This document appears to be a contract amendment related to a federal contract opportunity for the Troy Lock - Stoplog Dam Concrete Recesses and Steel Lock Filter project. The key details are:
The modifications include revisions to the Schedule of Prices, Section 01 11 00 Summary of Work, Section 01 20 00 Price and Payment Procedures, Attachment A to Section 01 33 00, and Section 01 53 11 Protection, Dewatering, and Debris Removal. The work includes, but is not limited to, placing and dewatering cofferdams, demolition, concrete work, underwater concrete, fabrications, painting, surveying, stoplogs, dive inspection and video inspection, and site restoration. The work location is the Hudson River in Troy, Rensselaer County, New York. The solicitation number is W912DS24B0006. Option A includes furnishing two cofferdams. The contract opportunity is a competitive 8(a) Invitation for Bid.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The following modifications are made to the SCHEDULE OF PRICES, SECTION 01 11 00, SECTION 01 20 00 00, ATTACHEMENT A TO SECTION 01 33 00, and
SECTION 01 53 11.
SCHEDULE OF PRICES
a. ALL PAGES. Delete the Schedule of Prices in its entirety, and substitute therefor revised Schedule of Prices, AMEND 0001 dated 03 May 2024.
SECTION 01 11 00
b. ALL PAGES. Delete Section 01 11 00 in its entirety, and substitute therefor revised Section 01 11 00, AMEND 0001 dated 03 May 2024.
SECTION 01 20 00
c. PAGES 1, 2, AND 6. Delete Section 01 20 00 Pages 1, 2, and 6, and substitute therefor revised Section 01 20 00 Pages 1, 2, and 6, AMEND 0001 dated 03 May 2024.
ATTACHEMENT A TO SECTION 01 33 00
d. ALL PAGES. Delete Attachment A to Section 01 33 00 in its entirety, and substitute therefor revised Attachment A to Section 01 33 00, AMEND 0001 dated 03 May 2024.
SECTION 01 53 11
e. ALL PAGES. Delete Section 01 53 11 in its entirety, and substitute therefor revised Section 01 53 11, AMEND 0001 dated 03 May 2024.
ATTACHMENTS: Schedule of Prices; Section 01 11 00; Section 01 20 00
Pages 1, 2, and 6; Attachment A to Section 01 33 00, and
Section 01 53 11.
SOLICITATION NO.: W912DS24B0006
E3TRYLCK202201
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.1.1 Base Bid
1.1.2 Option A
1.2 PROJECT LOCATION
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1 AMEND 0001
03 MAY 2024
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.1.1 Base Bid
The work includes, but is not limited to, placing and dewatering cofferdams, demolition, concrete work and underwater concrete, fabrications, painting, surveying, stoplogs, dive inspection and video inspection, and site restoration.
1.1.2 Option A
The work includes, but is not limited to, furnishing two cofferdams including all necessary design, submittals, fabrication, and transportation.
1.2 PROJECT LOCATION
The work is located at Hudson River, Troy, Rensselaer County, New York, and as indicated.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 11 00 Page 2 AMEND 0001
03 MAY 2024
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 JOB PAYMENT ITEMS
1.1.1 Mobilization and Demobilization
1.1.1.1 Payment
1.1.1.2 Unit of Measure
1.1.2 Survey
1.1.2.1 Payment
1.1.2.2 Unit of Measure
1.1.3 Diving
1.1.3.1 Payment
1.1.3.2 Unit of Measure
1.1.4 Cofferdam Work
1.1.4.1 Payment
1.1.4.2 Unit of Measure
1.1.5 Electrical Work
1.1.5.1 Payment
1.1.5.2 Unit of Measure
1.1.6 Recess Work
1.1.6.1 Payment
1.1.6.2 Unit of Measure
1.1.7 Protection Plate Fabrication
1.1.7.1 Payment
1.1.7.2 Unit of Measure
1.1.8 Lifting Beam Guide Block Installation
1.1.8.1 Payment
1.1.8.2 Unit of Measure
1.1.9 Stoplog Work
1.1.9.1 Payment
1.1.9.2 Unit of Measure
1.1.10 Trash Rack Work
1.1.10.1 Payment
1.1.10.2 Unit of Measure
1.1.11 Handrailing Replacement
1.1.11.1 Payment
1.1.11.2 Unit of Measure
1.1.12 Site Restoration
1.1.12.1 Payment
1.1.12.2 Unit of Measure
1.1.13 Furnish Cofferdams
1.1.13.1 Payment
1.1.13.2 Unit of Measure
1.2 UNIT PRICE PAYMENT ITEMS
1.2.1 Temporary Construction Facilities
1.2.1.1 Payment
1.2.1.2 Measurement
1.2.1.3 Unit of Measure
1.2.2 Stoplog Recess Concrete Removal
SECTION 01 20 00 Page 1 AMEND 0001
03 MAY 2024
1.2.2.1 Payment
1.2.2.2 Measurement
1.2.2.3 Unit of Measure
1.2.3 Stoplog Recess Concrete Placement
1.2.3.1 Payment
1.2.3.2 Measurement
1.2.3.3 Unit of Measure
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 20 00 Page 2 AMEND 0001
03 MAY 2024
1.1.10 Trash Rack Work
1.1.10.1 Payment
Payment for all costs associated with upstream trash racks, support beams, and embedded metals, including, but not limited to, concrete removal including embedded metals, concrete placement, fabricating trash rack grating, painting, installing support beams, and installing trash racks will be made for Item No. 0013, "Trash Rack Work."
