FY15 REPAIR FACILITY DEFICIENCIES TO CURRENT CODES
& STANDARDS, BUILDING 110
WATERVLIET ARSENAL, NEW YORK
W912DS-14-D-0002-0016
TECHNICAL SPECIFICATION
July 31, 2019
Prepared For:
United States Army Corps of Engineers New York District and
Watervliet Arsenal, NY
Prepared by:
QPK Design LLP in association with
Crawford Consulting Engineers GHD Engineers
TOC - 1
TABLE OF CONTENTS
BUILDING 110 WATERVLIET
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 PROJECT IDENTIFICATION
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
--- INFORMATION FOR CONTRACTORS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
02 84 16 HANDLING OF LIGHTING BALLASTS & LAMPS CONTAINING PCBs & MERCURY
DIVISION 03 - CONCRETE
03 30 53 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 04 - MASONRY
04 01 20.70 UNIT MASONRY CLEANING AND RESTORATION
04 20 00 UNIT MASONRY
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC TILING
09 51 00 ACOUSTICAL CEILINGS
09 84 20 ACOUSTICAL CURTAIN PANELS
09 90 00 PAINTS AND COATINGS
TOC - 2
DIVISION 10 - SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 28 13 TOILET ACCESSORIES
10 51 13 METAL LOCKERS
DIVISION 21 -FIRE SUPPRESSION
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
21 13 18.00 10 PREACTION SPRINKLER SYSTEMS, FIRE PROTECTION
21 30 00 FIRE PUMPS
DIVISION 22 -PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 -HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 COMMON PIPING FOR HVAC
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 09 23.13 20 BACnet DIRECT DIGITAL CONTROL SYSTEMS FOR HVAC
23 09 93 SEQUENCES OF OPERATION FOR HVAC CONTROL
23 22 13.35 40 STEAM TRAPS
23 22 26.00 20 STEAM SYSTEM AND TERMINAL UNITS
23 31 13.00 40 METAL DUCTS
23 34 23.00 40 HVAC POWER VENTILATORS
23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLS
23 81 00.00.10 UNITERY AIR CONDITIONING EQUIPMENT
23 82 00.00 20 TERMINAL HEATING UNITS
23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT
DIVISION 26 -ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.10 10 INSULATED WIRE AND CABLE
26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES
26 09 23.00 40 LIGHTING CONTROL DEVICES
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 24 16.00 40 PANELBOARDS
26 51 00 INTERIOR LIGHTING
26 52 00.00 40 EMERGENCY LIGHTING
26 53 00.00 40 EXIT SIGNS
26 56 00 EXTERIOR LIGHTING
DIVISION 28 – FIRE PROTECTION
28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE
DIVISION 31 – EARTH MOVING
31 00 00 EARTHWORK
DIVISION 32 – SITE IMPROVEMENTS
32 12 17 HOT-MIX BITUMINOUS PAVEMENT
32 31 13 CHAIN LINK FENCES AND GATES
DIVISION 33 – SITE IMPROVEMENTS
33 11 00 WATER UTILITY DISTRIBUTION PIPING
END OF TOC
Building 110 Watervliet 216234
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01
33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with
Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan; G, AE
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes installation of a fire suppression system, replacement of doors, windows, and lighting, interior painting, and upgrades to existing bathroom facility fixtures and finishes. Incidental related work includes, but is not limited to new water entrances, pump room enclosures, alarm system integration, exterior masonry repairs, electrical wiring, and minor exterior painting.
1.2.2 Location
The work is located at the Watervliet Arsenal, Watervliet NY, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 FAR 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor shall be required to (i) commence Work under this
Contract within five (5) calendar days after the date the Contractor receives the Notice to Proceed, (ii) prosecute the Work diligently, and
(iii) complete the entire Work ready for use, not later than 365 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises. (FAR 52.212-3) e3enmjpt Highlight
Section 01 11 00 Page 2
b. Location: The Site of Work is located at Watervliet Arsenal, Watervliet, New York. The Site of the Work is on a military reservation and all rules and regulations issued by the Commanding
Officer covering general safety, security, and sanitary requirements, etc., shall be observed by the Contractor.
c. The Contractor shall furnish all labor, materials, equipment, and services for the following work: Design and construction for infrastructure upgrades as described in the solicitation package.
d. All Work shall be in accordance with the Drawings and Specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.
1.5 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation and comply with installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar
(GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
Section 01 11 00 Page 3
1.6.2 Dig Permit
Notify and obtain a dig permit from the Watervliet Arsenal Directorate of
Public Works.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
1.1 SUBMITTALS
used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. The B110 will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
The Contractor shall assume the scope of work between column bays 23 and 69 will be performed during second shift.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.
Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
Section 01 14 00 Page 2
1.3.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed.
a. The Government performs background screening and credentialing.
Throughout the year the Contractor employee must continue to meet background screening standards.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 9 hour period established by the
Contractor Officer, between 7 a.m. and 4 p.m., Monday through Friday, excluding Government holidays. Second shift will consist of a 9-hour period following first shift.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the
Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Occupied Building
The Contractor shall be working in an existing building which is occupied.
The existing buildings and their contents must be kept secure at all times.
Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material and equipment located in the building during the construction period. Protective covers or enclosures must be removed to allow Government use during first shift activities unless coordinated in advance with the COR.
Relocate movable furniture as required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.
Section 01 14 00 Page 3
The Government may remove and relocate other Government mobile property in the areas of the building scheduled to receive work at the Governments discretion.
1.3.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
Not Used
Appendix A
INFO FOR CONTRACTORS - WORK RESTRICTIONS
This Information is intended to provide general guidelines and instructions to contractors who will be providing various services on the Watervliet
Arsenal Installation. These guidelines include general as well as specific information dealing with Security, Fire, Facilities, Environmental, Industrial Hygiene and Safety issues. These should not be considered as all-inclusive but as a guide as to what is expected when performing work at the arsenal. Questions should be directed to the Contracting Officer, the
Contracting Officer's Representative (COR), or the WVA Project Manager.
1. The Watervliet Arsenal personnel from Safety, Industrial Hygiene, Security, Fire Department, and Facilities Engineering will perform periodic inspections at the work site. WATERVLIET ARSENAL RESERVES THE RIGHT TO STOP
WORK OR THE USE OF EQUIPMENT NOT IN COMPLIANCE WITH APPLICABLE LAWS,
STANDARDS, OR REGULATIONS.
2. EMERGENCIES: All emergencies must be reported. All fires must be reported regardless of size. All spills (oils, chemicals, fuels, coolants, etc.) must be reported regardless of size. Discovery of all pre-existing spills must also be reported regardless of size. First aid is available at the Arsenal Fire House 24 hours/day. Emergency phone numbers at the arsenal
(prefix 266) are:
Fire - Ext 5222 Ambulance - Ext 5333 Security - Ext 5444
Safety Office- Ext- HOTLINE (4537)/Safety Manager (5677)
Industrial Hygiene - Ext 4517/4516
To Report a Spill - Ext 5888 / dial 911 from a mobile phone (Albany County)
Section 01 14 00 Page 4
3. WORK HOURS: Visitors and Contractors will only be allowed access to
Watervliet Arsenal during normal duty hours, which are 7:00 AM through 4:00
PM, Monday through Thursday, and 7:00 AM through 3:00 PM on select Fridays
(the arsenal is closed every other Friday). Work may be performed on shutdown Fridays, after normal duty hours, Saturdays, Sundays or holidays only after the contractor has submitted their request two working days in advance through the project COR or technical point of contact for request evaluation and approval by the Contracting Officer. (Note: request approval is not guaranteed). If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday. The COR or Arsenal
Point of Contact will submit a request to the Security Office and arrange for a responsible arsenal POC to be on post at all times when the visitor is on post.
4. CONTRACTOR'S PROJECT WORK ATTENDANCE: The contractor is responsible to inform the COR and/or Project Inspector of their presence on post at all times. At the beginning and end of each workday, the Contractor is required to notify the COR and/or Project Inspector of location(s) on post where work is being performed or has been completed for the day.
5. SUB-CONTRACTORS: It is the responsibility of the Contractor to inform all their sub-contractors of all the instructions contained in this information sheet. Subcontractors are responsible to report project work attendance through the prime contractor to the COR whenever they are on post.
6. OIL AND CHEMICALS: The contractor shall furnish and utilize secondary containment measures for all storage activities. The contractor shall protect oils and chemicals from rainwater at all times. Containers shall be appropriately closed and labeled; the load shall be adequately secured during all transportation on post. The contractor shall not abandon any oil and/or chemicals on post at WVA.
7. ELEVATED THREAT LEVEL FORCE PROTECTION CONDITION (FPCON) AT WATERVLIET
ARSENAL: Impact on contractor performance during increased FPCON during periods of increased threat. During FPCONs Charlie and Delta, services may be discontinued/postponed due to higher threat. Services will resume when
FPCON level is reduced to level Bravo or lower.
