SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 72 PAGES
FY13 Dormitory (48 Person), Thule AB, Greenland
01 32 01.00 18 G ROInitial Project Schedule G ROPreliminary Project Schedule G ROPeriodic Project Schedule G RONarrative Report
01 32 01.00 18 SD-07 Certificates Qualifications Statement
01 35 26 SD-01 Preconstruction Submittals
1.6 G ROAccident Prevention Plan (APP)
1.7 G ROActivity Hazard Analysis (AHA)
1.6.1 G ROCrane Critical Lift Plan
1.5.1.2 G ROCrane Operators
SD-06 Test Reports 1.11Reports 1.11.1Accident Reports 1.11.3Monthly Exposure Reports 1.11.4Crane Reports
Gas Protection SD-07 Certificates
1.8Confined Space Entry Permit 1.8Hot work permit
01 45 04.00 18 SD-01 Preconstruction Submittals G ROContractor Quality Plan (CQC)
01 52 60.00 18 SD-01 Preconstruction Submittals G ROConstruction Indoor Air Quality
(IAQ) Management Plan SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 72 PAGES
01 52 60.00 18 Photographs G ROFiltration Media
SD-11 Closeout Submittals G ROConformance with IAQ
01 57 20.00 10 SD-01 Preconstruction Submittals
1.7 G ROEnvironmental Protection Plan
01 74 19 SD-01 Preconstruction Submittals
1.6 G ROWaste Management Plan
SD-11 Closeout Submittals 1.7Records
01 78 00.00 18 SD-03 Product Data G ROAs-Built Record of Equipment and Materials Warranty Management Plan Warranty Tags Final Cleaning Spare Parts Data
SD-08 Manufacturer’s Instructions Preventative Maintenance Condition Monitoring (Predictive Testing) Inspection Posted Instructions
SD-10 Operation and Maintenance Data
G ROOperation and Maintenance Manuals
SD-11 Closeout Submittals G RORecord Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 72 PAGES
01 78 00.00 18 G ROCertification of EPA Designated Items
G ROInterim Form DD1354 G ROChecklist for Form DD135 G RONAVFAC Sustainable & Energy
Data Record Card 03 20 00.00 10 SD-02 Shop Drawings
3.1 G ROReinforcement
SD-03 Product Data Welding
SD-07 Certificates 2.3Reinforcing Steel
03 30 00 SD-02 Shop Drawings 1.6.1.1Fabrication Drawings 1.6.1.2Formwork 1.6.1.2Formwork
1.6.1.3 G ROReinforcing steel
SD-03 Product Data 2.4.6Materials for curing concrete 2.4.9Joint sealants 2.4.8Joint filler 2.1.2Plastic Forms 2.1.3Carton Forms 2.4.3.2Recycled Aggregate Materials 2.4.1Cement 2.4.1.3Portland Cement
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 4 OF 72 PAGES
03 30 00 2.3.2Ready-Mix Concrete 2.6Bonding Materials 2.7Floor Finish Materials 2.3.3Concrete Curing Materials 2.5Reinforcement 1.6.1.1Reinforcement Materials 2.7.1Liquid Chemical Floor Hardener 2.4.10Epoxy bonding compound
Waterstops 2.1.1Wood Forms 1.8.1Local/Regional Materials 2.4.11Biodegradable Form Release
Agent SD-05 Design Data
2.3.1 G ROmix design
SD-06 Test Reports
1.6.3.1 G ROConcrete mix design
1.6.3.2Fly ash 1.6.3.2Pozzolan 1.6.3.3Ground granulated blast-furnace slag Aggregates
3.9.2.1Tolerance report 3.11.2.3Compressive strength tests 3.11.2.5Unit weight of structural lightweight concrete
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 5 OF 72 PAGES
03 30 00 2.8.4Slump 2.8.1Air Entrainment
SD-08 Manufacturer’s Instructions 1.6.3.2Fly ash 1.6.3.3Ground granulated blast-furnace slag 1.10Welding Procedures 1.10Welding Procedures 2.5.7Steel Bar 1.10Welder Qualifications
03 40 00.00 10 SD-01 Preconstruction Submittals
1.4.1.2 G ROQuality Control Procedures
SD-02 Shop Drawings
1.2.1 G ROStandard Precast Units
1.2.2 G ROCustom-Made Precast Units
SD-03 Product Data
1.2.1 G ROStandard Precast Units
1.2.3 G ROProprietary Precast Units
3.1.3 G ROEmbedded Items
2.1.10 G ROAccessories
SD-05 Design Data
1.2.2 G RODesign Calculations
1.2.5.1 G ROConcrete Mix Proportions
SD-06 Test Reports
1.4.1.2 G ROTest Reports
SD-07 Certificates
