Package_3_-_Davis_Barracks_Chiller_Plant_and_Shotcrete_-_Specs.pdf

PDF 4 MB Posted

Attached to
Central Chiller Plant/Distribution at the USMA, West Point, NY
Solicitation number
W912DS-17-R-0008
Issued by

About this file

Package 3 - Davis Barracks Chiller Plant and Shotcrete - Specs

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications Volume 1

USMA West Point, New York Davis Barracks Chilled Water Plant and Cooling Tower

W912DS-17-R-0008

Issue for Bid

April 2017

Prepared for:

US Army Corps of Engineers New York District

Prepared by:

2318 Mill Road, Suite 1040 Alexandria, VA 22314

DAVIS BARRACKS CHILLER PLANT AND DISTRIBUTION SYSTEM W912DS-17-R-0008

Section 00 01 07 Page 1 Issue for Bid

SECTION 00 01 07

SEALS PAGE

ARCHITECT:

Atkins 6504 BridgePoint Parkway #200 Austin, Texas 78730

7-29-2016

CIVIL ENGINEER:

Atkins 11818 Rock Landing Drive Suite 100 Newport News, Virginia 23606

STRUCTURAL ENGINEER:

Atkins 482 South Keller Road Orlando, Florida 32810

STRUCTURAL ENGINEER

FOUNDATIONS:

Tectonic Engineering and Surveying 1279 Route 300 Newburgh, New York 12550

ELECTRICAL ENGINEER

HIGH AND MEDIUM VOLTAGE:

Atkins 482 South Keller Road Orlando, Florida 38210

Issue for Bid

This page intentionally left blank

Section 00 01 07 Page 2 Issue for Bid

ELECTRICAL ENGINEER:

Vanderweil 1001 Avenue of the Americas 21st Floor New York, NY 10018

7-29-2016

TELECOMMUNICATIONS:

Vanderweil 1001 Avenue of the Americas 21st Floor New York, NY 10018

7-29-2016

MECHANICAL ENGINEER

STEAM TUNNEL PIPING:

Atkins 2318 Mill Road #1040 Alexandria, Virginia 22314

MECHANICAL ENGINEER

HVAC:

Vanderweil 1001 Avenue of the Americas 21st Floor New York, NY 10018

7-29-2016

FIRE PROTECTION ENGINEER:

Vanderweil 1001 Avenue of the Americas 21st Floor New York, NY 10018

7-29-2016

Section 00 01 07 Page 3 Issue for Bid

PLUMBING ENGINEER:

Vanderweil 1001 Avenue of the Americas 21st Floor New York, NY 10018

-- End of Seals Page--

SECTION 00 01 10 Page 1 Issue for Bid

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 SEALS PAGE

00 01 10 PROJECT TABLE OF CONTENTS

00 73 00.00 18 SPECIAL CONTRACT REQUIREMENTS (NYD) 03/15

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK 08/15

01 32 01.00 10 PROJECT SCHEDULE 02/15

01 33 00 SUBMITTAL PROCEDURES 05/11

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS 02/12

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS 11/14

01 45 02.00 18 QUALITY CONTROL SYSTEM (QCS)(NYD) 07/10

01 45 04.00 18 CONTRACTOR QUALITY CONTROL (NYD) 12/99

01 45 20.00 18 TESTING FOR MECHANICAL AND ELECTRICAL SYSTEMS (NYD) 09/03

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS 08/09

01 52 60.00 18 CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT (NYD) 09/05

