work required by this section.

1.1.3 Rock Excavation for Trenches

Measure and pay for rock excavation by the number of cubic yards of acceptably excavated rock material. Measure the material in place, but base volume on a maximum 30 inches width for pipes 12 inches in diameter or less, and a maximum width of 16 inches greater than the outside diameter of the pipe for pipes over 12 inches in diameter. Provide the measurement to include all authorized overdepth rock excavation as determined by the Contracting Officer. For manholes and other appurtenances, compute volumes of rock excavation on the basis of 1 foot outside of the wall lines of the structures.

1.1.4 Topsoil Requirements

Separate excavation, hauling, and spreading or piling of topsoil and related miscellaneous operations will be considered subsidiary obligations of the Contractor, covered under the contract unit price for excavation.

SECTION 31 00 00 Page 2

1.1.5 Overhaul Requirements

Allow the unit of measurement for overhaul to be the station-yard. The overhaul distance will be the distance in stations between the center of volume of the overhaul material in its original position and the center of volume after placing, minus the free-haul distance in stations. The haul distance will be measured along the shortest route determined by the

Contracting Officer as feasible and satisfactory. Do not measure or waste unsatisfactory materials for overhaul where the length of haul for borrow is within the free-haul limits.

1.1.6 Select Granular Material

Measure select granular material in place as the actual cubic yards replacing wet or unstable material in trench bottoms in authorized overdepth areas. Provide unit prices which include furnishing and placing the granular material, excavation and disposal of unsatisfactory material, and additional requirements for sheeting and bracing, pumping, bailing, cleaning, and other incidentals necessary to complete the work.

1.2 PAYMENT PROCEDURES

Payment will constitute full compensation for all labor, equipment, tools, supplies, and incidentals necessary to complete the work.

1.2.1 Classified Excavation

Classified excavation will be paid for at the contract unit prices per cubic yard for common or rock excavation.

1.2.2 Piping Trench Excavation

Payment for trench excavation will constitute full payment for excavation and backfilling, including specified overdepth, except in rock or unstable trench bottoms.

1.2.3 Rock Excavation for Trenches

Payment for rock excavation will be made in addition to the price bid for the trench excavation, and will include all necessary drilling and blasting and all incidentals necessary to excavate and dispose of the rock. Select granular material, used as backfill replacing rock excavation, will not be paid for separately, but will be included in the unit price for rock excavation.

1.2.4 Unclassified Excavation

Unclassified excavation will be paid for at the contract unit price per cubic yard for unclassified excavation.

1.2.5 Classified Borrow

Classified borrow will be paid for at the contract unit prices per cubic yard for common or rock borrow.

1.2.6 Unclassified Borrow

Unclassified borrow will be paid for at the contract unit price per cubic

SECTION 31 00 00 Page 3 yard for unclassified borrow.

1.2.7 Authorized Overhaul

The number of station-yards of overhaul to be paid for will be the product of number of cubic yards of overhaul material measured in the original position, multiplied by the overhaul distance measured in stations of 100 feet and will be paid for at the contract unit price per station-yard for overhaul in excess of the free-haul limit as designated in paragraph

DEFINITIONS.

1.2.8 Sheeting and Bracing

Sheeting and bracing, when shown or authorized by the Contracting Officer to be left in place, will be paid for as follows:

1.2.8.1 Timber Sheeting

Timber sheeting will be paid for as the number of board feet of lumber below finish grade measured in place prior to backfilling. Include in the measurement sheeting wasted when cut off between the finished grade and 1 foot below the finished grade.

1.2.8.2 Steel Sheeting and Soldier Piles

Steel sheeting, soldier piles, and steel bracing will be paid for according to the number of pounds of steel calculated. Calculate the steel by multiplying the measured in-place length in feet below finish grade by the unit weight of the section in pounds per foot. Obtain unit weight of rolled steel sections from recognized steel manuals.

1.3 CRITERIA FOR BIDDING

Base bids on the following criteria:

a. Surface elevations are as indicated.

b. Pipes or other artificial obstructions, except those indicated, will not be encountered.

c. Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.

d. Ground water elevation is 1 to 3 feet below existing surface elevation.

e. Material character is indicated by the boring logs.

f. Hard materials and rock will not be encountered in 90 percent of the excavations .