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 6 OF 72 PAGES
03 40 00.00 10 1.4.1.2 G ROQuality Control Procedures 03 41 16 SD-02 Shop Drawings
1.3Fabrication Drawings 1.3Installation Drawings 2.1.1Precast Concrete Slabs
Cast-in-Place Curb Units SD-03 Product Data
2.1.1Precast Concrete Slabs Packaged Concrete Materials
2.5Absorption Cover 2.5Moisture-Retaining Cover
SD-05 Design Data 2.1.1Precast Concrete Slabs
SD-06 Test Reports 2.1.1Test Reports 2.1.1Strength Tests
SD-07 Certificates 2.1.1Precast Concrete Slabs
Clips 2.2Threaded Fasteners 2.3Cement Grout Joint Sealing
Materials Bituminous Joint Sealing Materials
SD-08 Manufacturer’s Instructions 2.1.1Installation Instructions
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 7 OF 72 PAGES
05 05 23 SD-03 Product Data
1.5 G ROWelding Procedure Qualifications
1.5.4Welder, Welding Operator, and
Tacker Qualification 1.5.5Inspector Qualification 1.5.1Previous Qualifications 1.5.2Pre-qualified Procedures
SD-06 Test Reports 3.2Quality Control
Quality Assurance 05 12 00 SD-02 Shop Drawings
1.5.2.1 G DOErection Plan
1.5.1 G DOFabrication drawings
SD-03 Product Data 2.4Shop primer
2.2.5 G DOLoad indicator bolts
SD-06 Test Reports 2.4Class B coating 2.2Bolts, nuts, and washers
SD-07 Certificates 2.1Steel 2.2Bolts, nuts, and washers 2.4Shop Primer 2.3.1Welding Electrodes and Rods 2.3.2Nonshrink Grout 2.5Galvanizing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 8 OF 72 PAGES
05 12 00 1.5.2.2Welding procedures and qualifications
05 21 19 SD-02 Shop Drawings
1.5.1 G ROSteel joist framing
SD-07 Certificates G ROSteel joist
05 30 00 SD-02 Shop Drawings
1.3.5 G ROFabrication Drawings
SD-03 Product Data
2.2 G ROAccessories
2.3.1 G RODeck Units
2.2.10 G ROMechanical Fasteners
SD-05 Design Data
2.3.1 G RODeck Units
2.2 G ROAccessories
SD-07 Certificates G ROWelding Procedures
1.3.4.1 G ROFire Safety
G ROQualification of Welders
2.3.1 G RODeck Units
2.2 G ROAccessories
1.3.4.2 G ROWind Storm Resistance
05 40 00 SD-02 Shop Drawings
1.6.1 G DOFraming Components
SD-03 Product Data 2.1studs,joists
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 9 OF 72 PAGES
05 40 00 SD-05 Design Data
1.6.2 G DOMetal framing calculations
SD-07 Certificates 1.4Load-bearing cold-formed metal framing 3.1.1Welds
05 50 13 SD-02 Shop Drawings G ROFloor gratings G ROGalvanized Steel Fence/Security
Grille SD-03 Product Data
2.3Access doors and panels Cover plates and frames
2.4Control-joint covers Galvanized Steel Fence/Security Grille
Expansion joint covers Floor gratings Structural steel door frames
SD-04 Samples Expansion joint covers
2.4Control-joint covers 05 50 14 SD-02 Shop Drawings
1.4.2 G RODetail Drawings
SD-03 Product Data
2.2.2.1 G ROWelding of Structural Steel
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 10 OF 72 PAGES
05 50 14 1.4.1 G ROWelding of Aluminum G ROStructural Steel Welding Repairs
2.1.1Materials Orders 2.1.2Materials List 2.1.3Shipping Bill
SD-06 Test Reports 2.3Tests, Inspections, and
Verifications SD-07 Certificates
1.4.1Qualification of Welders and Welding Operators
2.2.2.3 G ROApplication Qualification for Steel
Studs
1.4.1 G ROWelding of Aluminum
05 51 00 SD-02 Shop Drawings
2.1Iron and Steel Hardware 2.1Steel Shapes, Plates, Bars and
Strips 2.16Metal Stair System
SD-03 Product Data 2.2Structural Steel Plates, Shapes, and Bars 2.3Structural Steel Tubing 2.6Hot-Rolled Carbon Steel Sheets and Strips 2.5Cold Finished Steel Bars
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 11 OF 72 PAGES
05 51 00 2.4Hot-Rolled Carbon Steel Bars 2.7Cold-Rolled Carbon Steel Sheets 2.8Galvanized Carbon Steel Sheets 2.9Cold-Drawn Steel Tubing 2.10Gray Iron Castings 2.11Malleable Iron Castings 2.13Concrete Inserts 2.14Masonry Anchorage Devices 2.17Protective Coating 2.18Steel Pan Stairs