8. RAMDOM ANTITERRRORISM MEASURESS PROGRAM (RAMP) AT THE WATERVLIET
ARSENAL: In accordance with AR 525-13, contractor personnel working on an installation are subject to participation in installation RAMP security program (e.g. vehicles, wearing of ID badges, etc) and installation security program.
9. BADGES: All personnel will report to the Visitors Center daily to be issued a pass. They must return the pass when they leave for the day by dropping it off in the drop box by the Visitors Center attached to the barrier to the left prior to entering the exit lane of the south gate. All personnel must show a driver's license or state identification card (picture
ID) to the security guard in order to get the pass. If the personnel will be working on the arsenal for over 90 days, they may be authorized a WVA picture badge, which will allow them access during normal work hours without getting a daily pass.
PICTURE BADGES: The contractor may request through the Contracting Officer a picture badge if the term of the contract warrants. Requests must be made
Section 01 14 00 Page 5 in writing on company letterhead to the Contracting Officer listing the following:
a. Contract Number
b. Indicate that the individual(s) work for said company
c. Project name and location of worksite (i.e. Bldg. #)
d. Duration of performance (start and stop dates)
e. All personnel being issued a picture badge shall present a passport or original birth certificate (with a raised seal) and driver's license. (A social security card is not an acceptable form of identification).
f. During performance of the contract, the contractor is responsible for prompt return of badges for any employee who no longer requires access to the work site.
g. Upon completion or termination of the contract or expiration of badge(s), the contractor shall ensure that they are returned to the issuing office.
h. Final payment on the contract will be held until all badges are properly returned.
i. Possession of a picture badge does not relieve the badge holder from the responsibility to notify the COR of project work attendance.
10. ACCESS POLICY: a. All contractor personnel entering the installation and requiring unescorted access must have a valid purpose to enter and be sponsored by a US government organization or a contractor providing support on the installation. They must have their identity proofed and vetted through the National Crime Information Center (NCIC) database, and be issued, or in possession of an authorized and valid access credential from the Watervliet Arsenal installation.
b. At the discretion of the Commander, US Army Watervliet Arsenal, any individual known to have a criminal background involving violence or meets the disqualifying standards in the Final Credentialing Standards for Issuing
Personal Identity Verification Cards under HSPD-12 (31 JUL 2008) and local command guidance, may be denied access to the Watervliet Arsenal.
Fingerprinting of employees and any other security procedures deemed necessary for the security of Watervliet Arsenal (vehicle searches or x-raying packages, bags, briefcases) may be required based on the Force
Protection Condition level at the time of access and whether the installation or building location is identified as a restricted area or
Mission Essential Vulnerable Area (MEVA).
11. NON-CITIZENS: Non-citizens of the U.S. may not be approved for access.
12. CAMERAS:
a. The Security Office and Public Affairs Officer must approve all cameras use prior to any pictures being taken, to include using a photographic-capable cell phone as a photographic device. Requests must be submitted to the WVA COR then routed to Security and then to the Public Affairs Officer.
Violations may result in the camera and film being confiscated and a citation being issued for an appearance before the U.S. Magistrate in
Albany, NY.
b. For any photos that have been approved by the Security Office and
Public Affairs Officer be advised that the photos contain military imagery that is owned by the US Government: US Army Watervliet Arsenal. It is not to be used for any purpose other than the purpose for which it is furnished nor distributed or reproduced for any purpose to persons other than the individuals specified to receive it, or their employees, without written consent of the US Army Watervliet Arsenal.
Section 01 14 00 Page 6
c. All photos must be reviewed by the security office before the photo capture system (i.e., camera, cell phone, etc) has left the arsenal.
13. TRAFFIC CONTROL: Post Speed Limit is 15 mph. Parking is allowed in valid spaces only. All valid spaces are clearly marked with white lines on both sides of the space. Vehicles parked in other than valid spaces are subject to being issued traffic citations requiring a monetary fine and/or an appearance before the U.S. Magistrate in Albany, N.Y. Motorists within the confines of WVA are subject to all New York State Vehicle and Traffic
Laws. Any moving or nonmoving violation may result in a traffic citation being issued. Loading and unloading of vehicles will be allowed only for the amount of time required to perform the function. Vehicles cannot be left unattended in other than valid parking spaces. If a patrol officer can approach a vehicle, write a traffic citation, affix that citation to the vehicle, and depart the area with no one present at the vehicle, that vehicle is considered to be unattended. Both the Fire Department and
Security Department must be notified prior to blocking of streets. The contractor must coordinate through the COR for approval to block or close streets.