1.4 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

SECTION 31 00 00 Page 4

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO T 180 (2017) Standard Method of Test for

Moisture-Density Relations of Soils Using a 4.54-kg (10-lb) Rammer and a 457-mm

(18-in.) Drop

AASHTO T 224 (2010) Standard Method of Test for

Correction for Coarse Particles in the

Soil Compaction Test

AMERICAN WATER WORKS ASSOCIATION (AWWA)

AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances

AMERICAN WELDING SOCIETY (AWS)

AWS D1.1/D1.1M (2020) Structural Welding Code - Steel

AMERICAN WOOD PROTECTION ASSOCIATION (AWPA)

AWPA P5 (2015) Standard for Waterborne

Preservatives

ASTM INTERNATIONAL (ASTM)

ASTM A139/A139M (2016) Standard Specification for

Electric-Fusion (ARC)-Welded Steel Pipe

(NPS 4 and over)

ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe Piles

ASTM C136/C136M (2019) Standard Test Method for Sieve

Analysis of Fine and Coarse Aggregates

ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using

Standard Effort (12,400 ft-lbf/cu. ft.

(600 kN-m/cu. m.))

ASTM D1140 (2017) Standard Test Methods for

Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by

Washing

ASTM D1556/D1556M (2015; E 2016) Standard Test Method for

Density and Unit Weight of Soil in Place by Sand-Cone Method

ASTM D1557 (2012; E 2015) Standard Test Methods for

Laboratory Compaction Characteristics of

Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)

ASTM D1586/D1586M (2018) Standard Test Method for Standard

Penetration Test (SPT) and Split-Barrel

SECTION 31 00 00 Page 5

Sampling of Soils

ASTM D1883 (2016) Standard Test Method for California

Bearing Ratio (CBR) of

Laboratory-Compacted Soils

ASTM D2434 (1968; R 2006) Permeability of Granular

Soils (Constant Head)

ASTM D2487 (2017; E 2020) Standard Practice for

Classification of Soils for Engineering

Purposes (Unified Soil Classification

System)

ASTM D4253 (2016; E 2019) Standard Test Methods for

Maximum Index Density and Unit Weight of

Soils Using a Vibratory Table

ASTM D4254 (2016) Standard Test Methods for Minimum

Index Density and Unit Weight of Soils and

Calculation of Relative Density

ASTM D4318 (2017; E 2018) Standard Test Methods for

Liquid Limit, Plastic Limit, and

Plasticity Index of Soils

ASTM D6938 (2017a) Standard Test Method for In-Place

Density and Water Content of Soil and

Soil-Aggregate by Nuclear Methods (Shallow

Depth)

ASTM D5778 (2020) Standard Test Method for

Electronic Friction Cone and Piezocone

Penetration Testing of Soils

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 1110-2-1913 (2000) Engineering and Design; Design and

Construction of Levees

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA 600/4-79/020 (1983) Methods for Chemical Analysis of

Water and Wastes

EPA SW-846.3-3 (1999, Third Edition, Update III-A) Test

Methods for Evaluating Solid Waste:

Physical/Chemical Methods

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

CID A-A-203 (Rev C; Notice 3) Paper, Kraft, Untreated

1.5 DEFINITIONS

1.5.1 Satisfactory Materials

Satisfactory materials comprise any materials classified by ASTM D2487 as

GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, and SP. Satisfactory materials for grading comprise stones less than 8 inches, except for fill

SECTION 31 00 00 Page 6 material for pavements and railroads which comprise stones less than 3 inches in any dimension.

1.5.2 Unsatisfactory Materials

Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as satisfactory which contains root and other organic matter or frozen material. Notify the Contracting Officer when encountering any contaminated materials.

1.5.3 Cohesionless and Cohesive Materials

Cohesionless materials include materials classified in ASTM D2487 as GW, GP, SW, and SP. Cohesive materials include materials classified as GC, SC, ML, CL, MH, and CH. Materials classified as GM and SM will be identified as cohesionless only when the fines are nonplastic. Perform testing, required for classifying materials, in accordance with ASTM D4318, ASTM C136/C136M and ASTM D1140.

1.5.4 Degree of Compaction

Degree of compaction required, except as noted in the second sentence, is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557 abbreviated as a percent of laboratory maximum density. Since ASTM D1557 applies only to soils that have 30 percent or less by weight of their particles retained on the 3/4 inch sieve, express the degree of compaction for material having more than 30 percent by weight of their particles retained on the 3/4 inch sieve as a percentage of the maximum density in accordance with AASHTO T 180 and corrected with AASHTO T 224. To maintain the same percentage of coarse material, use the "remove and replace" procedure as described in NOTE 8 of

Paragraph 7.2 in AASHTO T 180.

1.5.5 Overhaul

Overhaul is the authorized transportation of satisfactory excavation or borrow materials in excess of the free-haul limit of 10 stations.

Overhaul is the product of the quantity of materials hauled beyond the free-haul limit, and the distance such materials are hauled beyond the free-haul limit, expressed in station yards.

1.5.6 Topsoil

Material suitable for topsoils obtained from offsite areas or excavations is defined as: Natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than one inch diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Amend topsoil pH range to obtain a pH of 5.5 to 7.