Steel Stairs Steel Stairs, Circular
SD-07 Certificates 1.3Welding Procedures 1.3Welder Qualification
SD-08 Manufacturer’s Instructions 2.2Structural Steel Plates, Shapes, and Bars 2.3Structural Steel Tubing 2.6Hot-Rolled Carbon Steel Sheets and Strips 2.5Cold Finished Steel Bars 2.4Hot-Rolled Carbon Steel Bars 2.7Cold-Rolled Carbon Steel Sheets 2.8Galvanized Carbon Steel Sheets 2.9Cold-Drawn Steel Tubing
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 12 OF 72 PAGES
05 51 00 2.10Gray Iron Castings 2.11Malleable Iron Castings 2.17Protective Coating 2.14Masonry Anchorage Devices
05 52 00 SD-02 Shop Drawings
1.2.1 G ROFabrication Drawings
2.1 G ROIron and Steel Hardware
3.1 G ROIron and Steel Hardware
2.1Steel Shapes, Plates, Bars and
Strips 3.1Steel Shapes, Plates, Bars and
Strips SD-03 Product Data
1.2.1 G ROStructural Steel Plates, Shapes, and Bars
2.3 G ROStructural Steel Plates, Shapes, and Bars
1.2.1 G ROStructural Steel Tubing
2.4 G ROStructural Steel Tubing
1.2.1 G ROCold-Finished Steel Bars
2.6 G ROCold-Finished Steel Bars
1.2.1 G ROHot-Rolled Carbon Steel Bars
2.5 G ROHot-Rolled Carbon Steel Bars
1.2.1 G ROCold-Drawn Steel Tubing
2.7 G ROCold-Drawn Steel Tubing
1.2.1 G ROConcrete Inserts
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 13 OF 72 PAGES
05 52 00 2.9 G ROConcrete Inserts
1.2.1 G ROMasonry Anchorage Devices
2.10 G ROMasonry Anchorage Devices
1.2.1 G ROProtective Coating
2.12 G ROProtective Coating
1.2.1 G ROSteel Railings and Handrails
2.13 G ROSteel Railings and Handrails
1.2.1 G ROAnchorage and Fastening
Systems SD-07 Certificates
1.4.1 G ROWelding Procedures
1.4.2 G ROWelder Qualification
SD-08 Manufacturer’s Instructions
3.1 G ROInstallation Instructions
06 10 00 SD-03 Product Data Adhesives
SD-05 Design Data
1.9.2 G ROModifications of structural
members SD-06 Test Reports
1.4.3Preservative-treated SD-07 Certificates
1.11.2Forest Stewardship Council (FSC) Certification
1.9.3Certificates of grade 1.7Preservative treatment
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 14 OF 72 PAGES
06 10 00 SD-10 Operation and Maintenance Data
1.4.6Plastic 3.2Take-back program
SD-11 Closeout Submittals Local/Regional Materials Adhesives
1.11.1Certified Wood 1.11.2Certified Wood
06 20 00 SD-02 Shop Drawings 1.3Detail Drawings
SD-03 Product Data Wood
SD-04 Samples Moldings
2.2Fascias and Trim SD-07 Certificates
1.4Certificates of grade 1.4Certificates of compliance
06 61 16 SD-02 Shop Drawings
1.4.2 G RODetail Drawings
3.1 G ROInstallation
SD-03 Product Data 2.1Solid polymer material 1.4.1Qualifications 2.3Fabrications
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 15 OF 72 PAGES
06 61 16 1.4.3Certification SD-04 Samples
2.1 G ROMaterial
2.3.6 G ROCounter and Vanity Tops
SD-06 Test Reports 2.1Solid polymer material
SD-07 Certificates 2.3Fabrications 1.4.1Qualifications
SD-10 Operation and Maintenance Data
3.2Clean-up 07 21 16 SD-03 Product Data
2.1Blanket insulation Sill sealer insulation
2.3Vapor retarder 2.4Pressure sensitive tape 2.5Accessories 1.3Certification
SD-08 Manufacturer’s Instructions 3.3.1Insulation
07 27 00.45 10 SD-03 Product Data
3.3 G DOBuilding Air Tightness Test
3.4.1 G DOThermography Test Procedures
SD-06 Test Reports 1.4.3Test Report
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 16 OF 72 PAGES
07 27 00.45 10 3.3Building Air Tightness Test 3.4.2Thermography Test Report
SD-07 Certificates 1.6Air Barrier Inspector 1.5Building Air Tightness Test
Technician 07 41 13 SD-02 Shop Drawings
1.4.5 G RORoofing Panels
1.4.5 G ROFlashing and Accessories
SD-03 Product Data
2.1 G RORoof panels
1.4.5 G ROFactory-Applied Color Finish
