This document contains an abstract of bids received in response to Solicitation Number W912DS-20-B-0004 issued by the U.S. Army Corps of Engineers, New York District. The solicitation sought bids for the construction of fourteen new stone groin structures and five groin rehabilitations along the Atlantic shorefront in Rockaway, New York as part of the Rockaway Beach Erosion Control Features project. Eight offers were received by the April 14, 2020 deadline ranging in total price from $114.3 million to $226.4 million. The scope of work involves placing approximately 265,000 tons of 10-ton rock armor, 75,000 tons of 5-ton armor, and 22,000 tons of core and bedding stone to construct the new and rehabilitated groins. Additional requirements include 30,000 cubic yards of rock excavation, 350,000 cubic yards of sand excavation, and removal of two timber groins approximately 300 feet in length each. The contractor must commence work within five calendar days of receiving notice to proceed and complete all work within 1,460 calendar days.

View the file

Other files

File Type Posted
W912DS-20-B-0004 Amendment 0007.pdf PDF
W912DS-20-B-0004-Amendment-0006.pdf PDF
W912DS-20-B-0004 Amendment 0005.pdf PDF
W912DS-20-B-0004 Amendment 0004.pdf PDF
RKWY_C-101.pdf PDF
S-300-00-SandRetainingWallPlansS.PDF PDF
Rockaway Make Safe -Baffle Wall 2013-01-14.pdf PDF
RKWY_C-102.pdf PDF
W912DS-20-B-0004 Amendment 0003.pdf PDF
01 45 00.00 10.pdf PDF
01 14 00.pdf PDF
01 30 00.pdf PDF
00 90 02.pdf PDF
35 31 29.40.pdf PDF
RKWY_G_G-001.pdf PDF
W912DS20B0004-0002.pdf PDF
4674-MAP-35FT-SORTED-MED-ELEVATIONxyz.txt TXT text file
4697-149th groin.pdf PDF
4717-40FT-SORTED-LiDAR-HYDRO-ELEV.txt TXT text file
4697-35FT-MAP-MED-LAND-HYDRO-ELEV.txt TXT text file
4674 SHT2 GROIN PROFILES.pdf PDF
4674 SHT1 GROIN PROFILES.pdf PDF
4674 SHT3 GROIN PROFILES.pdf PDF
RKWY_G-101.pdf PDF
W912DS20B0004-Amendment0001.pdf PDF
RKWY_C-501.pdf PDF
01 57 19.pdf PDF
RKWY_G-003.pdf PDF
W912DS20B0004.pdf PDF
Rockaway Groin Contract_Specification_02-19-2020.pdf PDF
Rockaway Groins Plan Set 02142020.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

ABSTRACT OF OFFERS - CONSTRUCTION1. SOLICITATION NUMBER:
W912DS-20-B-00042. DATE ISSUED:
21-FEB-20203. DATE OPENED:

14-APR-2020

4. ISSUING OFFICE:

U.S. Army Corps of Engineering, NY District 26 Federal Plaza, Room 16-300 New York N.Y. 10278-0090 I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. NAME AND TITLE OF CERTIFYING OFFICIAL:

Nicole Fauntleroy

Signature:
Nicole Fauntleroy
5. PROJECT TITLE:

Coastal Storm Risk Management, East Rockaway Inlet to Rockaway Inlet and Jamaica Bay, Atltantic Shore Front Groins Project, Rockaway, NY