1.1.10.2 Unit of Measure
Unit of measure: job.
1.1.11 Handrailing Replacement
1.1.11.1 Payment
Payment for all costs associated with handrailing, fabricating, packaging, delivering, and incidentals, including painting, will be made for Item No.
0014, "Handrailing Replacement."
1.1.11.2 Unit of Measure
Unit of measure: job.
1.1.12 Site Restoration
1.1.12.1 Payment
Payment for all costs associated with restoring the site and staging areas to original or better condition includes, but is not limited to, seeding and debris removal will be made for Item No. 0015, Site Restoration."
1.1.12.2 Unit of Measure
Unit of measure: job.
1.1.13 Furnish Cofferdams
1.1.13.1 Payment
Payment for all costs associated with furnishing two cofferdams, including but not limited to, design, fabrication, submittals, transport to and from site, and rental fees (if applicable) will be made for Item No. 101, Option A - Furnish Cofferdams."
1.1.13.2 Unit of Measure
Unit of measure: job.
1.2 UNIT PRICE PAYMENT ITEMS
Payment items for unit price payments will be made in the SCHEDULE OF PRICES and as specified. The unit price and payment made for each item will constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each unit price item.
SECTION 01 20 00 Page 6 AMEND 0001
03 MAY 2024
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 9 PAGES
Troy Lock, Troy, NY, Stoplog Recess and Trash Rack Replacement
00 73 05 SD-01 Preconstruction Submittals
1.6.1 G SLBackground Checks
1.6.2 G SLCompany Enrollment in E-Verify
1.6.2 G SLForm I-9
1.9 G CTInsurance
GPermits
1.12 GPre-Construction Condition
Survey
1.25 GHigh Water Action Plan
1.29 GECDLVideo Inspection Plan
SD-11 Closeout Submittals
1.12 GPost-Construction Condition
Survey
01 14 00 SD-01 Preconstruction Submittals
1.8.1 GFloating Plant Plan
1.4.1 GPre-Closure Work Plan
SD-05 Design Data
1.7.1 GECDSEquipment Placement Plan
1.7.2 GECDSLock Wall Stability Analysis
01 32 16 SD-01 Preconstruction Submittals
1.2 GConstruction Schedule
SD-07 Certificates
1.4Monthly Updates
01 35 26 SD-01 Preconstruction Submittals
1.6 G SOAccident Prevention Plan (APP)
1.7 G SOActivity Hazard Analysis (AHA)
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
AMEND 0001
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 9 PAGES
01 35 26 1.6 G SOCrystalline Silica Plan
1.6 G SOCrane Critical Lift Plan
1.4.1.4 G SOCrane Operators
1.13 GDiving Plan
SD-06 Test Reports
1.10Accident Reports
1.10Crane Reports
SD-07 Certificates
1.11 G SOHot Work Permit
1.10 G SOCertificate of Compliance
1.9First Aid and CPR
1.6 G SOBoat Operator
01 45 00 SD-01 Preconstruction Submittals
1.7.2.1 GPay Activity Data
01 45 04 SD-01 Preconstruction Submittals
3.2 GContractor Quality Control (CQC)
Plan
01 50 00 SD-02 Shop Drawings
1.3 G ECCSign Legend Orders
1.3 GConstruction Project Signs
01 50 02 SD-01 Preconstruction Submittals
1.2 GSite Plan
01 53 11 SD-01 Preconstruction Submittals
3.7 GECDLCofferdam Installation and
Dewatering Plan
2.2.2 GECDLCofferdams
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 9 PAGES
01 57 19 SD-01 Preconstruction Submittals
1.6 GECDNEnvironmental Protection Plan
3.9Hazardous Material Management
SD-06 Test Reports
1.8Solid Waste Management Report
GECDNLaboratory Analysis
SD-11 Closeout Submittals
3.8.3.4 GECDNDisposal Documentation for