2.4 G ROAccessories
1.4.5 G ROFasteners
1.4.5 G ROPressure Sensitive Tape
2.7 G ROUnderlayments
2.8 G ROGaskets and Sealing/Insulating
Compounds LEED Submittals Credit MR 4:
Product data indicating the following:
G ROa. Percentage by weight of post-consumer and pre-consumer recycled content
G ROb. Total weight of products provided
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 17 OF 72 PAGES
07 41 13 G ROc. Include statement indicating costs for each product having recycled content
SD-04 Samples
2.1 G RORoof Panels
1.4.5 G ROFactory-applied Color Finish
2.4 G ROAccessories
1.4.5 G ROFasteners
1.4.5 G ROGaskets and Sealant/Insulating
Compounds SD-05 Design Data
1.2.1.2 G ROWind Uplift Resistance
SD-06 Test Reports
1.2.1.1Leakage Test Report 1.2.1.2Wind Uplift Test Report
Fire Rating Test Report 2.2Factory Finish and Color
Performance Requirements SD-07 Certificates
2.1 G RORoof Panels
1.4.1 G ROQualification of Manufacturer
1.4.2 G ROQualification of Applicator
SD-08 Manufacturer’s Instructions
G ROINSULATION
1.4.5 G ROINSTALLATION MANUAL
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 18 OF 72 PAGES
07 41 13 SD-09 Manufacturer’s Field Reports
3.9.1Manufacturer's Field Inspection Reports
SD-11 Closeout Submittals 1.8Warranties 3.10Information Card 3.11Date Of Installation Wall-Mounted
Placard 07 41 63 SD-01 Preconstruction Submittals
1.5.1 G ROQualification of Manufacturer
1.5.3 G ROQualification of Manufacturer
1.5.1 G ROQualification of Installer
1.5.1Qualifications for Welding
SD-02 Shop Drawings
1.5.1 G RORoofing Panels
1.5.1 G ROFlashing and Accessories
G ROGutter/Downspout Assembly SD-03 Product Data
G ROInsulation Roof Panel (structural)
1.5.1 G ROCoil Stock
1.5.1 G ROFactory Color Finish
1.5.1 G ROSub-girts and Formed Shapes
1.5.1 G ROClosure Materials
1.5.1 G ROInsulation
1.5.1 G ROPressure Sensitive Tape
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 19 OF 72 PAGES
07 41 63 1.5.1 G ROSealants and Caulking
1.5.1 G RORated Wall Assembly
1.5.1 G ROAccessories
SD-04 Samples
1.5.1 G ROCoil Stock
1.5.1 G RORoofing Panels
2.2.2 G ROFasteners
2.4.1 G ROMetal Closure Strips
1.5.1 G ROInsulation
1.5.1 G ROManufacturer s color charts and
chips SD-05 Design Data
1.5.1 G ROWind design analysis
1.5.1 G ROSeismic design analysis
SD-06 Test Reports
2.1.4 G ROtest reports
3.7.2 G ROLeakage Tests
1.5.1 G ROFire Rating Test Report
3.1 G ROCoatings and base metals of
metal roofing
1.5.1 G ROFactory Finish and Color
Performance Requirements
1.5.1 G ROWind Uplift Test Report
1.5.1 G ROSeismic Test Report
SD-07 Certificates
1.5.1 G ROCoil Stock
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 20 OF 72 PAGES
07 41 63 2.2.2 G ROFasteners
1.5.1 G ROGalvanizing Repair Paint
1.5.1 G ROEnamel Repair Paint
SD-08 Manufacturer’s Instructions
1.5.1 G ROInstallation of Roof panel
assemblies SD-11 Closeout Submittals
1.8 G ROWarranty
3.10 G ROInformation Form and Placard
3.9.1 G ROManufacturer's field inspection
reports
1.5.1 G ROInstructions
1.5.1 G ROMaterial Safety Data Sheets
3.12 G RODate Of Installation Wall-Mounted
Placard
1.8.1 G RO20 year 'No-Dollar-Limit' warranty
for labor and materials 07 42 13 SD-01 Preconstruction Submittals
1.5.3 G ROQualification of Manufacturer
1.5.4 G ROQualification of Installation
Contractor
1.5.4.1 G ROQualification of Welders
1.8 G ROWarranty
SD-02 Shop Drawings
1.5.1.1 G ROInstallation Drawings
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 21 OF 72 PAGES
07 42 13 Recycled Content;
2.3.1 G ROWall Panels
2.3.2Factory Color Finish 1.5.5Closure Materials 2.6.4.4Pressure Sensitive Tape 2.6.4.1Sealants and Caulking 1.5.3.1Galvanizing Repair Paint 1.5.3.1Enamel Repair Paint 2.8Aluminized Steel Repair Paint 1.5.5Accessories 2.6Accessories