1.5.7 Hard/Unyielding Materials

Hard/Unyielding materials comprise weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" with stones greater than 12 inches in any dimension or as defined by the pipe manufacturer, whichever is smaller. These materials usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.

SECTION 31 00 00 Page 7

1.5.8 Rock

Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.

1.5.9 Unstable Material

Unstable materials are too wet to properly support the utility pipe, conduit, or appurtenant structure.

1.5.10 Select Granular Material

1.5.10.1 General Requirements

Select granular material consist of materials classified as GW, GP, SW, or

SP, SM, SC, or SC-SM, by ASTM D2487 where indicated. The liquid limit of such material must not exceed 35 percent when tested in accordance with

ASTM D4318. The plasticity index must not be greater than 12 percent when tested in accordance with ASTM D4318, and not more than 35 percent by weight may be finer than No. 200 sieve when tested in accordance with

ASTM D1140. Provide a minimum coefficient of permeability of 0.0004 feet per minute when tested in accordance with ASTM D2434.

1.5.10.2 California Bearing Ratio Values

Bearing Ratio: At 0.1 inch penetration, provide a bearing ratio of at least 25 percent at 95 percent ASTM D1557 maximum density as determined in accordance with ASTM D1883 for a laboratory soaking period of not less than 4 days. Conform the combined material to the following sieve analysis:

Sieve Size Percent Passing by Weight

2-1/2 inches 100

No. 4 40 - 85

No. 10 20 - 80

No. 40 10 - 60

No. 200 5 - 25

1.5.11 Select Gravel Fill Material

Select gravel fill will be required for the gravel adjacent to the floodwall and shall be obtained by the Contractor. Provide materials classified as GP or GW by ASTM D2487 where indicated. The liquid limit of such material shall not exceed 35 percent when tested in accordance with

ASTM D4318. The plasticity index shall not be greater than 0 percent when

SECTION 31 00 00 Page 8 tested in accordance with ASTM D4318, and not more than 5 percent by weight shall be finer than No. 200 sieve when tested in accordance with

ASTM D1140. The select gravel fill be determined by a registered

Professional Engineer in the State of New Jersey in accordance with

Appendix D of EM 1110-2-1913 or another approved method. The gradation may change throughout the jobsite as needed. This determination shall be submitted to the Government for approval. The following gradation shall be used for bidding purposes only.

Sieve Size Percent Passing by Weight

1-1/2 inches 100

1 inch 90 - 100

1/2 inches 65 - 95

3/8 inch 45 - 85

No. 4 20 - 45

No. 30 0 - 15

No. 200 0 - 5

1.5.12 Select Granular Fill Material

Select granular fill will be required for the sand material adjacent to the floodwall, and for the sand toe drain in the levee section, and backfill for the cofferdam on Campbells Avenue and shall be obtained by the Contractor. Provide materials classified as SP or SW by ASTM D2487 where indicated. The liquid limit of such material shall not exceed 40 percent when tested in accordance with ASTM D4318. The plasticity index shall not be greater than 0 percent when tested in accordance with ASTM

D4318, and not more than 5 percent by weight shall be finer than No. 200 sieve when tested in accordance with ASTM D1140. The select granular fill be determined by a registered Professional Engineer in the State of New

Jersey in accordance with Appendix D of EM 1110-2-1913 or another approved method. The select granular fill must meet filter criteria for the native soil, embankment fill, and the select gravel fill as applicable. The gradation may change throughout the jobsite as needed. This determination shall be submitted to the Government for approval.

1.5.13 Select Earth Fill Material

Select earth fill material will be required for the earth embankment and shall be obtained by the Contractor. The select earth fill materials shall have a plasticity index (PI) between 5 and 50 as determined by ASTM

D 4318 testing method. The select earth fill shall be well graded having a maximum particle size not exceeding 1/2 of the placement lift thickness and not less than 35% by weight passing a Standard No. 200 sieve. The select earth fill shall consist of materials meeting the above requirements and classified in ASTM D 2487 as clays (CL), silty or sandy clays (CL-ML, CL); silts (ML), clayey sands (SC), or clayey gravels (GC).

All stones and rock fragments exceeding 2/3 of the placement lift thickness shall be removed at the source prior to hauling to the fill.

Uniform silts or sands, soft organic soils, frozen materials, or other

SECTION 31 00 00 Page 9 soils deemed unsuitable by the Contracting Officer shall not be utilized in the select earth fill. Uniform silts or sands are defined as silts and sands with a uniformity coefficient (Cu=D60/D10) which is less than 6.