Hazardous and Regulated Waste
01 78 00 SD-11 Closeout Submittals
1.2.1 GAs-Built Drawings
02 21 00 SD-01 Preconstruction Submittals
1.6 GECDLWork Plan and Schedule
3.4 GECDLPreliminary Survey
1.5 GECDLProfessional Registration
3.6 GECTSPosition Monument Survey
SD-11 Closeout Submittals
3.5 GECTSFinal Survey
02 41 00 SD-01 Preconstruction Submittals
1.7 GNotifications
1.10 GDemolition And Deconstruction
Plan
03 01 10 SD-01 Preconstruction Submittals
3.1 G ECGIRemoval Plan
3.7 GQuality Control Plan
03 01 20 SD-01 Preconstruction Submittals
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 9 PAGES
03 01 20 Part 2 GECDLEquipment
1.4 GECDLWork Plan
SD-07 Certificates
3.1 GExperience
03 11 19 SD-01 Preconstruction Submittals
1.3.1 G ECGFormwork Calculations
SD-02 Shop Drawings
1.3.2 GECDLShop Drawings
SD-03 Product Data
2.1 GECDLFormwork Materials
2.1.1 GECDSPlywood
2.2.2 GECDLConcrete Form Hardboard
2.2.1 GECDLPrefabricated Steel Forms
2.3 GECDLForm Coating
SD-06 Test Reports
G ECGConcrete Strength - Control Tests
03 15 14 SD-01 Preconstruction Submittals
1.3 G ECGIJointing Plan
SD-03 Product Data
2.2 G ECGIBacker Rod
2.3 G ECGISealants
2.1 G ECGIExpansion/Isolation Joint Filler, Premolded
03 20 01 SD-02 Shop Drawings
3.1 GECDLReinforcement
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 9 PAGES
03 20 01 2.1.1 GECDLReinforcing Steel
03 31 00 SD-01 Preconstruction Submittals
1.8 G ECGIAggregate Source
3.8.6 G ECGICold-Weather Placing
3.8.7 G ECGIHot-Weather Placing
3.2 G ECGIBatching and Mixing Equipment
3.5 G ECGIPlacing Equipment and Methods
3.7.3 G ECGIConstruction Joint Treatment
SD-02 Shop Drawings
3.8.1 G ECGIConcrete Placement Plan
SD-03 Product Data
2.1.8 G ECGINonshrink Grout for Concrete
Repairs
2.1.4 G ECGICuring and Protection Materials
SD-05 Design Data
2.1.7 G ECGIEpoxy Resin
1.6 G ECGIConcrete Mixture Proportions
1.9 G ECGIThermal Control Plan
3.11.2.1 G ECGIRandom Sampling Plan
SD-06 Test Reports
G ECGIAggregate Test Results
3.11 G ECGITests and Inspections
3.8.8 G ECGITemperature Monitoring
2.2.3 G ECGIPotential Alkali-Silica Reactivity
SD-07 Certificates
G ECGIWaybills and Delivery Tickets
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 9 PAGES
03 31 00 G ECGIConcrete Finish Qualifications
G ECGIConcrete Inspector Qualifications
3.11.1 G ECGISample and Test Concrete
05 05 20 SD-01 Preconstruction Submittals
1.4.1 GInstaller Qualifications
1.4.2 GPost-Installed Anchor Special
Inspector Qualifications
GTest Setup Sketches and
Specifications for Proof Loads
3.5 GEpoxy Anchor Quality Control
Procedure
SD-02 Shop Drawings
3.4.2 GECDLTesting Apparatus
SD-03 Product Data
2.1.5 GECDLAdhesive Anchor System in
Concrete
3.1.2 GECDLNon-Shrink, Non Metallic Grout
SD-06 Test Reports
3.4.5 GPost-Installed Anchor Special
Inspections Report
SD-07 Certificates
2.1.3 GPost-Installed Anchor
Certification
SD-08 Manufacturer’s Instructions
2.1.4 GManufacturer's Printed
Installation Instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 9 PAGES
05 05 20 1.4Manufacturer's Safety Data
Sheets
05 05 23 SD-01 Preconstruction Submittals
3.2 GECDLWelding Quality Assurance Plan
1.3 GECDLWelding Procedure Qualifications
1.3.3 GECDLWelder, Welding Operator, and
Tacker Qualification
1.3.2 GECDLPre-Qualified Procedures