SD-04 Samples
2.3.1 G ROWall Panels
1.5.3.1 G ROFasteners
2.6.3 G ROMetal Closure Strips
G ROColor chart SD-05 Design Data
1.5.1.2 G ROWind load design analysis
SD-06 Test Reports
3.7.2 G ROLeakage Tests
1.3.2 G ROWind Load Tests
2.3.2.2 G ROCoating
2.3.2.2 G ROChalking
1.3.2 G ROSeismic Tests
SD-07 Certificates
1.5.3.1 G ROCoil Stock
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 22 OF 72 PAGES
07 42 13 1.5.3.1 G ROFasteners
1.5.3.1 G ROGalvanizing Repair Paint
1.5.3.1 G ROEnamel Repair Paint
SD-08 Manufacturer’s Instructions
3.3 G ROInstallation
SD-09 Manufacturer’s Field Reports
3.8.1 G ROManufacturer's Field Reports
SD-11 Closeout Submittals
1.8 G ROWarranty
1.5.6 G ROMaintenance Instructions
1.8.120 year 'No Dollar Limit' warranty for labor and material 07 60 00 SD-02 Shop Drawings
3.1.22 G ROCovering on flat, sloped, or
curved surfaces
3.1.23 G ROExpansion joints
3.1.15 G ROGravel stops and fascias
3.1.11 G ROBase flashing
3.1.12 G ROCounterflashing
3.1.24 G ROFlashing at roof penetrations
3.1.13 G ROReglets
G ROScuppers
3.1.27 G ROCopings
3.1.16 G RODrip edge
3.1.19Conductor heads
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 23 OF 72 PAGES
07 60 00 3.1.20 G ROOpen valley flashing
3.1.21 G ROEave flashing
SD-11 Closeout Submittals 3.5Quality Control Plan
07 84 00 SD-02 Shop Drawings 2.1Firestopping Materials
SD-07 Certificates 1.4.2Manufacturer's Technical
Representative 2.1Firestopping Materials 1.4.1Installer Qualifications 3.3Inspection
07 92 00 SD-03 Product Data 2.1Sealants 2.2Primers 2.3Bond breakers 2.4Backstops
SD-07 Certificates 3.3.6Sealant
08 11 13 SD-02 Shop Drawings
2.1 G RODoors
2.1 G RODoors
2.6 G ROFrames
2.6 G ROFrames
2.4Accessories 2.8Weatherstripping
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 24 OF 72 PAGES
08 11 13 G RODoor Frames SD-03 Product Data
2.1 G RODoors
2.6 G ROFrames
2.4Accessories 2.8Weatherstripping
SD-04 Samples
2.10.4 G ROFactory-applied enamel finish
08 14 00 SD-02 Shop Drawings
2.1 G RODoors
SD-03 Product Data
2.1 G RODoors
2.2Accessories 2.3.7Water-resistant sealer 1.5warranty
2.1.2 G ROSound transmission class rating
G ROFire resistance rating 1.3Certification
SD-04 Samples 2.1Doors
2.3.6.3 G RODoor finish colors
SD-06 Test Reports 2.4Split resistance 2.4Cycle-slam 2.4Hinge loading resistance
08 53 00 SD-02 Shop Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 25 OF 72 PAGES
08 53 00 2.2.1 G ROWindows
2.2.1 G ROWindows
SD-03 Product Data
2.2.1 G ROWindows
2.4.8Fasteners 2.4.4Hardware 2.4.6Screens 2.4.5Weatherstripping 2.4.9Accessories 2.2.5Adhesives
Environmental Data SD-04 Samples
2.2.1 G ROWindows
SD-06 Test Reports
2.2.1 G ROWindows
SD-07 Certificates
2.2.1Windows SD-10 Operation and Maintenance Data
2.2.1 G ROWindows
1.6.1Plastic Identification
08 71 00 SD-02 Shop Drawings
1.3 G ROHardware schedule
2.3.5Keying system
SD-03 Product Data
2.3 G ROHardware items
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 26 OF 72 PAGES
08 71 00 SD-08 Manufacturer’s Instructions 3.1Installation
SD-10 Operation and Maintenance Data
1.3 G ROHardware Schedule
SD-11 Closeout Submittals Key Bitting
08 81 00 SD-02 Shop Drawings Installation
SD-03 Product Data 1.6.1Insulating Glass 1.3Glazing Accessories
Environmental Data SD-08 Manufacturer’s Instructions
2.3Setting and sealing materials 3.2Glass setting
09 06 90 SD-04 Samples
2.2 G ROColor Schedule
09 22 00 SD-02 Shop Drawings
2.1 G ROMetal support systems
09 29 00 SD-03 Product Data Cementitious backer units Glass Mat Water-Resistant Gypsum Tile Backing Board
Water-Resistant Gypsum Backing Board
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 27 OF 72 PAGES