1.5.14 Sand Filter Material

Sand filter material will be required for the toe drain and shall be obtained by the Contractor. The sand filter material shall have a plasticity index (PI) of 0 percent and be classified as (SW) or (SP) as tested by ASTM D2487. Submit gradation test results of the proposed sand filter material to the Government for approval. The following gradation table is for bidding purposed only:

Sieve Size Percent Passing

3/8 inch 100.0

No. 4 95-100

No. 8 80-100

No. 16 50-85

No. 30 25-65

No. 14 15-20

No. 20 10-15

No. 100 5-10

No. 200 0-2

1.5.15 Gravel Filter Material

Gravel filter material will be required for the toe drain and shall be obtained by the Contractor. The gravel filter material shall have a plasticity index (PI) of 0 percent and be classified as (GW) or (GP) as tested by ASTM D2487. Submit gradation test results of the proposed gravel filter material to the Government for approval. The following gradation table is for bidding purposed only:

Sieve Size Percent Passing

1-1/2 inches 100.0

1 inch 80-90

3/4 inch 45-85

1/2 inch 25-45

3/8 inch 15-20

SECTION 31 00 00 Page 10

No. 4 10-15

No. 30 5-10

No. 200 0-2

1.5.16 Initial Backfill Material

Initial backfill consists of select granular material or satisfactory materials free from rocks 2 inches or larger in any dimension or free from rocks of such size as recommended by the pipe manufacturer, whichever is smaller. When the pipe is coated or wrapped for corrosion protection, free the initial backfill material of stones larger than 1 inches in any dimension or as recommended by the pipe manufacturer, whichever is smaller.

1.5.17 Expansive Soils

Expansive soils are defined as soils that have a plasticity index equal to or greater than 25 percent when tested in accordance with ASTM D4318.

1.5.18 Nonfrost Susceptible (NFS) Material

Nonfrost susceptible material are a uniformly graded washed sand with a maximum particle size of 0.187 inches (passing the No. 4 sieve) and less than 5 percent passing the No. 200 size sieve, and with not more than 3 percent by weight finer than 0.02 mm grain size.

1.5.19 Pile Supported Structure

As used herein, a structure where both the foundation and floor slab are pile supported.

1.6 SYSTEM DESCRIPTION

Subsurface soil boring logs are included in Section 00 31 32.02 18. The subsoil investigation report and samples of materials taken from subsurface investigations may be examined at the U.S. Army Corps of

Engineers - Baltimore District Office (NAB) Materials and Investigations

Unit, Fort McHenry, Baltimore, MD. These data represent the best subsurface information available; however, variations may exist in the subsurface between boring locations.

1.6.1 Classification of Excavation

No consideration will be given to the nature of the materials, and all excavation will be designated as unclassified excavation. Finish the specified excavation on a classified basis, in accordance with the following designations and classifications.

1.6.1.1 Common Excavation

Include common excavation with the satisfactory removal and disposal of all materials not classified as rock excavation.

1.6.1.2 Rock Excavation

Submit notification of encountering rock in the project although bedrock is not expected to be encountered. Include rock excavation with blasting, SECTION 31 00 00 Page 11 excavating, grading, disposing of material classified as rock, and the satisfactory removal and disposal of boulders 1/2 cubic yard or more in volume; solid rock; rock material that is in ledges, bedded deposits, and unstratified masses, which cannot be removed without systematic drilling and blasting; firmly cemented conglomerate deposits possessing the characteristics of solid rock impossible to remove without systematic drilling and blasting; and hard materials (see Definitions). Include the removal of any concrete or masonry structures, except pavements, exceeding

1/2 cubic yard in volume that may be encountered in the work in this classification. If at any time during excavation, including excavation from borrow areas, the Contractor encounters material that may be classified as rock excavation, uncover such material and notify the

Contracting Officer. Do not proceed with the excavation of this material until the Contracting Officer has classified the materials as common excavation or rock excavation and has taken cross sections as required.

Failure on the part of the Contractor to uncover such material, notify the

Contracting Officer, and allow ample time for classification and cross sectioning of the undisturbed surface of such material will cause the forfeiture of the Contractor's right of claim to any classification or volume of material to be paid for other than that allowed by the

Contracting Officer for the areas of work in which such deposits occur.

1.6.2 Blasting

Blasting will not be permitted.

1.6.3 Dewatering Work Plan

Submit procedures for accomplishing dewatering work.

1.7 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Shoring; G, DO

Dewatering Work Plan; G, DO

SD-02 Shop Drawings

Toe Drain Gradation; G, RO

Levee Toe Drain; G, RO

SD-03 Product Data

Utilization of Excavated Materials; G, DO

Rock Excavation

Opening of any Excavation or Borrow Pit

Shoulder Construction

SD-05 Design Data

Toe Drain Gradation Report; G, DO

SECTION 31 00 00 Page 12

SD-06 Test Reports

Testing

Borrow Site Testing

Within 24 hours of conclusion of physical tests, submit 3 copies of test results, including calibration curves and results of calibration tests.