14. DELIVERIES: Deliveries to contractors shall enter the post through the South Gate. Contractors expecting deliveries should notify the South
Gate (266-5821) prior to the arrival of the delivery. The contractor's representative must accept deliveries. Materials, which are delivered to the site, are the responsibility of the contractor. Storage and special conditions must be coordinated with the COR.
15. EXPLOSIVE MATERIALS: The use of explosive materials is prohibited.
16. CONTRABAND: Alcohol, illegal drugs, and any firearms are prohibited.
Violations may result in the items being confiscated and a citation being issued for an appearance before the U.S. Magistrate in Albany, NY.
17. RESTRICTION OF WVA PROVIDED DOCUMENTS: Documents provided by WVA contain proprietary information and are to be used only in support of their current authorized release. Other requests for documents must be referred to the Contracting Officer, Army Contracting Command - Warren (ACC-WRN) (WVA), 1 Buffington Street, Watervliet, NY 12189. Documents shall be destroyed to prevent disclosure and reconstruction of the contents upon completion of contracted work.
18. SECURITY OF EQUIPMENT: Contractors are responsible for securing all of their equipment. WVA is not responsible for stolen or lost items.
19. VEHICLES IN BUILDINGS: Contractors' vehicles and equipment using fuel shall receive clearance from the Fire Chief before entering the building.
Refueling of vehicles in a building requires Fire Department standby.
20. STORAGE SHED/TRAILERS/TEMPORARY OFFICES: The placement of all storage shed/trailers/temporary offices are subject to the approval of the Public
Works Division, the Watervliet Arsenal Fire department, and the Watervliet
Arsenal Security Department. The contractor shall submit their placement request in writing 10 business days in advance to the project COR or technical POC for request evaluation and approval. (Note:
request approval is not guaranteed.)
Section 01 14 00 Page 7
All temporary sheds, trailers or offices within thirty feet of any Arsenal structure must be equipped with a temporary sprinkler system as required by
NFPA 13. The Fire Inspection Staff will assist contractors in determining sprinkler requirements on site, upon request. Call extension 5990 for fire inspector assistance.
21. EQUIPMENT, DUMPSTER, STORAGE CONTAINER/SHED, TRAILER, and OFFICE
IDENTIFICATION: Contractor shall prominently display the following information on all contractor and subcontractor, owned, leased or rented motorized and wheeled equipment, dumpsters, storage containers/sheds, trailers, and offices:
a. Contractor Company Name
b. Project Number/Contract Number or Equivalent (information will be provided to contractor by the Watervliet Arsenal, the Arsenal Partnership
(AP), or the AP's Construction Manager)
c. Contractor Project Point of Contact (POC) with phone number or
Arsenal/AP Project POC with phone number (information will be provided to contractor by the Watervliet Arsenal, the AP, or the AP's Construction
Manager)
22. FLAME PERMITS: A flame permit is required daily for the use of any open flame device (blowtorches, portable furnaces, tar kettles, welding, cutting devices, etc.). Call extension 5990 for request of a flame permit to be issued; give exact location of the job site, and the name of the contractor that will use the permit.
23. FIRE EXTINGUISHERS: Whenever open flame devices are used, the contractor will provide an approved fire extinguisher. Minimum size will be a 10-pound chemical (A-B-C) powder or CO2.
24. FIRE WATCH PERSONNEL (OVERHEAD WELDING OR CUTTING): The contractor will retain a worker at floor level at all times during cutting/welding operations with proper extinguishers to assure that sparks are properly controlled. Fire Watch personnel must also be provided for hot tar kettles while in operation, with approved fire extinguisher and sandbag (dike) around tar kettle. Contractor must have a fire blanket to cover flammable material that cannot be moved.
25. GASOLINE CONTAINERS AND FLAMMABLES: Gasoline will be stored in safety containers equipped with self closing lids and other features as certified by the Underwriters' Laboratories. Flammable liquids will be kept in
National Fire Protection Association or UL approved containers; Fire
Department (extension 5990) will be called in event of a question. If gasoline or any other type fuel is kept in a portable tank it must have secondary containment or the tank be double walled and the product labeled on the side of the tank (i.e. flammable).
26. FIRE HYDRANTS: Fire hydrants shall not be used without the permission of Facilities Engineering and notification of the Fire Department (extension
5990). If permission is granted to use hydrants, the contractor will provide adapters, valves and hoses. A backflow preventer will also be required of the contractor. It is the responsibility of the contractor to insure the hydrants are shut off and have drained properly. The Fire Department must be notified when finished.