09 29 00 Glass Mat Covered or Reinforced Gypsum Sheathing
Glass Mat Covered or Reinforced Gypsum Sheathing Sealant
Impact Resistant Gypsum Board 2.1.6Accessories 1.3Certification 2.1.1Gypsum Board 2.1.4Adhesives 2.1.3Joint Treatment Materials
SD-07 Certificates
2.1 G ROAsbestos Free Materials
SD-08 Manufacturer’s Instructions 2.1Material Safety Data Sheets
SD-10 Operation and Maintenance Data
2.1Manufacturer maintenance instructions
Waste Management SD-11 Closeout Submittals
2.1.1Gypsum Board 2.1.4Adhesives
09 30 00 SD-02 Shop Drawings
1.4 G RODetail Drawings
SD-03 Product Data
2.1 G ROTile
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 28 OF 72 PAGES
09 30 00 2.1 G ROTile
2.2 G ROSetting-Bed
2.4 G ROMortar, Grout, and Adhesive
2.2.6Reinforcing Wire Fabric 1.2.2Certification
SD-04 Samples
2.1 G ROTile
2.1.3 G ROAccessories
G ROMarble Thresholds
2.4 G ROGrout
SD-06 Test Reports 3.7Testing
SD-07 Certificates
2.1 G ROTile
2.4 G ROMortar, Grout, and Adhesive
SD-11 Closeout Submittals 2.1Tile 2.2.6Reinforcing Wire Fabric 2.4Adhesives
09 51 00 SD-02 Shop Drawings 1.2Approved Detail Drawings
SD-03 Product Data 1.2.1Acoustical Ceiling Systems 1.4Certification
SD-04 Samples 2.1Acoustical Units
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 29 OF 72 PAGES
09 51 00 2.1.1Acoustic Ceiling Tiles SD-06 Test Reports
1.2.1Fire Resistive Ceilings 1.2.2Ceiling Attenuation Class and
Test SD-07 Certificates
2.1Acoustical Units 2.1.1Acoustic Ceiling Tiles
09 65 00 SD-02 Shop Drawings
2.9 G ROResilient Flooring and
Accessories SD-03 Product Data
2.9 G ROResilient Flooring and
Accessories
2.5Adhesives Vinyl Composition Tile Sheet Vinyl Flooring Rubber Tile Rubber Sheet Flooring Solid Vinyl Tile Cement-Fiber Board
2.2Wall Base 2.3Stair Treads, Risers and
Stringers Environmental Data Sheet Linoleum
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 30 OF 72 PAGES
09 65 00 Linoleum Tile Cork
1.4Certification SD-04 Samples
2.9 G ROResilient Flooring and
Accessories
SD-06 Test Reports
3.3 G ROMoisture, Alkalinity and Bond
Tests SD-08 Manufacturer’s Instructions
3.2Surface Preparation 3.1Installation
SD-10 Operation and Maintenance Data
2.9 G ROResilient Flooring and
Accessories
SD-11 Closeout Submittals 2.9Resilient Flooring and
Accessories 2.5Adhesives
Sheet Linoleum Linoleum Tile Cork
09 68 00 SD-02 Shop Drawings 3.4Installation 2.5Moldings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 31 OF 72 PAGES
09 68 00 SD-03 Product Data 2.1Carpet 2.3Carpet Cushion 2.5Moldings 3.1Surface Preparation 3.4Installation
1.4 G RORegulatory Requirements
2.1.1Physical Characteristics
SD-04 Samples 2.1Carpet 2.5Moldings
SD-06 Test Reports
3.2 G ROMoisture and Alkalinity Tests
SD-07 Certificates 2.1Carpet
SD-10 Operation and Maintenance Data
2.1Carpet 3.5Cleaning and Protection
Maintenance Service SD-11 Closeout Submittals
2.1Carpet 2.4Adhesives and Concrete Primer
09 72 00 SD-03 Product Data
2.1 G ROWall Coverings and Accessories
2.3Primer and Adhesive
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 32 OF 72 PAGES
09 72 00 Vinyl Wall Covering 1.3Certification
SD-04 Samples
2.1 G ROWall Coverings and Accessories
2.1 G ROWall Coverings
SD-07 Certificates 2.1Wall Coverings and Accessories
SD-08 Manufacturer’s Instructions 2.1Wall Coverings and Accessories
SD-10 Operation and Maintenance Data
G ROVinyl Wall Covering 09 90 00 SD-02 Shop Drawings
Piping identification stencil
SD-03 Product Data 1.4.4Certification
Environmental Data 2.1Materials
2.1 G ROCoating
2.1Manufacturer's Technical Data
Sheets Sealant
SD-04 Samples
1.10 G ROColor
1.4.2 G ROTextured Wall Coating System
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 33 OF 72 PAGES
09 90 00 1.4.3 G ROSample Textured Wall Coating System Mock-Up