Laboratory Testing Plan

SD-07 Certificates

Testing

PART 2 PRODUCTS

2.1 REQUIREMENTS FOR OFFSITE SOILS

Test offsite soils brought in for use as backfill for Total Petroleum

Hydrocarbons (TPH), Benzene, Toluene, Ethyl Benzene, and Xylene (BTEX) and full Toxicity Characteristic Leaching Procedure (TCLP) including ignitability, corrosivity and reactivity. Backfill shall contain a maximum of 100 parts per million (ppm) of total petroleum hydrocarbons

(TPH) and a maximum of 10 ppm of the sum of Benzene, Toluene, Ethyl

Benzene, and Xylene (BTEX) and shall pass the TCPL test. Determine TPH concentrations by using EPA 600/4-79/020 Method 418.1. Determine BTEX concentrations by using EPA SW-846.3-3 Method 5030/8020. Perform TCLP in accordance with EPA SW-846.3-3 Method 1311. Provide Borrow Site Testing for TPH, BTEX and TCLP from a composite sample of material from the borrow site, with at least one test from each borrow site. Do not bring material onsite until tests have been approved by the Contracting Officer.

2.2 BURIED WARNING AND IDENTIFICATION TAPE

Provide metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines. Provide tape on rolls, 3 inches minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording.

Provide permanent color and printing, unaffected by moisture or soil.

Warning Tape Color Codes

Red Electric

Yellow Gas, Oil; Dangerous Materials

Orange Telephone and Other Communications

Blue Water Systems

Green Sewer Systems

SECTION 31 00 00 Page 13

Warning Tape Color Codes

White Steam Systems

Gray Compressed Air

2.2.1 Warning Tape for Metallic Piping

Provide acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.003 inch and a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.

2.2.2 Detectable Warning Tape for Non-Metallic Piping

Provide polyethylene plastic tape conforming to the width, color, and printing requirements specified above, with a minimum thickness of 0.004 inch, and a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Manufacture tape with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to

3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.

3.1 DETECTION WIRE FOR NON-METALLIC PIPING

Insulate a single strand, solid copper detection wire with a minimum of 12

AWG.

2.4 MATERIAL FOR RIP-RAP

Provide bedding material, geotextile, coarse aggregate, grout, and rock conforming to the following sections and in accordance with NJDOT State

Standard Specifications for Road and Bridge Construction, paragraph

603.03.03), as applicable, for construction indicated.

2.4.1 Bedding Material

Provide bedding material consisting of sand, gravel, or crushed rock, well graded with a maximum particle size of 2 inches. Compose material of tough, durable particles. Allow fines passing the No. 200 standard sieve with a plasticity index less than six.

2.4.2 Grout

Provide durable grout composed of cement, water, an air-entraining admixture, and sand mixed in proportions of one part Portland cement to two parts of sand, sufficient water to produce a workable mixture, and an amount of admixture which will entrain sufficient air, as determined by the Contracting Officer. Mix grout in a concrete mixer. Allow a sufficient mixing time to produce a mixture having a consistency permitting gravity flow into the interstices of the rip-rap with limited spading and brooming.

2.4.3 Rock

Provide rock fragments sufficiently durable to ensure permanence in the structure and the environment in which it is to be used. Use rock

SECTION 31 00 00 Page 14 fragments free from cracks, seams, and other defects that would increase the risk of deterioration from natural causes. Provide fragments sized so that no individual fragment exceeds a weight of 150 pounds and that no more than 10 percent of the mixture, by weight, consists of fragments weighing 2 pounds or less each. Provide rock with a minimum specific gravity of 2.50. Do not permit the inclusion of more than trace 2 percent quantities of dirt, sand, clay, and rock fines.

2.5 CAPILLARY WATER BARRIER

Capillary water barrier is not needed.

2.6 PIPE CASING

2.6.1 Casing Pipe

ASTM A139/A139M, Grade B, or ASTM A252, Grade 2, smooth wall pipe. Match casing size to the outside diameter and wall thickness as indicated on contract drawings. Protective coating is not required on casing pipe.

2.6.2 Wood Supports

Treated Yellow Pine or Douglas Fir, rough, structural grade. Provide wood with nonleaching water-borne pressure preservative (ACA or CCA) and treatment conforming to AWPA P5. Secure wood supports to carrier pipe with stainless steel or zinc-coated steel bands.

PART 3 EXECUTION

3.1 STRIPPING OF TOPSOIL

Where indicated or directed, strip topsoil to a depth of 12 inches.

Spread topsoil on areas already graded and prepared for topsoil, or transported and deposited in stockpiles convenient to areas that are to receive application of the topsoil later, or at locations indicated or specified. Keep topsoil separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 2 inches in diameter, and other materials that would interfere with planting and maintenance operations. Remove from the site any surplus of topsoil from excavations and gradings.