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS 11/15

01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT 01/07

01 78 00.00 18 CLOSEOUT SUBMITTALS (NYD) 06/12

01 78 23.00 18 OPERATION AND MAINTENANCE DATA (NYD) 12/01

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION 05/10

DIVISION 03 – CONCRETE

03 11 13.00 10 05/14 03 15 00.00 10 05/14

03 20 00.00 10 05/14

03 30 00.00 10 05/14 03 30 53

STRUCTURAL CAST IN PLACE CONCRETE

CONCRETE ACCESSORIES

CONCRETE REINFORCING

CONCRETE REINFORCING - SHOTCRETE SOW

CAST-IN-PLACE CONCRETE

MISCELLANEOUS CAST-IN-PLACE CONCRETE

SHOTCRETE

05/14

DIVISION 04 – MASONRY

04 20 00 UNIT MASONRY 11/15

DIVISION 05 – METALS

05 05 23.16 STRUCTURAL WELDING 05/14

05 12 00 STRUCTURAL STEEL 05/14

05 30 00 STEEL DECKS 05/15

05 40 00 COLD-FORMED METAL FRAMING 05/15

05 50 13 MISCELLANEOUS METAL FABRICATIONS 05/10

05 51 00 METAL STAIRS 02/12

05 51 33 METAL LADDERS 05/10

05 52 00 METAL RAILINGS 02/11

03 20 00.00 10

03 37 13

SECTION 00 01 10 Page 2 Issue for Bid

DIVISION 06 – WOOD, PLASTIC, AND COMPOSITES

06 10 00 ROUGH CARPENTRY 02/12

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 21 16 MINERAL FIBER BLANKET INSULATION 11/11

07 42 13 METAL WALL PANELS 05/11

07 84 00 FIRESTOPPING 05/10

07 92 00 JOINT SEALANTS 01/07

DIVISION 08 – OPENINGS

08 11 13 STEEL DOORS AND FRAMES 02/10

08 33 23 OVERHEAD COILING DOORS 08/15

08 71 00 DOOR HARDWARE 08/08

DIVISION 09 – FINISHES

09 22 00 SUPPORTS FOR GYPSUM BOARD 02/10

09 29 00 GYPSUM BOARD 05/11

09 51 00 ACOUSTICAL CEILINGS 08/10

09 90 00 PAINTS AND COATINGS 05/11

DIVISION 10 – SPECIALTIES

10 14 00.20 INTERIOR SIGNAGE 11/12

10 44 16 FIRE EXTINGUISHERS 05/15

DIVISION 21 - FIRE SUPPRESSION

21 13 00.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION 05/09

DIVISION 22 – PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE 11/11

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 08/10

23 03 00.00 20 08/10 23 05 15 02/14 23 05 48.00 40

08/15 23 05 93 08/09 23 07 00 02/13 23 08 00.00 10 01/08 23 09 00 11/15 23 09 13 11/15 23 09 23.01