SD-07 Certificates 1.3Applicator's qualifications
1.4.1.2 G ROQualification Testing
SD-08 Manufacturer’s Instructions Application instructions
3.4.2Mixing 1.7.2Manufacturer's Material Safety
Data Sheets SD-10 Operation and Maintenance Data
G ROCoatings 10 14 01 SD-02 Shop Drawings
3.1 G ROApproved Detail Drawings
SD-03 Product Data
3.1Installation
1.2 G ROExterior Signage
Wind Load Requirements SD-04 Samples
1.2 G ROExterior Signage
SD-10 Operation and Maintenance Data
3.1.2Protection and Cleaning 10 14 02 SD-02 Shop Drawings
1.2 G RODetail Drawings
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 34 OF 72 PAGES
10 14 02 SD-03 Product Data
3.1 G ROInstallation
SD-04 Samples 1.2Interior Signage
Software SD-10 Operation and Maintenance Data
3.1Approved Manufacturer's Instructions
3.1.2Protection and Cleaning 10 26 13 SD-02 Shop Drawings
2.2 G ROCorner Guards
G ROWall Guards (Bumper Guards) G RODoor Protectors G ROWall Covering/Panels
SD-03 Product Data 1.3Certification
SD-04 Samples 2.4Finish
SD-06 Test Reports 2.2Corner Guards
Wall Guards (Bumper Guards) Door Protectors Wall Covering/Panels
SD-07 Certificates 2.2Corner Guards
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 35 OF 72 PAGES
10 26 13 Wall Guards (Bumper Guards) Door Protectors Wall Covering/Panels
10 28 13 SD-03 Product Data 2.1.2Finishes 2.2Accessory Items
SD-04 Samples 2.1.2Finishes 2.2Accessory Items
SD-07 Certificates 2.2Accessory Items
SD-10 Operation and Maintenance Data Electric Hand Dryer
10 44 16 SD-01 Preconstruction Submittals 2.1Manufacturer's Data
SD-02 Shop Drawings 2.1Fire Extinguishers 2.4Accessories 2.5Cabinets
SD-03 Product Data 2.1Fire Extinguishers 2.4Accessories 2.5Cabinets 3.2.1Replacement Parts
SD-04 Samples
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 36 OF 72 PAGES
10 44 16 2.1Fire Extinguisher 2.1Cabinet
Wall Brackets 2.4Accessories
SD-07 Certificates 2.1Fire Extinguishers 2.1Manufacturer's Warranty with
Inspection Tag 10 51 13 SD-02 Shop Drawings
2.1 G DOTypes
1.4 G DOLocation
3.1Installation 3.2Numbering system
SD-03 Product Data 2.2Material
Locking Devices Lock Control Chart Handles Finish
2.3components 3.1Assembly
SD-04 Samples
1.5.1 G DOColor chips
11 13 13 SD-02 Shop Drawings
1.4.1 G RODetail Drawings
SD-03 Product Data
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 37 OF 72 PAGES
11 13 13 G RODock Bumpers SD-04 Samples
2.2Fastening Materials 2.2Angles 2.2Rods 2.2Fastening Hardware
Dock Bumpers 2.2Rubber 2.2Rubberized Fabric
SD-07 Certificates 2.2Fastening Materials 2.2Rubberized Fabric 2.2Steel Angles 2.2Hardware Items
SD-11 Closeout Submittals
1.4.2 G RORecord Drawings
12 22 00 SD-02 Shop Drawings
1.3 G RODrawings
SD-03 Product Data 1.5Certification
SD-04 Samples
2.1.1.1 G RODrapery fabric
G ROMotor and Controller 3.2Finished drapery
SD-06 Test Reports 2.1.1.3Flame resistance
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 38 OF 72 PAGES
12 22 00 SD-08 Manufacturer’s Instructions 2.1.4Drapery hardware
Motor and Controller 2.2.1fabrication
SD-10 Operation and Maintenance Data
1.4 G RODrapery system
12 24 13 SD-03 Product Data
2.1Window Shades 1.4.5Certification
SD-04 Samples 2.1Window Shades
SD-06 Test Reports 2.1Window Shades
SD-08 Manufacturer’s Instructions 2.1Window Shades
SD-10 Operation and Maintenance Data
2.1Window Shades SD-11 Closeout Submittals Recycled Content (LEED)
1.4.4Shade Cloth (LEED) 13 48 00.00 10 SD-02 Shop Drawings
3.1Coupling and Bracing 3.3Flexible Couplings or Joints 1.3Equipment Requirements
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 39 OF 72 PAGES
13 48 00.00 10 1.2.4Contractor Designed Bracing
G RO;
SD-03 Product Data
3.1 G ROCoupling and Bracing
1.3 G ROEquipment Requirements