3.2 ADDITIONAL GEOTECHNICAL EXPLORATION

As soon as practical after Contract award, perform soil borings to verify the geotechnical recommendations. The Contractor shall complete the number of soil borings as shown on the plans. The Contractor shall hire a geotechnical engineering firm with at least 5 years of experience in drilling, sampling, and boring log production to complete these borings.

The borings shall be accomplished using the Standard Penetration Test

(SPT) Procedure per ASTM D1586/D1586M using a 1-3/8 inch ID x 2 foot 8 inch long split spoon sampler. Sample spoons shall be advanced automatically by a 140 pound hammer dropped 30 inches. Testing shall be accomplished at 2.5-foot intervals to a total depth of 70 feet. These explorations shall be completed and the results submitted to the

Contracting Officer for review at a minimum of 20 days before the start of fill or excavation activities. The boring logs shall be prepared in a format similar to the logs shown in Section 00 31 32.02 18 BORING DATA.

The Contractor shall retain all soil samples collected for a period of one year after completion of the soil borings and shall provide any soil

SECTION 31 00 00 Page 15 samples, at no additional charge, to the Government at the request of the

Contracting Officer.

The Contractor will perform Geotechnical Explorations on the prepared foundation subgrade for the levee embankment every 150 feet. The

Geotechnical Explorations will be a combination of the Standard Penetration testing (SPT) and Cone Penetrometer Testing (CPT). CPT will be completed in general accordance with ASTM D5778. Exploration locations will extend 10 feet or the minimum depth of the displaced soil for the levee foundation.

The Contractor will propose a laboratory testing plan that will include, but not limited to, particle size analysis of soils, permeability testing, unconfined compressive strength, etc.

3.3 GENERAL EXCAVATION

Perform excavation of every type of material encountered within the limits of the project to the lines, grades, and elevations indicated and as specified. Perform the grading in accordance with the typical sections shown and the tolerances specified in paragraph FINISHING. Transport satisfactory excavated materials and place in fill or embankment within the limits of the work. Excavate unsatisfactory materials encountered within the limits of the work below grade and replace with satisfactory materials as directed. Include such excavated material and the satisfactory material ordered as replacement in excavation. Dispose surplus satisfactory excavated material not required for fill or embankment in areas approved for surplus material storage or designated waste areas. Dispose unsatisfactory excavated material in designated waste or spoil areas. During construction, perform excavation and fill in a manner and sequence that will provide proper drainage at all times.

Excavate material required for fill or embankment in excess of that produced by excavation within the grading limits from the borrow areas indicated or from other approved areas selected by the Contractor as specified.

3.3.1 Ditches, Gutters, and Channel Changes

Finish excavation of ditches, gutters, and channel changes by cutting accurately to the cross sections, grades, and elevations shown on Contract

Drawings. Do not excavate ditches and gutters below grades shown.

Backfill the excessive open ditch or gutter excavation with satisfactory, thoroughly compacted, material or with suitable stone or cobble to grades shown. Dispose excavated material as shown or as directed, except in no case allow material be deposited a maximum 4 feet from edge of a ditch.

Maintain excavations free from detrimental quantities of leaves, brush, sticks, trash, and other debris until final acceptance of the work.

3.3.2 Drainage Structures

Make excavations to the lines, grades, and elevations shown, or as directed. Provide trenches and foundation pits of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or other hard foundation material of loose debris and cut to a firm, level, stepped, or serrated surface. Remove loose disintegrated rock and thin strata. Do not disturb the bottom of the excavation when concrete or masonry is to be placed in an excavated area. Do not excavate to the final grade level until just before the concrete or masonry is to be placed. Where pile foundations are to be used, stop the excavation of each pit at an elevation

1 foot above the base of the footing, as specified, before piles are driven. After the pile driving has been completed, remove loose and displaced material and complete excavation, leaving a smooth, solid, SECTION 31 00 00 Page 16 undisturbed surface to receive the concrete or masonry.

3.3.3 Drainage

Provide for the collection and disposal of surface and subsurface water encountered during construction. Completely drain construction site during periods of construction to keep soil materials sufficiently dry. Construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed.

3.3.4 Dewatering

Control groundwater flowing toward or into excavations to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. Do not permit French drains, sumps, ditches or trenches within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Take control measures by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, maintain the water level continuously, at least 2 feet below the working level. Operate dewatering system continuously until construction work below existing water levels is complete subject to the approval of the

Contracting Officer. Submit performance records weekly. Measure and record performance of dewatering system at same time each day by use of observation wells or piezometers installed in conjunction with the dewatering system. Relieve hydrostatic head in previous zones below subgrade elevation in layered soils to prevent uplift.

