AMENDMENT 0004

View the file

Other files

File Type Posted
W912DS-13-B-0003_Amend_0006.pdf PDF
Plans_-_Amendment__5.pdf PDF
W912DS-13-B-0003_Amend_0005.pdf PDF
Appendix_T_-_FY13_Sealift_Rates_-_Amendment__5.pdf PDF
Specs_-_Amendment__5_(MTOC).pdf PDF
Specs_01_33_00_5_(Submittal_Register).pdf PDF
Plans_-_Amendment__4.pdf PDF
Specs_01_33_00_4_(Submittal_Register).pdf PDF
Specs_23_09_23_4.pdf PDF
Specs_-_Amendment__4_(MTOC).pdf PDF
Amendment_0003.pdf PDF
Plans_-_Amendment__2.pdf PDF
Appendix_M_-_DBA_Waiver_-_Amendment__2.pdf PDF
W912DS-13-B-0003_Amend_0002.pdf PDF
W912DS-13-B-0003_Amend_0001.pdf PDF
SF24-98_Bid_Bond.pdf PDF
Plans_-_Amendment__1.pdf PDF
Package_2_-_FY13_Thule_Dorm_48_Person_-_Plans.pdf PDF
Package_3_-_FY13_Thule_Dorm_48_Person_-_CID.pdf PDF
Appendix_S_-_Foundations_Governing_Forces.pdf PDF
Appendix_B_-_NFS_Material_Borrow_Site.pdf PDF
W912DS-13-B-0003_Solicitation.pdf PDF
Appendix_C_-_Conservation_Mgmt_Plan.pdf PDF
Appendix_E_-_Spill_Prevention-Response_Plan.pdf PDF
Appendix_K_-_FGS-GL_(Environmental_Protection).pdf PDF
Appendix_H_-_Storm_Water_Mgmt_Plan.pdf PDF
Appendix_P_-_Pacer_Goose_Shipping_Instructions.pdf PDF
Appendix_D_-_HWM_Plan.pdf PDF
Appendix_Q_-_Shipping_Rates_Gov_Furnished_Transport.pdf PDF
Appendix_A_-_Active_Landfills.pdf PDF
Appendix_M_-_DBA_Waiver.pdf PDF
Appendix_J_-_Installation_HAZMAT_Management_Plan.pdf PDF
Appendix_L_-_Affirmative_Proc_Plan.pdf PDF
Appendix_F_-_PPM_Plan.pdf PDF
Appendix_N_-_FY13_Thule_Dorm_Topo_Survey.dwg DWG drawing
Appendix_R_-_Geotechnical_Investigation.pdf PDF
Appendix_O_-_Survey_Photos_of_Project_Site.pdf PDF
Appendix_I_-_Slug_Mgmt_Plan.pdf PDF
Appendix_G_-_Solid_Waste_Mgmt_Plan.pdf PDF
Package_1_-_FY13_Thule_Dorm_48_Person_-_Specs.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1) Revise the Draw ings

2) Revise the Specifications

3) Respond to contractors' questions (FOR INFORMATIONAL PURPOSES ONLY)

The bid opening date remains unchanged, 27 February 2013 at 9:00AM EST in New York and 3:00PM in Copenhagen, Denmark.

NOTE: Bidders must acknow ledge receipt of this amendment by the date specified in the bid (or as amended) by one of the follow ing methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENT BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE

MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 30-Jan-2013

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DS-13-B-0003

X 9B. DATED (SEE ITEM 11)

28-Nov-2012

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

29-Jan-2013

CODE

US ENGINEER DISTRICT, NEW YORK

US ARMY CORPS OF ENG, NYD

NEW YORK NY 10278

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS-13-B-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0004

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- Drawing M-706 - General Note #6 is replaced in its entirety with the following: “Total of six (6) ground thermistor strings from Civil DWG C-103”

2. The following DRAWINGS have been REVISED and REISSUED:

- Drawing A-302

- Drawing A-402

- Drawing A-504

- Drawing E-002

- Drawing EL-501

3. The following DRAWINGS have been ADDED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- Section 23 09 23.13 20 – BACnet Direct Digital Control system for HVAC

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- Section 22 10 00 – Plumbing – Domestic Potable Supply Water Piping Inside Building.

- Section 23 09 23 – LonWorks Direct Digital Control system for HVAC and other building control systems

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- Section 01 33 00.00 18 – Submittal Procedures (Submittal Register Only)

- Main Table of Contents

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- Section 23 00 00 – Paragraph 2.14.3 - Controls is hereby replaced in its entirety with the following: “The requirements for controls are specified in Section 23 05 93 TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS and Section 23 09 23.13 20 BACnet

DIRECT DIGITAL CONTROL FOR HVAC.”

- Section 23 57 10.00 10 – Paragraph 2.14.5 - Controls is hereby replaced in its entirety with the following: “Controls shall be provided as specified in 23 09 23.13 20 BACnet DIRECT DIGITAL

CONTROL FOR HVAC.”

- Section 23 57 10.00 10 - Paragraph 2.17.1 (i), (q) and paragraph 2.17.2 (i), (q) is herby replaced in its entirety with the following; “B&G technologic # 502 controller duplex variable frequency drive, Modbus or Johnson N2 communication on open protocol BACnet”,and “Nema 4-12 native BACnet control panel with complete start-up and shut down sequence for remote operation.”

respectively.

- Section 23 57 10.00 10 - Paragraph 2.17.3 (l) is hereby replaced in its entirety with the following:

“Nema 4-12 native BACnet control panel with complete start-up and shut down sequence for remote operation.”

- Section 26 11 16 – Paragraph 2.2.4.1 (a) is hereby replaced in its entirety with the following:

“Design: Provide meter designed for use on a 3-phase, 4-wire, 4160/2400 volt system with 3 current transformers. Include necessary KYZ pulse initiation hardware for Energy Monitoring and Control System (EMCS) as specified in Section 23 09 23.13 20 BACnet DIRECT DIGITAL

CONTROL FOR HVAC.”

- Section 26 23 00 – Switchboards: Replace the first paragraph of section 2.2.4.2 and the sub-paragraph (a) with the following: “Provide a switchboard style electronic programmable watthour meter, semi-drawout, semi-flush mounted, as indicated. Meter shall either be programmed at the factory or shall be programmed in the field. When field programming is performed, turn field programming device over to the Contracting Officer at completion of project. Meter shall be coordinated to system requirements and conform to IEEE C12.16.

a. Design: Provide meter designed for use on a 3-phase, 4-wire, 208Y/120 volt system with 3 current transformers. Include necessary KYZ pulse initiation hardware for Energy Monitoring and Control System (EMCS) as specified in the designated specification for direct digital control for HVAC and other building control systems. Refer to Division 23 for more specific details.”

BIDDER’S QUESTIONS AND GOVERNMENT REPLY (FOR INFORMATIONAL PURPOSES

ONLY)

1. Please inform of the shipping rates for transports between Denmark and Thule AB.

Response: The Rates will be provided in future Amendment.

2. Materials and Norms: Can we use European norms for equipment and materials equal to the ASTM norms in the Specification?

Response: Generally yes; however, it is not possible to definitively provide an absolute answer without proper Review and Approval of Shop Drawings for the system or product.

3. In section no. 22.10.00 part no. 1.1 it is described that polypropylene pipe shall be used in the building.

However in section 22.00.00 Table no. II this is not prescribed. Please advise which type of pipe shall be used and where this shall be used.

Response: Specification Section 22 10 00 shall be deleted in its entirety by this amendment.

Polypropylene (PP) plastic piping shall not be used.

(End of Summary of Changes)