11/15 23 25 00

AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST

SYSTEMS

BASIC MECHANICAL MATERIALS AND METHODS

COMMON PIPING FOR HVAC

VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

TESTING, ADJUSTING, AND BALANCING FOR HVAC

THERMAL INSULATION FOR MECHANICAL SYSTEMS

COMMISSIONING OF HVAC SYSTEMS

INSTRUMENTATION AND CONTROL FOR HVAC

INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER

BUILDING CONTROL SYSTEMS

CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS 11/08

SECTION 00 01 10 Page 3 Issue for Bid

23 64 10 WATER CHILLERS, VAPOR COMPRESSION TYPE 08/09

23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING

SYSTEMS 08/09

23 65 00 COOLING TOWERS 08/08

23 70 03.00 10 HEATING AND UTILITIES SYSTEMS, CENTRAL STEAM 01/08

DIVISION 25 - INTEGRATEED AUTOMATION

25 08 10 UTILITY MONITORING AND CONTROL SYSTEM TESTING 04/06

25 10 10 UTILITY MONITORING AND CONTROL SYSTEM (UMCS) FRONT

END AND INTEGRATION 11/15

DIVISION 26 - ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS 07/06

26 05 13.00 40 MEDIUM-VOLTAGE CABLES 11/13

26 08 00 APPARATUS INSPECTION AND TESTING 08/08

26 11 16 SECONDARY UNIT SUBSTATIONS 02/10

26 20 00 INTERIOR DISTRIBUTION SYSTEM 08/08

26 23 00 LOW-VOLTAGE SWITCHGEAR 05/15

26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION 10/07

26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS 04/06

26 33 53.00 20 UNINTERRUPTIBLE POWER SUPPLY (UPS) 04/08

26 41 00 LIGHTNING PROTECTION SYSTEM 11/13

26 51 00 INTERIOR LIGHTING 07/07

DIVISION 27 - COMMUNICATIONS

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS 08/11

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM 08/11

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND

SECURITY 06/11

28 20 01.00 10 ELECTRONIC SECURITY SYSTEM 10/07

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM 08/11

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK 08/08

31 60 00 FOUNDATION PREPARATION 11/08

31 63 26 DRILLED CAISSIONS 08/08

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 01 16.17 COLD MILLING OF BITUMINOUS PAVEMENTS 08/08

32 10 00 BITUMINOUS CONCRETE PAVEMENT 08/08

32 12 10 BITUMINOUS TACK AND PRIME COATS 08/08

32 16 13 CONCRETE SIDEWALKS AND CURBS 04/08

32 92 19 SEEDING 10/06

32 92 23 SODDING 04/06

SECTION 00 01 10 Page 4 Issue for Bid

DIVISION 33 – UTILITIES

33 11 00 WATER DISTRIBUTION 02/11

33 30 00 SANITARY SEWERS 04/08

33 61 00 PREFABRICATED UNDERGROUND HEATING/COOLING

DISTRIBUTION SYSTEM 04/08

-- End of Section --

The graphic format for this 4' x 6' sign panel follows the legend guidelines and layout as specified below. The large 4' x 4' section of the panel in the right is to be white with black legend. The 2' x 4' section of the sign on the left with the full corps Signature (reverse version) is to be screen printed Communications Red on the white background. The castle insignia will be furnished by the Government in pressure sensitive vinyl for affixing by the Contractor.

See attached sheet for fabrication and mounting guidelines.

SAMPLE:

2"

2.5"

Davis Barracks Chilled Water Plant

US Military Academy, West Point NY

3" 21" 1" 21"

6"

4.5"

3"

(Dimensions are in inches)

4.5"

6"

2.25"

21" 3" 42" of Engineers

Design and Construction

New York District

US Army Corps

7.75"

9.5"

2"

1.875"

1.875"

1.875"

1.875" identification of project or facility

(civil works) or name of sponsoring department (military).

Typeface: 3" Helvetica Bold

Maximum line length: 42"

Legend Group 4: One-to two-line three-line project title legend describes the work being done under this contract.

Color: Black

Color: White

Typeface: 1.25" Helvetica Regular

Legend Group 3: One- to

10.5"

PROJECT IDENTIFICATION SIGN

MILITARY PROJECT

4.5"

6.25"

Legend Group 1: One- to two-line 3"

Supervised by Color: White

District Name (optional). Place description of Corps relationship to project

Castle) below 10.5" Reverse Signature (6"

Typeface: 1.25" Helvetica Regular

Maximum line length: 19"

Legend Group 2: Division or

PROJECT IDENTIFICATION SIGN

* Refers to the U.S. Army Corps of Engineers, "Sign Standards Manual", EPS-310-1-6.

CID-01 various

Panel

48" WH-RD/BK

line identification of prime

Cross-align the first of Legend

4' x 6'

Color

Size Size Code Height Bkg/Lgd

Mounting

4' x 4'

Type

Legend

* Appendix D

Color: Black

(architect, general contractor, etc.), corporate or firm name, city, state.

Use of Legend Group 5 is optional.

contractors including: type

Post Specification Sign

HDO-3

Legend Group 5a-b: One-to-five initial capitals only as shown.

Letter and word spacing to follow

Corps standards as specified in

Typeface: 1.25" Helvetica Regular

Maximum line length: 21"

All typography is flush left and rag right upper and lower case with

Group 4 with the first line of the

Corps Signature (US Army Corps) as shown.