27. WATER: Backflow prevention is required for any connections to the arsenal water system throughout construction work.
Section 01 14 00 Page 8
28. DISCHARGES: Unless granted prior written approval, there shall be no discharge to the sanitary sewer, the storm sewer, the industrial sewer system, or the Industrial Waste Treatment Plant (IWTP). Except when WVA has established with the contractor a prior written agreement regarding discharge of "purge water" originating from groundwater monitoring wells and/or "decontamination water" originating from activities associated with groundwater monitoring wells, there shall be no dumping of oil or chemicals or fluids to the ground.
29. DOCUMENTATION OF DISPOSITION OF MATERIALS AND ITEMS REMOVED FROM
WATERVLIET ARSENAL: The contractor shall furnish documentation of the final disposition of all materials and items leaving Watervliet Arsenal. If an item is resold intact, indicate such action for the item and the name and address of purchaser. If oil is drained from an item, provide documentation for both the oil and the item by identifying final disposition location and management method for each (e.g., recycled, incinerated, land filled). All materials and items leaving Watervliet Arsenal shall be managed strictly in accordance with all applicable environmental regulations. The contractor shall indicate intentions for all such materials and items at the pre-construction meeting, for approval by Watervliet Arsenal.
30. WASTE DISPOSAL: All hazardous waste shall be relinquished to WVA at a location on post as designated by the COR, thereafter WVA will be responsible for management of such hazardous waste. Hazardous waste shall be relinquished to WVA in accordance with the RCRA "three day" rule. Drums of hazardous waste shall not remain outdoors overnight. Other wastes include any spent material such as garbage, packaging, residues, construction and demolition debris, excavated soils and earthen materials not designated for immediate reuse, etc., which is known by WVA and/or demonstrated by the contractor via appropriate sampling and analysis to not be hazardous waste
(such demonstration shall be to the satisfaction of WVA). The contractor is responsible for disposal of other wastes. Disposal of wastes at private sites such as sites advertising clean fill wanted, etc. is prohibited. The contractor shall comply with 6 NYCRR Part 364 for all waste hauling activities. The contractor shall furnish copies of documents for each waste shipment, such as Bills of Lading, etc. (Including "light weight" upon entering WVA, and "heavy weight" upon exiting WVA), through the COR to
Facilities Engineering. Contractor shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance Oriented Packaging Standards [POPS]) for containerizing waste. Contractor supplied dumpsters shall be covered with water proof covers to prevent precipitation from entering the dumpster.
Covers shall be secured in place whenever the contractor leaves the job site, and whenever precipitation is possible or occurring.
31. INDUSTRIAL WASTE TREATMENT: Remediation work and/or hazardous waste work shall be performed in accordance with the requirements of the Resource
Conservation and Recovery Act (RCRA) and OSHA's Hazardous Waste Operations and Emergency Response (HAZWOPER), including, but not limited to:
a. Documentation of appropriate training.
b. Submittal for approval of a Site Specific Work Plan.
c. Submittal for approval of a Health & Safety Plan.
d. Except when WVA has established with the contractor a prior written agreement whereby WVA agrees to furnish drums and/or containers, contractor
Section 01 14 00 Page 9 shall furnish and properly label new, unused, appropriate drums and/or containers (including, but not limited to, compliance with DOT's Performance
Oriented Packaging Standards (POPS) for containerizing hazardous waste.
e. Contractor shall appropriately containerize all hazardous waste, consolidating the waste to minimize the number of containers as appropriate.
Contractor shall not overload containers. Each container which has some hazardous waste shall be appropriately labeled, and shall be closed at all times except when waste is actually being added to the container ("closed" means sealed in a manner appropriate for shipment).
f. All hazardous waste generated shall be relinquished to WVA.
32. INDUSTRIAL WASTE TREATMENT PLANT (IWTP): Due to OSHA Process Safety
Management rule requirements, the contractor shall coordinate with the IWTP
Leader regarding IWTP- specific requirements when work is to be performed in and/or around the IWTP. Requirements will include:
-hazard awareness of chemicals used at the - to include sulfur dioxide
(so2).
-hazmin system- access by IWTP leader for all chemicals/msds upon request.
-proper PPE to be used when working with chemicals.
-building evacuation procedures when so2 alarm activates.
-must sign in/out of IWTP roster as acknowledgment this procedure.
33. ASBESTOS: Both OSHA Regulation 29CFR1910 and NY State Industrial
Code Rule 56, (12NYCRR56) will be followed with regard to asbestos removal.
