This solicitation is for a construction contract to build fourteen new stone groins and rehabilitate five existing groins along the Atlantic Coast of New York City. The project aims to reduce coastal storm risk and erosion. Key details include:

  • The U.S. Army Corps of Engineers, New York District is the contracting agency.

  • The work includes constructing twelve new groins from B. 145th Street to B. 92nd Street, two new groins at B. 52nd Street and B. 32nd Street, and rehabilitating four groins between B. 45th Street and B. 36th Street.

  • The groins will use various sizes of stone for armor, core and bedding layers. Approximately 265,000 tons of 10-ton rock armor, 75,000 tons of 5-ton armor, and 22,000 tons of core/bedding stone will be placed.

  • The completion period is 1460 calendar days from NTP at an estimated cost of $100-250 million.

  • Interested parties can download plans and specifications from SAM.gov. The solicitation requires registration with SAM and use of CPARS for past performance evaluations.

View the file

Other files

File Type Posted
W912DS20B0004 Bid Abstract.xlsx XLSX spreadsheet
W912DS-20-B-0004 Amendment 0007.pdf PDF
W912DS-20-B-0004-Amendment-0006.pdf PDF
W912DS-20-B-0004 Amendment 0005.pdf PDF
W912DS-20-B-0004 Amendment 0004.pdf PDF
RKWY_C-101.pdf PDF
S-300-00-SandRetainingWallPlansS.PDF PDF
Rockaway Make Safe -Baffle Wall 2013-01-14.pdf PDF
RKWY_C-102.pdf PDF
W912DS-20-B-0004 Amendment 0003.pdf PDF
01 45 00.00 10.pdf PDF
01 30 00.pdf PDF
00 90 02.pdf PDF
35 31 29.40.pdf PDF
RKWY_G_G-001.pdf PDF
W912DS20B0004-0002.pdf PDF
4674-MAP-35FT-SORTED-MED-ELEVATIONxyz.txt TXT text file
4697-149th groin.pdf PDF
4717-40FT-SORTED-LiDAR-HYDRO-ELEV.txt TXT text file
4697-35FT-MAP-MED-LAND-HYDRO-ELEV.txt TXT text file
4674 SHT2 GROIN PROFILES.pdf PDF
4674 SHT1 GROIN PROFILES.pdf PDF
4674 SHT3 GROIN PROFILES.pdf PDF
RKWY_G-101.pdf PDF
W912DS20B0004-Amendment0001.pdf PDF
RKWY_C-501.pdf PDF
01 57 19.pdf PDF
RKWY_G-003.pdf PDF
W912DS20B0004.pdf PDF
Rockaway Groin Contract_Specification_02-19-2020.pdf PDF
Rockaway Groins Plan Set 02142020.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

East Rockawy Inlet to Rockawy Inlet-Groin ROCKAWYJAMBAYGRO Amendment 002

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G,RO

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity RegulationsEnsure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours must consist of an 8 1/2 hour period established by the Contracting Officer, between 6 a.m. and 6 p.m., Monday through Friday, excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

SECTION 01 14 00 Page 1

East Rockawy Inlet to Rockawy Inlet-Groin ROCKAWYJAMBAYGRO Amendment 002

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.4 Environmental Restrictions

Comply with environmental requirements to protect bird species, red knot and seabeach amaranth. There is to be no construction activities between Beach 6th St and Beach 85th St during March 21st to September 1st.

See Section 01 57 19 TEMPORARY ENVIROINMENTAL CONTROL Paragraph 3.5 Biological Resources for more information.

1.3 SPECIAL SCHEDULING REQUIREMENTS

1.3.1 Order of Work

Groins will be constructed West to East to the maximum extent possible.

Work may be year round on groins B149 and W1 - W8 that are located between streets B149th and B109th. There shall be no work between Memorial Day and Labor Day, unless coordinated with the NYC Parks and COR, on groins W9 - W12 that are located between streets B105th and B90th. Refer to environmental restrictions paragraph for no work timeframes in the east groin field that also apply to vehicular access on B9th Street.

Groins will be constructed West to East to the maximum extent possible.

Work may be year round on groins B149 and W1 - W8 that are located between streets B149th and B109th. There shall be no work/access restriction between Memorial Day and Labor Day, unless coordinated with the City of New York and COR, on groins W9 - W12 that are located between streets B105th and B90th. Refer to environmental restrictions paragraph for no work/access restriction timeframes in the east groin field that also apply to vehicular access on B9th Street.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 14 00 Page 2