Date Signed:
14-Apr-20
6. NUMBER OF AMENDMENTS ISSUED:
Eight (8)GOVERNMENT ESTIMATEOFFEROR #1OFFEROR #2OFFEROR #3OFFEROR #4OFFEROR #5OFFEROR #6OFFEROR #7OFFEROR #8
Weeks Marine IncH&L ContractingCashman DredgingGrace IndustriesContinental Heavy Civil CorpKiewit Infrastructure CoJT ClearyMichels Corporation
ITEM NO.DESCRIPTION OF OFFERED ITEMUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated AmountUnit PriceEstimated Amount
0001Mobilization & Demobilization$ 6,663,900.00$ 20,849,000.00$ 12,452,520.00$ 27,000,000.00$ 19,550,000.00$ 11,600,000.00$ 28,500,000.00$ 2,000,000.00$ 16,257,212.39
0002AAW GROIN FIELD – GROIN REHABILITATION$ 2,187,200.00$ 915,000.00$ 450,000.00$ 750,000.00$ 1,050,000.00$ 825,000.00$ 1,080,000.00$ 1,800,000.00$ 1,145,850.00
0002ABW GROIN FIELD – GROIN REHABILITATION$ 301,700.00$ 139,000.00$ 58,480.00$ 20,000.00$ 150,000.00$ 58,000.00$ 80,000.00$ 50,000.00$ 99,480.00
0002ACW GROIN FIELD – GROIN REHABILITATION$ 2,870,400.00$ 2,182,656.00$ 2,082,432.00$ 3,340,800.00$ 2,449,920.00$ 2,032,320.00$ 2,449,920.00$ 4,454,400.00$ 2,355,932.16
0002ADW GROIN FIELD – GROIN REHABILITATION$ 1,073,300.00$ 886,496.00$ 716,016.00$ 1,278,600.00$ 895,020.00$ 720,278.00$ 639,300.00$ 1,321,220.00$ 883,384.74
0002AEW GROIN FIELD – GROIN REHABILITATION$ 829,500.00$ 508,005.00$ 415,350.00$ 958,500.00$ 549,540.00$ 469,665.00$ 431,325.00$ 1,278,000.00$ 521,264.25
0002AFW GROIN FIELD – GROIN REHABILITATION$ 1,230,700.00$ 737,352.00$ 630,630.00$ 1,455,300.00$ 805,266.00$ 664,587.00$ 853,776.00$ 970,200.00$ 723,284.10
0002AGW GROIN FIELD – GROIN REHABILITATION$ 143,100.00$ 452,556.00$ 208,872.00$ 870,300.00$ 556,992.00$ 530,883.00$ 1,392,480.00$ 522,180.00$ 212,179.14
0003AAW GROIN FIELD – 12 NEW GROINS$ 41,250,600.00$ 31,206,630.00$ 29,926,358.00$ 48,010,200.00$ 36,007,650.00$ 29,206,205.00$ 35,207,480.00$ 44,009,350.00$ 33,543,126.40
0003ABW GROIN FIELD – 12 NEW GROINS$ 12,880,400.00$ 10,638,784.00$ 8,592,864.00$ 15,344,400.00$ 10,945,672.00$ 8,644,012.00$ 7,672,200.00$ 17,901,800.00$ 10,601,445.96
0003ACW GROIN FIELD – 12 NEW GROINS$ 11,384,600.00$ 6,972,150.00$ 5,700,500.00$ 13,155,000.00$ 7,586,050.00$ 6,445,950.00$ 5,919,750.00$ 14,470,500.00$ 7,154,127.50
0002ADW GROIN FIELD – 12 NEW GROINS$ 16,878,100.00$ 10,112,560.00$ 8,648,900.00$ 19,959,000.00$ 11,043,980.00$ 9,114,610.00$ 11,709,280.00$ 13,306,000.00$ 9,919,623.00
0003AEW GROIN FIELD – 12 NEW GROINS$ 2,395,900.00$ 5,253,500.00$ 2,488,500.00$ 13,825,000.00$ 11,060,000.00$ 2,806,475.00$ 9,401,000.00$ 8,295,000.00$ 2,408,315.00
0003AGW GROIN FIELD – 12 NEW GROINS$ 145,900.00$ 34,000.00$ 60,000.00$ 400,000.00$ 340,000.00$ 272,500.00$ 1,000,000.00$ 500,000.00$ 129,029.34
0004AAE GROIN FIELD – 4 GROIN REHABILITATION$ 13,998,100.00$ 5,664,000.00$ 2,880,000.00$ 4,800,000.00$ 6,720,000.00$ 5,280,000.00$ 6,912,000.00$ 11,520,000.00$ 5,759,040.00
0004ABE GROIN FIELD – 4 GROIN REHABILITATION$ 3,016,700.00$ 1,360,000.00$ 630,000.00$ 200,000.00$ 1,500,000.00$ 580,000.00$ 800,000.00$ 500,000.00$ 994,800.00
0004ACE GROIN FIELD – 4 GROIN REHABILITATION$ 20,649,800.00$ 15,782,064.00$ 15,141,168.00$ 24,033,600.00$ 17,624,640.00$ 14,620,440.00$ 17,624,640.00$ 16,022,400.00$ 16,791,475.20