3.3.5 Trench Excavation Requirements

Excavate the trench as recommended by the manufacturer of the pipe to be installed. Slope trench walls below the top of the pipe, or make vertical, and of such width as recommended in the manufacturer's printed installation manual. Provide vertical trench walls where no manufacturer's printed installation manual is available. Shore trench walls more than 4 feet high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in. Shore vertical trench walls more than 4 feet high.

Excavate trench walls which are cut back to at least the angle of repose of the soil. Give special attention to slopes which may be adversely affected by weather or moisture content. Do not exceed the trench width below the pipe top of 24 inches plus pipe outside diameter (O.D.) for pipes of less than 24 inches inside diameter, and do not exceed 36 inches plus pipe outside diameter for sizes larger than 24 inches inside diameter. Where recommended trench widths are exceeded, provide redesign, stronger pipe, or special installation procedures by the Contractor. The

Contractor is responsible for the cost of redesign, stronger pipe, or special installation procedures without any additional cost to the

Government.

SECTION 31 00 00 Page 17

3.3.5.1 Bottom Preparation

Grade the bottoms of trenches accurately to provide uniform bearing and support for the bottom quadrant of each section of the pipe. Excavate bell holes to the necessary size at each joint or coupling to eliminate point bearing. Remove stones of 2 inches or greater in any dimension, or as recommended by the pipe manufacturer, whichever is smaller, to avoid point bearing.

3.3.5.2 Removal of Unyielding Material

Where unyielding material is encountered in the bottom of the trench, remove such material 3 inches below the required grade and replaced with suitable materials as provided in paragraph BACKFILLING AND COMPACTION.

3.3.5.3 Removal of Unstable Material

Where unstable material is encountered in the bottom of the trench, remove such material to the depth directed and replace it to the proper grade with select granular material as provided in paragraph BACKFILLING AND

COMPACTION. When removal of unstable material is required due to the

Contractor's fault or neglect in performing the work, the Contractor is responsible for excavating the resulting material and replacing it without additional cost to the Government.

3.3.5.4 Excavation for Appurtenances

Provide excavation for manholes, catch-basins, inlets, or similar structures of sufficient size to permit the placement and removal of forms for the full length and width of structure footings and foundations as shown. Clean rock or loose debris and cut to a firm surface either level, stepped, or serrated, as shown or as directed. Remove loose disintegrated rock and thin strata. Specify removal of unstable material. When concrete or masonry is to be placed in an excavated area, take special care not to disturb the bottom of the excavation. Do not excavate to the final grade level until just before the concrete or masonry is to be placed.

3.3.5.5 Jacking, Boring, and Tunneling

Unless otherwise indicated, provide excavation by open cut except that sections of a trench may be jacked, bored, or tunneled if, in the opinion of the Contracting Officer, the pipe, cable, or duct can be safely and properly installed and backfill can be properly compacted in such sections.

3.3.6 Underground Utilities

The Contractor is responsible for movement of construction machinery and equipment over pipes and utilities during construction. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. Excavation made with power-driven equipment is not permitted within 3 feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the

Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.

SECTION 31 00 00 Page 18

3.3.7 Structural Excavation

Ensure that footing subgrades have been inspected and approved by the

Contracting Officer prior to concrete placement. Excavate to bottom of pile cap prior to placing or driving piles, unless authorized otherwise by the Contracting Officer. Backfill and compact over excavations and changes in grade due to pile driving operations to 95 percent of ASTM

D698 maximum density.

3.4 SELECTION OF BORROW MATERIAL

Select borrow material to meet the requirements and conditions of the particular fill or embankment for which it is to be used. Obtain borrow material from the borrow areas within the limits of the project site, selected by the Contractor or from approved private sources. Unless otherwise provided in the contract, the Contractor is responsible for obtaining the right to procure material, pay royalties and other charges involved, and bear the expense of developing the sources, including rights-of-way for hauling from the owners. Borrow material from approved sources on Government-controlled land may be obtained without payment of royalties. Unless specifically provided, do not obtain borrow within the limits of the project site without prior written approval. Consider necessary clearing, grubbing, and satisfactory drainage of borrow pits and the disposal of debris thereon related operations to the borrow excavation.

3.5 TOE DRAIN GRADATION

Perform additional sampling during excavation of the toe trench to determine the needed gradation of sand filter material and gravel fill material as specified above. Samples shall be taken at a rate of at least one sample per 100 linear feet of trench. Sample locations shall be chosen by the Contractor's geotechnical engineering personnel or at the direction of the Contracting Officer.

3.5.1 PROFESSIONAL GEOTECHNICAL ENGINEER

Retain a Professional Engineer licensed by the State of New Jersey with five year of experience with similar work. The Professional Engineer must possess the credentials required to support the design and work described herein.

The Professional Engineer must prepare a toe drain gradation design report, which shall clearly indicate all computations and analyses for the toe drain, as well calculations for the disposition of water flow due to the toe drain design.