Color: Black

Typeface: 1.5" Helvetica Regular

Maximum line length: 42"

The graphic format, color, size and type-faces used on the sign are to be reproduced exactly as specified below. The title with First Aid logo in the top section of the sign, and the performance record captions are standard for all signs of this type. Legend Group 2 and 3 below identify the project and the contractor and are to be placed on the sign as shown.

Safety record numbers are mounted on individual metal plates and are screw-mounted to the background to allow for daily revisions to posted safety performance record.

Legend Group1: Standard two-line title "safety is a Job Requirement", with (8" od.) Safety Green First Aid logo. Color: To match PMS 347 Typeface: 3" Helvetica Bold Color: Black

Legend Group 2: One- to two-line project title legend describes the work being done under this contract and name of host project.

Color: Black 2.25" Typeface: 1.5" Helvetica Regular Maximum line length: 42"

2.25" Legend Group 3: One - to two-line identification: name of prime This project has Days without & contractor and city, state address. 1.875" operated: lost time injury 4.875" Color: Black Typeface: 1.5" Helvetica Regular Total days worked Maximum line length: 42" 1.875" on this contract 4.875"

Legend Group 4: Standard safety Lost time record captions as shown. 1.875" injuries 4.875" Color: Black

Typeface: 1.25" Helvetica Regular

R l bl b t b

3"

4"

3"

3" 3.875"

SAFETY PERFORMANCE SIGN

Safety is a Job Requirement

3" 3"8"

Davis Barracks

Chilled Water Plant

US Military Academy, West Point NY

3" 31"

6"

4.5"

10.5"

Replaceable numbers are to be mounted on white .060: aluminum plates and screw-mounted to background.

Color: Black Typeface: 3" Helvetica Regular Plate size: 2.5"x.5"

All typography is flush left and rag right, upper and lower case with initial capitals only as shown.

Letter- and word-spacing to follow Corps standards as specified in Appendix D. *

* Refer to the U.S. Army Corps of Engineers, "Sign Standards Manual", EPS-310-1-6.

Sign Legend Post Specifications Mounting Color Type Size Size Code Height Bkg/Lgd CID-02 various HDO-3 48" WH/BK-GR

.875"

3.125"

.975"

SAFETY PERFORMANCE SIGN

mounting guidelines.

Panel Size

2.5"

4"x4" 4"x4"

2.5" 2.5"

See attached sheet for fabrication and

Dimensions inches.

3" 2" 17"

As Construction Project Identification signs Detailed specifications for and Safety Performance signs are to be HDD plywood panel preparation are pro-fabricated and installed as described vided in Appendix B.** below. The signs are to be erected at a Shown below the mounting diagram is location designated by the contracting of- a panel layout grid with spaces provided ficer and shall conform to the size, format, for project information. Photocopy this and typographic standards shown on page and use as a worksheet when pre-the attached sheets. paring sign legend orders.

The sign panels are to be fabri-cated from .75" High Density Over-lay Plywood. Panel preparation to follow HDD specifications provided in Appendix B. **

Sign graphics to be prepared on a white non-reflective vinyl film with positionable adhesive backing.

All graphics except for the Com-munications Red background with Corps signature on the project sign are to be die-cut or computer-cut non-reflective vinyl, pre-spaced legends prepared in the sizes and typefaces specified and applied to the background panel following the graphic formats shown on the attached sheets.

The 2'x4' Communications Red panel (to match PMS-032) with full Corps signature (reverse ver-sion) is to be screen printed on the white background. Identifica-tion of the District or Division may be applied under the signature with white cut vinyl letters pre-pared to Corps standards. Large Construction Project Sign scale reproduction artwork for the Legend Group 1: Corps Relationship signature is provided on page 4.8

Drill and Insert six (6) .375" T-nuts from the front face of the HDD Legend Group 2: Division/District Name

2.

sign panel. Position holes as 1.

shown Flange of T-nut to be flush

18"

(photographically enlarge from 1.