If asbestos material is unexpectedly encountered during work, the contractor must contact the COR immediately. The contractor shall sign and submit the
"Contractor Asbestos Notification Record" prior to starting work on any facility project. All asbestos waste, except where WVA provides written authorization to do otherwise, shall be Properly containerized, labeled, manifested and disposed of by Contractor, at their expense, according to all
Local, State and Federal laws. All manifests for such waste, including weights, shall be presented to WVA Environmental staff for signature at least 24 hours prior to removal from WVA for disposal. The Generator copy of each Manifest shall be left with Environmental at the time of signing, for
WVA records. All asbestos personnel shall provide their training certificates to the safety office prior to beginning work on the job site.
Also all personnel shall have their training credentials with them at all times on the job site 34.
34. UTILITIES: Active utility services to the area of work, which are to remain, or services through the area feeding other areas, shall be rerouted, redirected or otherwise maintained. Required utility shutdowns shall be performed at such times as coordinated with Arsenal personnel and shall provide a minimum of shutdown time. Requests for shutdown shall be made at least 7 days prior to desired shutdown and be approved by the Contracting
Officer prior to Contractor's work. Arsenal personnel shall perform actual shutdown of utilities. The contractor's work schedule shall be well planned and accomplished as expeditiously as possible. Service no longer required shall be removed.
35. ENVIRONMENTAL MANAGEMENT SYSTEM (EMS) - Watervliet Arsenal (WVA) has implemented an Environmental Management System (EMS) to proactively deal the environmental impacts of its processes, activities and services. Watervliet
Arsenal uses the ISO 14001:2004 as the standard for its Environmental
Management System (EMS). All personnel performing work for or on behalf of
Watervliet Arsenal must be aware and understand Watervliet Arsenal's
Environmental Policy. The contractor, to include any subcontract that a
Section 01 14 00 Page 10 contractor uses, is responsible to ensure that all goods and services do not deviate from installation environmental policy. Watervliet Arsenal's
Environmental Policy can be viewed by going to http://www.wva.army.mil/
36. UTILITY CLEARANCE PERMIT (UCP): All contracted work is subject to the
WVA Regulation on utility clearance permits, WVAR 420-02. The contractor will assist the COR in preparing the UCP. The contractor shall review the project site, project documents and utility record plans to determine the presence of concealed utilities within the area(s) of the project work. The contractor is required to sign the UCP and concur / non-concur with the project UCP.
37. MARKING UNDER GROUND UTILITIES: All contract work, which involves the installation or unearthing of underground utilities, shall include the marking of these utilities as part of the required project work. The tape shall be detectable by a metal detector when buried up to 3 feet deep. The tape shall be of a type specifically manufactured for marking and locating underground utilities. The metallic core of the tape shall be encased in a protective jacket or provided with other means to protect it from corrosion.
Tape color shall be as specified below and shall bear a continuous printed inscription describing the specific utility.
RED: ELECTRIC
BLUE: WATER SYSTEM
GREEN: SEWER SYSTEM
YELLOW: GAS LINE OR PIPELINE (FOR NATURAL GAS, OIL, STEAM/CONDENSATE OR
OTHER DANGEROUS MATERIALS)
ORANGE: FIBER OPTIC (TELEPHONE, TELEVISION, SECURITY OR FIRE ALARM)
38. HISTORICAL ITEMS: The Contracting Officer or the COR reserves the right to declare any item or items resulting from removals, excavation, demolition, cleanup, or any other contract operation, as historically significant items. Included in this category are items of weaponry, ammunition, uniforms, equipment, relics, architectural features, archeological features or any other item that represents a part of the past history of the Arsenal. It is incumbent upon the contractor to report the finding of any item that may have historical significance. If the contractor discovers any item, which could be from the above category, all work will cease and the Contracting Officer or the COR will be contacted. These items shall remain in the property of the Arsenal and be delivered by the contractor to an area designated by the Contracting Officer or the COR.
Historical items shall be carefully removed and carefully handled to prevent damage.
39. ASBESTOS AND MERCURY FREE: All materials utilized in the contract work shall be asbestos and mercury free. An asbestos material is any material containing more than one percent by weight of asbestos.
40. LEAD-FREE/CHROMIUM-FREE PAINT: All paints applied shall be lead-free and chromium free. Lead based paint is paint that contains more than six one hundredths of one percent, 0.06%, lead in weight.
41. PCB's: To the extent that the project introduces fluids or equipment, such fluids and equipment shall not contain any polychlorinated biphenyls
(PCBs). PCB-Free is a level of contamination less than 2 PPM using EPA approved methodologies.