The Geotechnical Engineer must provide a work plan for evaluation by the

Government for the foundation preparation of the levee area that incorporates the use of Geotextiles.

The toe drain gradation report, as well as accompanying drawings, specifications, and records for the construction of the toe drain must be prepared under the direct supervision of the Professional Engineer with direct responsibility for the analysis of the toe drain. Any submittal packages for review and approval by the COR must sufficiently document the technical basis for the toe drain design. The documentation must include the methods used, the primary assumptions, and the results and conclusions of any investigations or diagnostic work conducted prior and during the design process.

SECTION 31 00 00 Page 19

3.6 OPENING AND DRAINAGE OF EXCAVATION AND BORROW PITS

Notify the Contracting Officer sufficiently in advance of the opening of any excavation or borrow pit or borrow areas to permit elevations and measurements of the undisturbed ground surface to be taken. Except as otherwise permitted, excavate borrow pits and other excavation areas providing adequate drainage. Transport overburden and other spoil material to designated spoil areas or otherwise dispose of as directed.

Provide neatly trimmed and drained borrow pits after the excavation is completed. Ensure that excavation of any area, operation of borrow pits, or dumping of spoil material results in minimum detrimental effects on natural environmental conditions.

3.7 SHORING

3.7.1 General Requirements

Submit a Shoring and Sheeting plan for approval 30 days prior to starting work. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations. Finish shoring, including sheet piling, and install as necessary to protect workmen, banks, adjacent paving, structures, and utilities. Remove shoring, bracing, and sheeting as excavations are backfilled, in a manner to prevent caving.

3.7.2 Geotechnical Engineer

Hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The

Geotechnical Engineer is responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions.

The Geotechnical Engineer is responsible for updating the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and submit an updated plan if necessary. Submit a monthly written report, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Contracting

Officer is responsible for arranging meetings with the Geotechnical

Engineer at any time throughout the contract duration.

3.8 GRADING AREAS

Where indicated, divide work into grading areas within which satisfactory excavated material will be placed in embankments, fills, and required backfills. Do not haul satisfactory material excavated in one grading area to another grading area except when so directed in writing. Place and grade stockpiles of satisfactory and unsatisfactory materials as specified. Keep stockpiles in a neat and well drained condition, giving due consideration to drainage at all times. Clear, grub, and seal by rubber-tired equipment, the ground surface at stockpile locations;

separately stockpile excavated satisfactory and unsatisfactory materials.

Protect stockpiles of satisfactory materials from contamination which may destroy the quality and fitness of the stockpiled material. If the

Contractor fails to protect the stockpiles, and any material becomes unsatisfactory, remove and replace such material with satisfactory material from approved sources.

3.9 FINAL GRADE OF SURFACES TO SUPPORT CONCRETE

Do not excavate to final grade until just before concrete is to be placed. For pile foundations, stop the excavation at an elevation of from

SECTION 31 00 00 Page 20

6 to 12 inches above the bottom of the footing before driving piles. After pile driving has been completed, complete the remainder of the excavation to the elevations shown. Roughen the level surfaces, and cut the sloped surfaces, as indicated, into rough steps or benches to provide a satisfactory bond. Protect and all surfaces from erosion resulting from ponding or water flow.

3.10 GROUND SURFACE PREPARATION

3.10.1 General Requirements

Remove and replace unsatisfactory material with satisfactory materials, as directed by the Contracting Officer, in surfaces to receive fill or in excavated areas. Scarify the surface to a depth of 6 inches before the fill is started. Plow, step, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so that the fill material will bond with the existing material. When subgrades are less than the specified density, break up the ground surface to a minimum depth of 6 inches, pulverizing, and compacting to the specified density. When the subgrade is part fill and part excavation or natural ground, scarify the excavated or natural ground portion to a depth of 12 inches and compact it as specified for the adjacent fill.

3.10.2 Frozen Material

Do not place material on surfaces that are muddy, frozen, or contain frost. Finish compaction by sheepsfoot rollers, pneumatic-tired rollers, steel-wheeled rollers, or other approved equipment well suited to the soil being compacted. Moisten material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used.

3.11 UTILIZATION OF EXCAVATED MATERIALS

Dispose unsatisfactory materials removing from excavations into designated waste disposal or spoil areas. Use satisfactory material removed from excavations, insofar as practicable, in the construction of fills, embankments, subgrades, shoulders, bedding (as backfill), and for similar purposes. Submit procedure and location for disposal of unused satisfactory material. Submit proposed source of borrow material. Do not waste any satisfactory excavated material without specific written authorization. Dispose of satisfactory material, authorized to be wasted, in designated areas approved for surplus material storage or designated waste areas as directed. Clear and grub newly designated waste areas on

Government-controlled land…