6.875" to 10.5"). **

Fabrication and Mounting Guidelines

48"

48"

(Dimensions in inches)

** Refers to the U.S. Army Corps of Engineer "Sign Standards Manual", EP-310-1-6.

Apply graphic panel to prepared Legend Group 3: Project Title HDD plywood panel following better. Post to be 12" long. Drill six (6) .375" mounting holes in Legend Group 4: Facility Name uprights to align with T-nuts in sign

Assemble sign panel and uprights. Legend Group 5a: Contractor/A&E Legend Group 5b: Contractor /A&E Imbed assembled sign panel and

Safety Performance Sign Legend Group 1: Project Title

Legend Group 2: Contractor/A&E

1.

2.

5. 5.

1.

2.

reinforce installation as shown 3. 3.

4. 4.

require bolting additional 2"x4" 2. 2.

struts on inside face of uprights to uprights in 4" hole. Local soil con- 1. 1.

ditions and/or wind loading may panel. Countersink (.5") back of 1.

hole to accept socket head cap screw (4"x.375"). 2.

2.Sign uprights to be structural grade 4"x4" treated Douglas Fir

3.or Southern Yellow Pine. No.1 or with sign face. 2.

manufacturers' instructions. 1.

shown. Flange of T-nut to be flush

DAVIS BARRACKS - CHILLED WATER PLANT AND COOLING TOWER W912DS-17-R-0008

USMA, West Point, New York

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The project includes construction of a chilled water plant within the Davis Barracks and portions of a site chilled water distribution piping system.

Davis Barracks construction is scheduled to be completed by 13 September 2016, with occupancy scheduled for 29 December 2016. The chilled water plant will supply chilled water to the nine historic cadet barracks (735 Scott Barracks, 745E MacArthur Short Barracks, 745D MacArthur Long Barracks, 751 Pershing Barracks, 745C Eisenhower Barracks, 602 Grant Barracks, 756 Bradley Barracks, 740 Lee Barracks, and 738 Sherman Barracks). The nine historic barracks will be renovated as part of the Cadet Barracks Upgrade Program (CBUP).

The project will include modifications to the chilled water plant provided as part of the Davis Barracks project, and include the following major components:

a. Two 850 ton water cooled electrical centrifugal chillers.

b. Two 850 ton water cooled steam turbine driven chillers.

c. Five variable flow primary chilled water pumps.

d. Chilled water expansion tanks.

e. Five variable flow condenser water pumps.

f. Five cooling tower cells and associated structural support with service platform.

g. Steam and condensate return piping systems.

h. Chilled water piping system.

i. Condenser water piping system.

j. Chilled water plant automation and control system.

k. An acoustically isolated ceiling.

l. 13.8 kv primary electrical service, electrical substation and electrical power distribution systems.

The project will include site chilled water piping as follows:

a. Direct-buried segment east of Washington Hall between Eisenhower and MacArthur Long Barracks.

b. Direct-buried segment in the main Cadet formation area that extends

Section 01 11 00 Page 1 from the south side of Eisenhower Barracks (5 feet outside building) to the new Davis Barracks utility tunnel under Brewerton Road (near Steam Vault G) and through Bradley Barracks basement.

c. Direct-buried segment between Davis Barracks and Sherman Barracks.

Main piping terminates 5 feet outside of the building underground near the northeast building corner for future connection to Sherman Barracks.

d. Segment in new utility tunnel from Davis Barracks/Cadet Barracks Chilled Water Plant to termination in Brewerton Road near Steam Vault G.

e. The project will include replacement of the exiting emergency high pressure steam supply piping from Building 604 (Central Power Plant) to Steam Vault G (approximately 800 LF). The steam piping is located in the existing underground steam tunnel.

The 13.8 kv primary electrical service will include new 13.8 kv feeders from the existing Delafield Substation to the chilled water plant substation.

The work includes construction of an approximately 1,150 square foot one-hour fire resistant interior room within the existing first level Barracks Chiller Area of the Davis Barracks. The room will contain new switchgear serving the existing adjacent chilled water treatment plant.