1.2.4 G ROContractor Designed Bracing
SD-07 Certificates 2.2Flexible Ball Joints
13 48 00 SD-02 Shop Drawings
3.1 G ROBracing
3.4 G ROResilient Vibration Isolation
Devices
1.3 G ROEquipment Requirements
SD-03 Product Data
3.1 G ROBracing
1.3 G ROEquipment Requirements
SD-06 Test Reports
3.3 G ROAnchor Bolts
21 13 13.00 10 SD-02 Shop Drawings 1.4.3Shop Drawings;
3.9As-Built Drawings
SD-03 Product Data 1.4.1Fire Protection Related
Submittals
2.3 G ROMaterials and Equipment
1.6Spare Parts
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 40 OF 72 PAGES
21 13 13.00 10 3.8 G ROPreliminary Tests
3.9 G ROFinal Acceptance Test
3.10 G ROOnsite Training
1.4.1 G ROFire Protection Specialist
1.4.2Sprinkler System Installer
SD-05 Design Data 1.4.3Sway Bracing 1.2.1.3Hydraulic Calculations
SD-06 Test Reports
3.8 G ROPreliminary Test Report
3.9 G ROFinal Acceptance Test Report
SD-07 Certificates 3.3Inspection by Fire Protection
Specialist SD-10 Operation and Maintenance Data
3.10Operating and Maintenance Manuals
22 00 00 SD-02 Shop Drawings
3.7.1 G ROPlumbing System
SD-03 Product Data 2.4Fixtures 2.4.2Flush tank water closets
Wall hung lavatories 2.4.4Kitchen sinks
Plastic bathtubs
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 41 OF 72 PAGES
22 00 00 2.9 G ROPumps
3.7.1.1 G DOBackflow prevention assemblies
2.6.2 G ROShower Faucets
3.7.1Plumbing System
SD-06 Test Reports 3.7Tests, Flushing and Disinfection
3.7.1.1 G ROTest of Backflow Prevention
Assemblies SD-07 Certificates
1.3Materials and Equipment 2.1.1Bolts
SD-10 Operation and Maintenance Data
3.7.1 G ROPlumbing System
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 42 OF 72 PAGES
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 43 OF 72 PAGES
23 00 00 SD-02 Shop Drawings
1.4.5 G RODetail Drawings
SD-03 Product Data 2.9.1.1Metallic Flexible Duct 2.9.1.2Insulated Nonmetallic Flexible
Duct Runouts 2.9.1.2Duct Connectors
2.9.2 G RODuct Access Doors
2.9.3Fire Dampers
2.9.4 G ROManual Balancing Dampers
2.9.5 G ROManual Balancing Dampers
Automatic Smoke-Fire Dampers Automatic Smoke Dampers
2.9.10Sound Attenuation Equipment 2.9.10Acoustical Duct Liner 2.9.11.1Diffusers 2.9.11.2Registers and Grilles
Louvers Air Vents, Penthouses, and Goosenecks
2.10.1.1Centrifugal Fans 2.10.1.2In-Line Centrifugal Fans 2.10.1.3Axial Flow Fans 2.10.1.4Panel Type Power Wall
Ventilators
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 44 OF 72 PAGES
23 00 00 2.10.1.5Centrifugal Type Power Wall Ventilators
2.10.1.6Centrifugal Type Power Roof Ventilators
Propeller Type Power Roof Ventilators
Air-Curtain Fans 2.10.1.7Ceiling Exhaust Fans
2.11 G ROAir Handling Units
G ROCabinet Unit Heaters & Unit Heaters
2.12 G ROEnergy Recovery Devices
1.4.6Test Procedures
1.2.1.2 G RODiagrams
SD-06 Test Reports
3.12 G ROPerformance Tests
3.10 G RODamper Acceptance Test
SD-07 Certificates 1.4.1Bolts 1.4.7Certification
SD-08 Manufacturer’s Instructions 3.2Manufacturer's Installation
Instructions 3.14.2Operation and Maintenance
Training
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P
A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 45 OF 72 PAGES
23 00 00 SD-10 Operation and Maintenance Data
3.14.1Operation and Maintenance Manuals
2.9.3 G ROFire Dampers
2.9.4 G ROManual Balancing Dampers
2.9.5 G ROManual Balancing Dampers
G ROAutomatic Smoke-Fire Dampers G ROAutomatic Smoke Dampers
2.10.1.1 G ROCentrifugal Fans
2.10.1.2 G ROIn-Line Centrifugal Fans
2.10.1.3 G ROAxial Flow Fans
2.10.1.4 G ROPanel Type Power Wall
Ventilators
2.10.1.5 G ROCentrifugal Type Power Wall
Ventilators
2.10.1.6 G ROCentrifugal Type Power Roof
Ventilators G ROPropeller Type Power Roof
Ventilators
2.10.1.7 G ROCeiling Exhaust Fans
2.11 G…