Section 01 14 00 Page 11
42. CONFINED SPACE ENTRY: All contracted work is subject to WVA
Regulation 385-1 Confined space entry procedure. Contractors shall provide proof of training in confined space entry procedures. Contractor shall provide the COR a completed WVA Form 385-17-E, confined space entry permit or equivalent company form prior to starting any work within a confined space. Contractors shall provide their own calibrated confined space
Monitors when entering all confined spaces. Contractors will have their own retrieval tripods and harnesses. Contractor will notify COR and Fire Dept contact prior to entering confined space each day.
43. ACCIDENT PREVENTION PLAN: Prior to commencement of contract work, the
Contractor shall submit for approval to the COR, an Accident Prevention Plan if required per Federal Acquisition Regulation construction clause 52.236-
13(f).
44. MATERIAL SAFETY DATA SHEETS (MSDS): When material safety data sheets
(MSDS's) or labels are required, failure to submit them prior to award, or when requested to do so, may result in the contractor being considered non-responsive. When providing MSDS's at any time, provide 7 copies to the
Contracting Officer. Material Safety Data Sheets for all chemicals/paints are to be made available at the work site and all containers of chemicals will be labeled for identification.
45. LASER OPERATIONS: All laser operations must be in accordance with
ANSI Z13.6.1. The Radiation Safety Officer must be notified when a laser will be used on a worksite.
46. SOUND LEVELS: Sound levels in the vicinity of equipment installed under any project shall not exceed 85 BA following construction when the equipment is in use (measured by a sound level meter set for A scale, slow response). The vicinity of installed equipment is defined as a distance not to exceed 1 meter from the equipment. Techniques such as sound level averaging or exposure time weighting shall not be used to meet this requirement. If an 85-dBA limit is beyond the state of art for the equipment, documentation verifying the minimum level achievable shall be submitted to WVA for review and acceptance at time of equipment submittals.
This documentation shall be provided and reviewed/approved prior to ordering any materials.
47. SAFETY REGULATIONS: The contractor shall comply with all provisions of U.S. Department of Labor and Occupational Safety and Health (OSHA) standards.
48. PROJECT DESIGN AND DOCUMENTATION: The Contractor shall be responsible to maintain a current copy of the project Statement of Work (SOW), or
Performance Work Statement (PWS), or Statement of Objectives (SOO), whichever is applicable to the project and appears in the Contract, at the worksite(s) available to all Contractor and Subcontractor employees for reference. The Contractor shall promote the distribution of the SOW, PWS, or
SOO to all Contractor and Subcontractor foremen, site supervisors, and employees providing construction services at the Watervliet Arsenal. Where the SOW, PWS, or SOO call out specific drawings and/or specifications for the proper performance and execution of project work, the Contractor shall also be responsible to provide copies of the drawings and specifications to the Contractor and Subcontractor employees, foremen, site supervisors, and workers.
Section 01 14 00 Page 12
49. SAFETY PRECAUTIONS: The contractor shall be responsible for instructing his workers and sub-contractors in appropriate safety measures and shall not permit them to place tools, machines and other equipment in traffic lanes or other locations in such a manner as to create safety hazards.
50. SAFETY RULES: Contractors must adhere to the following:
a. Work area will be barricaded and appropriately marked.
b. The work area will be kept clean and orderly. Waste materials are to be located so as not to create a hazard.
c. Dust and noise are to be kept to a minimum and within allowable limits
(OSHA AND ACGIH TLV's and PEL's). (To be determined by the contracting representatives with the assistance of Industrial Hygiene and Safety).
d. Existing means of egress will be adequately maintained during construction.
e. Compressed gas cylinders shall be secured in an upright position.
f. Flashback protection is required for oxygen and acetylene welding.
g. Hand and portable power tools shall be maintained and used in a safe manner.
h. Ground fault circuit interrupters are to be used with portable electric powered tools.
i. Proper protective clothing & equipment (PPE) must be provided and worn where necessary.
j. Safety glasses must be worn in designated areas in the arsenal and within any designated construction work area.
k. Hard hats must be worn when overhead work is being performed.
l. Ladders are to be free of defects and secured from movement.
m. Scaffolds or elevated work platforms are to be properly erected and adequately guarded. (Guardrails, toe boards, etc.).
n. Fall protection will be used whenever work is elevated above 6 feet.
o. Sides of all excavations in which employees are exposed to danger from moving ground shall be guarded by sloping, shoring, or other equivalent means.
p. Wheeled equipment (trailers, carts, etc.) must be free of defects and secured from movements.
q. Internal combustion engine exhausts are to be vented to the outside.
r. Bi-directional vehicles (fork trucks, dump trucks, shop carts, etc.)
will be equipped with backup alarms.
s. Vehicular traffic flow in and out of building (work site) will be such so as to not endanger safety of personnel.
t. Material Safety Data Sheets for all chemicals/paints are to be made available at the work site and all containers of chemicals will be labeled for identification.
u. Lock-out/tag-out procedures per OSHA will be used as required.