0004ADE GROIN FIELD – 4 GROIN REHABILITATION$ 4,293,400.00$ 3,580,290.00$ 2,864,232.00$ 5,114,700.00$ 3,580,290.00$ 2,881,281.00$ 2,557,350.00$ 5,114,700.00$ 3,533,746.23
0004AEE GROIN FIELD – 4 GROIN REHABILITATION$ 4,780,700.00$ 2,983,068.00$ 2,393,820.00$ 5,524,200.00$ 3,167,208.00$ 2,706,858.00$ 2,485,890.00$ 2,762,100.00$ 3,004,244.10
0004AFE GROIN FIELD – 4 GROIN REHABILITATION$ 6,867,700.00$ 4,168,934.00$ 3,519,230.00$ 8,121,300.00$ 4,493,786.00$ 3,708,727.00$ 4,764,496.00$ 5,414,200.00$ 4,036,286.10
0004AGE GROIN FIELD – 4 GROIN REHABILITATION$ 608,300.00$ 1,702,000.00$ 666,000.00$ 3,700,000.00$ 2,220,000.00$ 2,257,000.00$ 4,810,000.00$ 2,220,000.00$ 1,013,060.00
0005AAE GROIN FIELD – 2 NEW GROINS$ 10,050,100.00$ 7,720,020.00$ 7,291,130.00$ 11,697,000.00$ 8,772,750.00$ 7,115,675.00$ 8,577,800.00$ 7,798,000.00$ 8,172,304.00
0005ABE GROIN FIELD – 2 NEW GROINS$ 2,146,800.00$ 1,790,250.00$ 1,432,200.00$ 2,557,500.00$ 1,824,350.00$ 1,440,725.00$ 1,278,750.00$ 2,131,250.00$ 1,766,976.75
0005ACE GROIN FIELD – 2 NEW GROINS$ 2,323,400.00$ 1,440,789.00$ 1,163,370.00$ 2,684,700.00$ 1,548,177.00$ 1,315,503.00$ 1,208,115.00$ 1,342,350.00$ 1,460,029.35
0005ADE GROIN FIELD – 2 NEW GROINS$ 3,349,700.00$ 2,033,416.00$ 1,716,520.00$ 3,961,200.00$ 2,191,864.00$ 1,808,948.00$ 2,323,904.00$ 2,640,800.00$ 1,968,716.40
0005AEE GROIN FIELD – 2 NEW GROINS$ 795,900.00$ 1,104,300.00$ 552,150.00$ 3,067,500.00$ 2,454,000.00$ 644,175.00$ 2,085,900.00$ 1,840,500.00$ 539,880.00
0006Vibration Monitoring$ 45,000.00$ 400,000.00$ 966,100.00$ 500,000.00$ 125,000.00$ 732,550.00$ 1,000,000.00$ 500,000.00$ 708,936.43
0007As Build Record Drawing$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00$ 100,000.00
0008Additional Insurance$ 2,550,000.00$ 1,500.00$ 5,000.00$ 200,000.00$ 50,000.00$ 20,000.00$ 1.00$ - 0$ 57,781.31
0009Additional Timber Groin Removal(TG1 -TG4)$ 707,700.00$ 48,000.00$ 120,000.00$ 800,000.00$ 680,000.00$ 696,000.00$ 1,200,000.00$ 200,000.00$ 253,787.56
0010Additional Timber Groin Removal(TG5 -TG7)$ 530,800.00$ 36,000.00$ 90,000.00$ 600,000.00$ 510,000.00$ 522,000.00$ 900,000.00$ 105,000.00$ 190,761.96
0011Additional Timber Groin Removal(TG8 -TG11)$ 707,700.00$ 48,000.00$ 120,000.00$ 800,000.00$ 680,000.00$ 696,000.00$ 1,200,000.00$ 200,000.00$ 253,787.56
0012Additional Timber Groin Removal(TG12-TG16)$ 884,700.00$ 60,000.00$ 150,000.00$ 1,000,000.00$ 850,000.00$ 870,000.00$ 1,500,000.00$ 250,000.00$ 316,813.05
0013Additional Timber Groin Removal(TG17-TG19)$ 530,800.00$ 36,000.00$ 90,000.00$ 600,000.00$ 510,000.00$ 522,000.00$ 900,000.00$ 105,000.00$ 190,761.96
TOTAL BASE CLINS 0001-0007$ 173,260,900.00$ 140,716,820.00$ 113,747,342.00$ 222,428,800.00$ 159,312,155.00$ 118,582,367.00$ 162,865,356.00$ 170,784,950.00$ 135,803,748.54
TOTAL OPTIONAL CLINS 0008-0013$ 5,911,700.00$ 229,500.00$ 575,000.00$ 4,000,000.00$ 3,280,000.00$ 3,326,000.00$ 5,700,001.00$ 860,000.00$ 1,263,693.40
TOTAL BASE &OPTIONAL CLINS 0001-0013$ 179,172,600.00$ 140,946,320.00$ 114,322,342.00$ 226,428,800.00$ 162,592,155.00$ 121,908,367.00$ 168,565,357.00$ 171,644,950.00$ 137,067,441.94