Interior finishes consist of painted CMU walls, suspended gypsum board ceilings,and approximately 5,900 sf of suspended acoustical treated ceiling panels at the existing adjacent Barracks Chiller Area. Rated interior wall openings include a hollow metal double door unit and a manual overhead coiling door.

Exterior work includes an approximately 3,500 square foot reinforced concrete foundation on drilled caissons, supporting a structural steel platform and five evaporative cooling tower cells. Structural steel platform includes primary framing, grated assemblies, stair and rail assemblies, primary and secondary steel exterior wall framing systems supporting insulated metal panel assemblies.

1.1.2 Location

The project site is located at the United States Military Academy within the Central Cadet Zone. Chilled water equipment is located within the Davis Barracks building with distribution piping extending to all the barracks within the Cadet Zone. The cooling towers will be located on the embankment to the south of Davis Barracks, just north of the water tank and at the end of the De Russy Loop.

1.2 OCCUPANCY OF PREMISES

The Davis Barracks will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.3 EXISTING WORK

Section 01 11 00 Page 2

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.4 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground, pier deck or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.5 DELIVERY LOCATION

Access to the site is from the service road that is part of the Davis Barracks project. The cul-de-sac at the end of the service road can serve as a staging area (approximately 50 feet by 50 feet).

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

Section 01 11 00 Page 3

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G Preliminary Project Schedule; G Initial Project Schedule; G Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

Section 01 32 01.00 10 Page 1

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the

Section 01 32 01.00 10 Page 2 disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

Section 01 32 01.00 10 Page 3

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:

http://rms.usace.army.mil.

The SDEF format is as follows:

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

Section 01 32 01.00 10 Page 4

Field Activity Code Length Description

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

Section 01 32 01.00 10 Page 5

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

Section 01 32 01.00 10 Page 6

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs.

Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

Section 01 32 01.00 10 Page 7

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.12 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.13 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.14 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.15 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

3.3.16 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but

Section 01 32 01.00 10 Page 8 for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.

3.3.17 Remaining Duration

Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.

3.3.18 Cost Loading of Closeout Activities

Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).

3.3.18.1 As-Built Drawings

If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.

3.3.18.2 O & M Manuals

Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.

3.3.19 Anticipated Adverse Weather

Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Reflect the number of anticipated adverse weather delays allocated to a weather sensitive activity in the activity's calendar.

3.3.20 Early Completion Schedule and the Right to Finish Early

An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.

a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.

b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.

3.4 PROJECT SCHEDULE SUBMISSIONS

Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph

Section 01 32 01.00 10 Page 9

SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.

Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.

3.4.1 Preliminary Project Schedule Submission

Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP. Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code (FOW).

3.4.2 Initial Project Schedule Submission

Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.

3.4.3 Periodic Schedule Updates

Update the Project Schedule on a regular basis, monthly at a minimum.

Provide a draft Periodic Schedule Update for review at the schedule update meetings as prescribed in the paragraph PERIODIC SCHEDULE UPDATE MEETINGS.

These updates will enable the Government to assess Contractor's progress.

a. Update information including Actual Start Dates (AS), Actual Finish Dates (AF), Remaining Durations (RD), and Percent Complete is subject to the approval of the Government at the meeting.

b. AS and AF dates must match the date(s) reported on the Contractor's Quality Control Report for an activity start or finish.

3.5 SUBMISSION REQUIREMENTS

Submit the following items for the Preliminary Schedule, Initial Schedule, and every Periodic Schedule Update throughout the life of the project:

Section 01 32 01.00 10 Page 10

3.5.1 Data CD/DVDs

Provide two sets of data CD/DVDs containing the current project schedule and all previously submitted schedules in the format of the scheduling software (e.g. .xer). Also include on the data CD/DVDs the Narrative Report and all required Schedule Reports. Label each CD/DVD indicating the type of schedule (Preliminary, Initial, Update), full contract number, Data Date and file name. Each schedule must have a unique file name and use project specific settings.