51. SULFUR DIOXIDE (SO2) AWARENESS: Due to the presence of highly hazardous chemicals located in the Industrial Waste Treatment Plant, always follow the instructions of WVA officials quickly and completely in the event of any emergency. This is especially important when working in or near the
Industrial Waste Treatment Plant (IWTP).
Because of the requirements of OSHA's Process Safety Management (PSM) standard (For specific requirements see Title 29 of the Code of Federal
Regulations, Part 1910.119 on the OSHA website) safe work practices have been developed that provide for the control of hazards during operations such as lockout/tag out; confined space entry; line breaking of process
Section 01 14 00 Page 13 associated piping; control over IWTP facility entry. These safe work practices apply to all employees and contractors equally. Contractors must follow all safe work practices while working on the installation and provide training to employees on PSM before working within the IWTP.
For contractors performing maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process, contact the Contracting Officer's Representative (COR) for more instructions on special provisions of the PSM standard that applies to this work.
52. SUBMISSION OF RECORDABLE INJURIES AND ILLNESS CASES: Watervliet
Arsenal is pursuing OSHA Voluntary Protection Program (VPP) recognition. In
VPP, management, labor, and OSHA work cooperatively and proactively to prevent fatalities, injuries, and illnesses through a system focused on:
hazard prevention and control; worksite analysis; training; and management commitment and worker involvement.
The VPP impacts all contractors whose employees cumulatively work more than
1000 hours per quarter within a calendar year at Watervliet Arsenal (herein referred to as "applicable contractors"). It is the contractor's responsibility to ensure its employees and managers are in full compliance with OSHA requirements and have a general understanding of VPP. Detailed information on VPP is available on the OSHA website at http://www.osha.gov/dcsp/vpp/index.html . All contractors, whether regularly involved in routine site operations or engaged in temporary projects such as construction or repair, must follow the safety and health rules of
Watervliet Arsenal.
Applicable contractors are required to annually submit to Watervliet
Arsenal, ATTN: TAWV-XO S/Safety Office, 1 Buffington Street, Watervliet, NY
12189-4000 or email: usarmy.watervliet.tacom.list.wate-safety@mail.mil the following documents (covering the previous calendar year quarters) by 15
January:
- Total Case Incidence Rate (TCIR) - the number of recordable injuries and illness cases per 100 full-time employees that a site has experienced in a given time frame.
- Days Away, Restricted, and/or Transfer Case Incident Rate (DART) -
Number of recordable injuries and illness cases per 100 full-time employees resulting in days away from work, restricted work activity, and/or job transfer that a site has experienced in a given time frame.
- OSHA Form 300A
Applicable contractors may submit the above immediately following the completion of a quarter, if desired.
53. RADIOACTIVE SOURCES: Contractor must comply with U.S. Army requirements for Radioactive Sources well as Nuclear Regulatory Commission and local WVA requirements Watervliet Arsenal's Radiation Safety Officer
(RSO), in the Safety Office phone: 518-266-5635, must be notified when any radioactive sources are to be brought into WVA and must be given a copy of required licenses. The Watervliet Arsenal RSO must also be provided a POC before materials are to be brought on post for any potential follow-up questions or required information. No one will be allowed to bring any
Section 01 14 00 Page 14 radioactive source on post until an Army Radiation Permit is issued by the
Commanding Officer through the WVA RSO.
54. MEDIA: The Arsenal public affairs officer must approve any media announcement or press release that mentions the Watervliet Arsenal in either the headline or in the text of the release. Additionally, no media activity may occur on the Arsenal without prior coordination with the public affairs officer. Coordination or requests for approval must be submitted to the public affairs officer at least two working days prior to the event.
55. EMERGENCY EVACUATION PLAN: All contractor personnel working on the site will be responsible to be familiar with the building's existing emergency evacuation plan, if available and applicable to the project's worksite. The contractor shall provide the COR with the contractor's emergency evacuation plan from the worksite if different from the existing emergency evacuation plan.
56. HOT WORK PERMITS: All contractors are advised to avoid working on live/hot electrical systems on the installation. If it is deemed necessary to do any hot work on the installation a hot work permit must be authorized by the fire department before starting any
Section 01 22 00.00 10 Page 1
SECTION 01 22 00.00 10
PRICE AND PAYMENT PROCEDURES
1.1 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the SCHEDULE and described below.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.