AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Revise and reissue the plans and specifications.

2) Provide answ ers to questions received.

3) See additional changes below

Bidders must acknow ledge receipt of this amendment by the date specified in the solicitation (or as amended) by one of the follow ing methods: In the space provided on the SF1442, by separate letter, by telegram, or by signing the block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIEDMAY RESULT OF REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE MODIFICATIONS OF BIDS OR LATE WITHDRAWAL OF BIDS (FAR 14.304). Except as provided herein, all terms and conditions ofthe document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Sep-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS18B0022

X 9B. DATED (SEE ITEM 11)

10-Aug-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Aug-2018

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 1843

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS18B0022

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 3

TO OFFORERS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing IF101

- Drawing IF102

- Drawing M-604

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- Appendix A – MX Training Facility – Geotechnical Report

- Section 09 65 00 – Resilient Flooring

- Section 09 77 20 – Fiberglass Reinforced Wall Panel

- Section 10 14 00.20 – Interior Signage

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- None

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- None

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- Section 00 70 00 – Conditions of the Contract – Revise clause 52.236-1 in its entirety as follows: “The

Contractor shall perform on the site, and with its own organization, work equivalent to at least 20 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting. Officer determines that the reduction would be to the advantage of the Government.”

- Section 01 11 00 – Summary of Work – Add the following sub-paragraph to 1.2.1 “The Government is in the process of obtaining the Burlington County soil erosion permit, as soon as its approved it will be provided to the contractors. The contractor will be required to obtain the JB MDL Dig Permit. ”

- Section 01 14 00 – Work Restrictions – Replace only the first two sub-paragraphs of paragraph 1.2.4 with the following: “The contractor will be working within/next to occupied building. Any work disrupting classes shall be coordinated in advance (14 days) with the COR and building occupants. The existing building and its contents must be kept secure (temporary closure shall be provided at the location next to the new addition at the end of corridor in existing building 2324 (next to rooms 018 & 139) and/or in the hallway (next to room 009 & 027) segregating the area within B2324 that is going to be renovated. The number of temporary closures will depend on the contractors approach, to be discussed with the COR and building occupants.) ”

- Section 01 50 00 – Temporary Construction Facilities and Controls – replace paragraph 3.5.7 in its entirety with the following: “NOT USED.”

BIDDER’S QUESTIONS AND GOVERNMENT REPLY

1. Please provide us with the Geo-technical report and soil analysis report for the addition area of this solicitation. Response: Copy of the geotech report is issued with this amendment.

2. Please refer to drawings IF 101 and IF 102, general note mentions that all classroom furniture and equipment shall be provided by Boeing (Not in Contract). However, the bid form Item No. 0004 calls for Purchase, Deliver and Install furnishing and appliances. Please Clarify? Response: Classroom furniture that are shown with a dashed lines on drawings IF 101, 102 are not in contract. All other furnishings as listed in the Furniture Schedule on the drawings are to be provided as part of CLIN 0004. Note has been added to the drawings to clarify.

3. The louver schedule on M604 shows LV-1 as 44' x 44' and the other louvers are similarly designated in feet. Scaling the louvers from the plan suggests that the schedule should be in inches. Response: LV-1 is shown on M-401. Louver size should be 44"X44". Please see revised drawing.

4. Please provide specifications for VINYL COMPOSITION TILE (VCT) depicted on finish schedule.

Response: Specification Section 09 65 00, Resilient Flooring, is included with this amendment.

5. Please provide specification for Interior Signage. Please confirm that no exterior signage is required for this project. Response: Specification Section 10 14 00.20, Interior Signage, is issued by Amendment.

Correct, there is no exterior signage required.

6. IFB on clause 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) is stating that "The Contractor shall perform on the site, and with its own organization, work equivalent to at least 40 percent of the total amount of work to be performed under the contract"; this percent is higher than the usual 15% for small business contractors, would the government entertain reducing this percentage?

Response: The Clause is hereby revised to 20% of work to be completed by the contractor.

7. On section 01 14 00, para 1.2.4 Occupied Building; states that "The Contractor shall be working in and around an existing eligible historic structure which is occupied", please clarify what parts of the existing building that would be affected with project scope of work would be historic. Also the same paragraph states "Provide temporary closures as required to maintain security as directed by the Contracting Officer.

Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the area during the construction period." Please provide a plan where such temporary partitions are required and the expected level of construction and finish. Response: The paragraph relating to Historic building is hereby removed. Please see revision to the Specification as issued in this amendment.

8. on Section 01 45 00.00 10, para 3.4.3 CQC Personnel states that The additional CQC Personnel are "directly employed by the prime Contractor and cannot be employed by a supplier or subcontractor on this project; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized personnel’s areas of responsibility". Small Business GC cannot have this number of personnel with different disciplines experience employed on one project. Can these personnel by employed by subcontractors? Response: No, please follow the requirements of the specifications as outlined in the solicitation.

9. On section 01 50 00; please clarify if the building required per para (3.5.7 New Building) is the same as what required by para (3.6 GOVERNMENT FIELD OFFICE) or not? If not, whats this building is for?

Response: The sections is hereby revised to remove this requirement.

10. Please advise if the contractor is responsible for filing and/or paying fees for any state or local required project related permits. Response: The Government is obtaining the Burlington County Soil Erosion permit. The contractors will be responsible for JB MDL dig permit and others as applicable. Please refer to revisions to the specifications.

11. Door schedule on Sheet AE601 list no aluminum doors, please clarify which openings would specification section 08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS be applicable for.

Response: Exterior windows are to be framed with aluminum storefront framing as noted in Detail 6 on

AE606.

12. Paragraph 1.5 REQUIRED AIR BLAST DESIGN LOAD on Specification section 08 41 14 BLAST

PERFORMANCE REQUIREMENTS FOR EXTERIOR GLAZED DOORS, WINDOWS AND CURTAIN

WALL lists Window ID's that are not depicted on Architectural Drawings, please specify which of the windows (W1 to W12) would this specification section would be applied for. Response: The table included in Section 08 41 14 is an example of how the data should be formatted in the delegated design.

The only windows requiring blast resistant design are exterior windows (Type W12) windows on the south side of the addition, all others are interior windows.

13. Please provide the basis of design for the curtain walls. Response: The basis-of-design for the storefronts is Kawneer Trifab Versaglaze 451T center-set, an approved equal will also be considered.

14. Please provide the basis of design for the Translucent panels. Response: The basis of design for the translucent wall panels is Kalwall 4" Wall System in Reverse Shoji pattern, an approved equal will also be considered.

15. Please provide specification for the FRP Panel called out on note #3 of the finish schedule. Response:

Specification Section 09 77 20, Fiberglass Reinforced Panels, is hereby issued with the amendment.

(End of Summary of Changes)