SD-03 Product Data
2.2 GECDLWelding Electrodes and Rods
SD-06 Test Reports
1.3.1 GECDLPrevious Qualifications
3.3 GECDLNondestructive Testing
3.2 GECDLWeld Inspection Log
SD-07 Certificates
GECDLCertified Welding Procedure
Specifications (WPS)
GECDLCertified Procedure Qualification
Records (PQR)
GECDLCertified Welder Performance
Qualifications (WPQ)
1.3.4 GECDLCertified Welding Inspector
1.3.4 GECDLNondestructive Testing Personnel
05 50 14 SD-02 Shop Drawings
1.4.1 GECDLDetail Drawings
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 9 PAGES
05 50 14 Materials Certifications
09 97 02 SD-01 Preconstruction Submittals
1.3.1.1 GECDLPreparation and Painting
Management Program
1.3.2Equipment List
SD-04 Samples
2.1 GECDLSpecial Paint Formulas
2.3.3 GECDLSolvent and Thinners
SD-07 Certificates
1.3.1 GECDLQualified Paint Applicator
GECDLQuality Control Inspector
Qualification
GECDLShop Qualification
1.3.2 GECDLCoating Thickness Gage
Qualification
32 92 10 SD-07 Certificates
2.1 GSeed
2.1 GFertilizer
2.1 GMulch
33 71 02 SD-02 Shop Drawings
3.1 GECDGTemporary Power Plan
3.2.1 GECDGEmbedded Ducts Marking Photos
SD-03 Product Data
2.1 GECDGUninterruptible Power Supply
(UPS)
SD-06 Test Reports
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 9 PAGES
33 71 02 3.2.2.2 GECDGPreconstruction Electrical Test
Report
3.2.2.2 GECDGElectric Cable Continuity And
Megger Tests Report
3.2.2 GECDGAcceptance Checks and Tests
SD-07 Certificates
1.3.1 GTechnician Certification
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
ATTACHMENT A TO SECTION 01 33 00
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 53 11
PROTECTION, DEWATERING, AND DEBRIS REMOVAL
PART 1 GENERAL
1.1 SUBMITTALS
1.2 HISTORY OF LOCK CHAMBER DEWATERINGS
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED DEWATERING STRUCTURES
2.1.1 Lock Chamber Stoplogs
2.1.2 Cofferdams (Option A Not Awarded)
2.2 CONTRACTOR-FURNISHED DEWATERING ITEMS
2.2.1 Stair Towers
2.2.2 Cofferdams (Option A Awarded)
PART 3 EXECUTION
3.1 DEWATERING COORDINATION MEETING
3.2 STOPLOG RECESS PROTECTION PLATE ASSEMBLIES REMOVE/REINSTALL
3.3 WALKWAYS ACROSS STOPLOGS
3.4 LOCK CHAMBER MONITORING DURING DEWATERING
3.4.1 Contracting Officer Monitoring
3.4.2 Contractor Monitoring
3.5 REMOVAL OF MATERIAL FROM AREAS TO BE DEWATERED
3.6 EMERGENCY REWATERING OF LOCK CHAMBER
3.7 COFFERDAM INSTALLATION AND DEWATERING PLAN
-- End of Section Table of Contents --
SECTION 01 53 11 Page 1 AMEND 0001
03 MAY 2024
SECTION 01 53 11
PROTECTION, DEWATERING, AND DEBRIS REMOVAL
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Cofferdam Installation and Dewatering Plan; G ECDL
Cofferdams; G ECDL
Submit detailed drawings, calculations, and other pertinent data related to the design and construction of dewatering structures.
Only required if option A is awarded.
1.2 HISTORY OF LOCK CHAMBER DEWATERINGS
Troy Lock is regularly dewatered during winter for maintenance purposes.
There is no information on the requirements to dewater and maintain the lock chamber, however, the multiple previous lock dewaterings suggests that there are no seepage or scour issues present.
PART 2 PRODUCTS
2.1 GOVERNMENT FURNISHED DEWATERING STRUCTURES
2.1.1 Lock Chamber Stoplogs
Stoplogs for the downstream stoplogs recess will be Government furnished.