3.5.2 Narrative Report

Provide a Narrative Report with each schedule submission. The Narrative Report is expected to communicate to the Government the thorough analysis of the schedule output and the plans to compensate for any problems, either current or potential, which are revealed through that analysis. Include the following information as minimum in the Narrative Report:

a. Identify and discuss the work scheduled to start in the next update period.

b. A description of activities along the two most critical paths where the total float is less than or equal to 20 work days.

c. A description of current and anticipated problem areas or delaying factors and their impact and an explanation of corrective actions taken or required to be taken.

d. Identify and explain why activities based on their calculated late dates should have either started or finished during the update period but did not.

e. Identify and discuss all schedule changes by activity ID and activity name including what specifically was changed and why the change was needed. Include at a minimum new and deleted activities, logic changes, duration changes, calendar changes, lag changes, resource changes, and actual start and finish date changes.

f. Identify and discuss out-of-sequence work.

3.5.3 Schedule Reports

The format, filtering, organizing and sorting for each schedule report will be as directed by the Contracting Officer. Typically, reports contain Activity Numbers, Activity Description, Original Duration, Remaining Duration, Early Start Date, Early Finish Date, Late Start Date, Late Finish Date, Total Float, Actual Start Date, Actual Finish Date, and Percent Complete. Provide the reports electronically in .pdf format. Provide three set(s) of hardcopy reports. The following lists typical reports that will be requested:

3.5.3.1 Activity Report

List of all activities sorted according to activity number.

3.5.3.2 Logic Report

List of detailed predecessor and successor activities for every activity in ascending order by activity number.

Section 01 32 01.00 10 Page 11

3.5.3.3 Total Float Report

A list of all incomplete activities sorted in ascending order of total float. List activities which have the same amount of total float in ascending order of Early Start Dates. Do not show completed activities on this report.

3.5.3.4 Earnings Report by CLIN

A compilation of the Total Earnings on the project from the NTP to the data date, which reflects the earnings of activities based on the agreements made in the schedule update meeting defined herein. Provided a complete schedule update has been furnished, this report serves as the basis of determining progress payments. Group activities by CLIN number and sort by activity number. Provide a total CLIN percent earned value, CLIN percent complete, and project percent complete. The printed report must contain the following for each activity: the Activity Number, Activity Description, Original Budgeted Amount, Earnings to Date, Earnings this period, Total Quantity, Quantity to Date, and Percent Complete (based on cost).

3.5.3.5 Schedule Log

Provide a Scheduling/Leveling Report generated from the current project schedule being submitted.

3.5.4 Network Diagram

The Network Diagram is required for the Preliminary, Initial and Periodic Updates. Depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The Contracting Officer will use, but is not limited to, the following conditions to review compliance with this paragraph:

3.5.4.1 Continuous Flow

Show a continuous flow from left to right with no arrows from right to left. Show the activity number, description, duration, and estimated earned value on the diagram.

3.5.4.2 Project Milestone Dates

Show dates on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

3.5.4.3 Critical Path

Show all activities on the critical path. The critical path is defined as the longest path.

3.5.4.4 Banding

Organize activities using the WBS or as otherwise directed to assist in the understanding of the activity sequence. Typically, this flow will group activities by major elements of work, category of work, work area and/or responsibility.

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

Section 01 32 01.00 10 Page 12

With each schedule submission, provide a SVC diagram showing 1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates, and 2) Earned Value to-date.

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

Conduct periodic schedule update meetings for the purpose of reviewing the proposed Periodic Schedule Update, Narrative Report, Schedule Reports, and progress payment. Conduct meetings at least monthly within five days of the proposed schedule data date. Provide a computer with the scheduling software loaded and a projector which allows all meeting participants to view the proposed schedule during the meeting. The Contractor's authorized scheduler must organize, group, sort, filter, perform schedule revisions as needed and review functions as requested by the Contractor and/or Government.