The downstream dewatering structure to consist of several stoplog sections, stacked on top of one another. There are 21 stoplogs which, when stacked, form the downstream stoplogs Each stop log weighs approximately 6,500 lbs and dimensions of 48.5'L x 2.75'W x 33"H. A joint inspection of the stoplog sections will be performed and documented by the Contractor and Contracting Officer to ascertain their condition prior to use by the Contractor.
Additionally, a single pickup beam for the stoplogs will be Government furnished. The pickup beam weighs approximately 3,200 lbs.
The stoplogs are stored at Troy Lock. Install and maintain the stoplogs during the first closure until downstream stoplog recesses are complete, stoplogs have been installed and inspected, and lock has been dewatered;
after which the Contractor leaves the stoplogs in place in the stoplog recess and turns over site control to the Government. The Government will perform all stoplog operations during second closure.
SECTION 01 53 11 Page 2 AMEND 0001
03 MAY 2024
2.1.2 Cofferdams (Option A Not Awarded)
Two cofferdams will be provided by the Government for Contractor use if option A is not awarded. Install and maintain cofferdams during stoplog slot replacement. A joint inspection of the cofferdams will be performed and documented by the Contractor and Contracting Officer to ascertain their condition prior to use by the Contractor. At the time of return, a second joint inspection will be performed to determine the returned condition. Reinstall bottom plate on second cofferdam after use and before the second joint inspection. Any damage incurred due to Contractor operations will be required at the Contractor's expense. The cofferdams are not designed to handle ice loading. Provide bubblers or other means to prevent ice buildup on cofferdams.
2.2 CONTRACTOR-FURNISHED DEWATERING ITEMS
2.2.1 Stair Towers
Provide stair towers in accordance with USACE EM 385-1-1. Include description and quantity of stair towers in the Confined Space Entry Plan in accordance with Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS.
Stair towers are required for second dewatering only.
2.2.2 Cofferdams (Option A Awarded)
If option A is awarded, then furnish two (2) cofferdams in accordance with USACE technical manuals, safety manuals, and applicable design codes such as AISC and AWS D1.1/D1.1M . Submit the plan and detailed design of the dewatering structures, including possible walkways and handrails, as applicable, for approval a minimum of 45 days prior to start of construction of items. Perform proposed dewatering structure designs by a licensed Professional Structural Engineer with experience in designing dewatering structures and indicate on the submitted design with the Structural Engineer's signed stamp. The cofferdam design must consider the following minimum requirements:
a. Design for water when the top of the structure is in a dewatered state, to provide the maximum hydraulic force on the structure.
Cofferdam height extensions are prohibited unless specifically included in the design.
b. Include a 5 kip per lineal foot ice load acting in a location to provide maximum stress.
c. Include impact loads from falling debris and external forces such as floating debris.
d. Include consideration for uplift forces on the cofferdam.
e. Include considerations for securing the cofferdam to the existing structure, noting the existing concrete at the site was not air-entrained and constructed over 75 years ago, and condition of the concrete is unknown and may include cracking, spalling, and other forms of deterioration.
f. Include considerations for sealing of cofferdam on surfaces that are cracked, spalled, or have other forms of deterioration.
Design dewatering structures to fit the areas for work performed in the
SECTION 01 53 11 Page 3 AMEND 0001
03 MAY 2024
dry.
PART 3 EXECUTION
3.1 DEWATERING COORDINATION MEETING
Hold a preliminary meeting with Contracting Officer personnel directly involved with the dewatering effort approximately seven calendar days in advance of beginning dewatering operations at the site, for coordination with the Contractor on schedule, sequence, fleet management, and other issues directly related to the dewatering of the lock chamber.
3.2 STOPLOG RECESS PROTECTION PLATE ASSEMBLIES REMOVE/REINSTALL
There are wooden and steel protection plate assemblies within each of the two stoplog recesses which require removal to accommodate placement of stoplogs in the recesses.
3.3 WALKWAYS ACROSS STOPLOGS
If necessary, provide walkway across the downstream stoplogs to allow personnel access from the land wall to the river wall. Walkways used for personnel access only, and equipment or materials are not allowed across the walkways. Design walkways in accordance with USACE EM 385-1-1. The walkways may not be attached to the stoplogs by permanent methods (i.e., drilling holes thru stoplogs or welding to stoplogs). Design the downstream stoplog walkway for quick removal in case of necessity for emergency rewatering. Inspect walkways throughout use, and maintain or repair walkways in accordance as specified, indicated, and by EM 385-1-1.
3.4 LOCK CHAMBER MONITORING DURING DEWATERING
3.4.1 Contracting Officer Monitoring
During lock drawdown for dewatering, Contracting Officer will monitor the floor of the lock for boils or unusual wall movement. If floor slab heaving or any structural distress due to uplift pressures are detected, the Contracting Officer will immediately work with the Contractor to evacuate the chamber and the Government will rewater the lock chamber.
During the dewatering, the Contracting Officer will be monitoring the observation wells installed on an hourly basis during the lock dewatering drawdown, and then daily thereafter for the entire dewatering period.
Maintain access to the observation wells, as well as a 5-foot x 5-foot area around the well for Contracting Officer use. The Contracting Officer may place physical continuous monitoring devices during the dewatering at the observation wells which will take up the entire 5-foot x 5-foot area.
Plan construction activities to avoid disturbance or damage to equipment.
3.4.2 Contractor Monitoring
After completion of the dewatering, the Contractor and Contracting Officer to monitor the floor of the lock for boils or unusual wall movement. If floor slab heaving or any structural distress due to uplift pressures are detected, immediately evacuate the chamber. The Government will rapidly fill the chamber with water.
SECTION 01 53 11 Page 4 AMEND 0001
3.5 REMOVAL OF MATERIAL FROM AREAS TO BE DEWATERED
Remove all debris and materials in the lock chamber in the areas to be used for cofferdam placement and dewatering prior to underwater concrete placement. All debris and material is to be disposed off-site. Items that may be found include, but are not limited to, rocks, organic materials such as trees, silt, and man-made items such as wire rope, chain binders, recreational boating item, and any other items considered debris. If any hazardous materials, debris, or waste are encountered, work must immediately cease and the Contracting Officer notified. Refer to Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, for removal/disposal of found hazardous materials, debris, or waste.
Remove zebra mussels from all equipment, existing structures, and dewatered floor areas prior to re-entry of water. Properly dispose to a landfill area in a manner that will not allow the mussels to re-enter the water.
3.6 EMERGENCY REWATERING OF LOCK CHAMBER
In the event of structural instability of the lock chamber during dewatering, or other conditions where the integrity of the structure is in jeopardy, the Government will rapidly fill chamber to alleviate the distress by removing the downstream lock chamber bulkheads. Remove all equipment and materials, including any walkway structures located on the bulkheads, within 30 minutes of notice by the Contracting Officer.
SECTION 01 53 11 Page 5 AMEND 0001
3.7 COFFERDAM INSTALLATION AND DEWATERING PLAN
Submit a comprehensive plan detailing the work items to be completed, the proposed time for accomplishing work, the method proposed to install the dewatering structures with approved anchors, the method proposed to dewater the areas in which work is to be performed in the dry, the method proposed to seal leakage around or through the dewatering structures, through cracks/joints in the concrete which may leak and where existing structures have concrete spalling in the areas of the cofferdam seals, and the method to keep ice away from the cofferdams. Submit the dewatering plan a minimum 45 days prior to the closure period. Submit the seals that will be used on the cofferdams. Modifications of the cofferdams is prohibited if Government supplied.
a. In addition to installing the cofferdams, provide, operate, and maintain all pumps and other equipment necessary to maintain the cofferdams, in the dry, in dewatered condition.
b. Submit dewatering layouts plans as part of the cofferdam dewatering plan and revised in accordance with site conditions. Dewatering designs and the capacity of equipment in accordance with sound engineering practice. Hydraulically driven pumps are prohibited for dewatering.
c. Contractor will be present at all times during cofferdam dewatering and rewatering of the areas in which work is to be performed in the dry. During the time the work areas are dewatered and when a Contractor representative is not on the job site during Contractor working hours, the Contractor will ensure that a Contractor representative can be contacted via telephone at all times by Contracting Officer personnel. If requested by the Contracting Officer, the Contractor representative will be able to be present on the project site within 1/2 hour after the request is made.
d. During and after completion of cofferdam dewatering, monitor the dewatering structures for instability or unusual movement on a daily basis, prior to entering the cofferdam. Monitoring consists of, but not limited to, visually inspecting the cofferdam for changes in leakage amounts, movement of the structure, and impact damage. The Contracting Officer will provide oversight on the Contractor's evaluation and monitor the dewatering structure with emphasis on worker protection and dam structure integrity. If any structural distress is detected, the dewatering structure will be immediately evacuated and the Contractor to immediately notify the Contracting Officer.
e. Address provisions to control leakage around the cofferdam and through joints in the existing concrete structure.
-- End of Section --