This abstract of bids summarizes three offers received in response to Solicitation Number W912DR21B0007 for maintenance and improvements to the Third High Reservoir in support of the Washington Aqueduct Division. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Baltimore and involves construction services to upgrade Buildings R-3-A and R-3-B, install a mixer system, and perimeter fencing. Offerors provided lump sum pricing for the base scope of work items 0001 through 0004. Total estimated base bid amounts ranged from $3,304,000 to $5,498,307, with the government estimate being $3,692,000. All offers included the required 20% bid bond and acknowledged Amendment 6 to the solicitation.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
4. ISSUING OFFICE Name and title of Certifying Official (Type) I CERTIFY that I have opened, read, and
USACE, BALTIMORE DISTRICT recorded on this abstract all offers Signature Date Signed 2 HOPKINS PLAZA received in response to this solicitation.
BALTIMORE, MD 21201 Contracting Officer: SHARON L.ALEXANDER
5. PROJECT TITLE
8. GOVERNMENT ESTIMATE
(Check A, B or C and complete D, E, and F.)
A. HIRED LABOR
B. REASONABLE CONTRACT B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) B. Bid Security (Type and Amount) (Without Profit)
X C. REASONABLE CONTRACT C. Amendment Acknowledged C. Amendment Acknowledged C. Amendment Acknowledged (Including Profit)
7A. 7B. 7C. D. E. F. E. F. E. F. E. F.
ITEM DESCRIPTION OF OFFERED ITEM EST. UNIT UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED UNIT ESTIMATED
No. QUANTITY PRICE AMOUNT IGE PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
All costs in connection with construction of improvements to the 3rd High Reservoir Improvements complete as shown on the drawings and specified, but exclusive of work covered under Bid items 0002, 0003, and 0004 below.
1 Job LS
$437,852.56
LS
$2,202,000.00
LS
$4,034,405.00
LS
$1,674,000.00
All costs in connection with Building R-3-A and Building R-3-B including the demolition & reconstruction of the buildings complete, HVAC, lighting, security, communication, sampling station, plumbing, electrical wiring and breakers, floor access ports and hatch covers as shown in drawings S-02, S-03, S-04, A-01, A- 02, A-03.
1 Job LS
$2,567,568.15
LS
$1,100,000.00
LS
$886,999.00
LS
$1,250,000.00 0003 All costs for the installation of a mixer system as specified in section 46 41 23 and shown in sheet M-02. 1 Job LS $436,284.37 LS $175,000.00 LS $293,878.00 LS $180,000.00
0004 All costs in connection with the installation of the perimeter fence. 1 Job LS $295,739.46 LS $215,000.00 LS $283,025.00 LS $200,000.00
TOTAL ESTIMATED BASE BID AMOUNT $3,737,444.54 $3,692,000.00 $5,498,307.00 $3,304,000.00
TOTAL ESTIMATED AMOUNT (BASE BID ITEMS) 3,737,444.54$ 3,692,000.00$ 5,498,307.00$ 3,304,000.00$
NSN 7540-01-150-0981 501419-101 NOTE: If more than two offers are received, continue on OF 1419A. Prescribed by GSA-FAR(48 CER)53.236-1 OPTIONAL FORM 1419 (11-88)
Bid Bond 20%
Yes
ABSTRACT OF OFFERS - CONSTRUCTION 2. DATE ISSUED1. SOLICITATION NUMBER
6. NUMBER OF AMENDMENTS ISSUED: 6 (SIX)
Yes
Bid Bond 20%
29-Mar-21W912DR-21-B-0007
3RD High Reservior in support of Washington Aqueduct Division Washington, D.C.
No. 1
9. OFFERS
PAGE
9. OFFERS
No. 3
NORAIR Engineering Corp 337 Brightseat Road, Ste 200 Landover, MD 20785
3. DATE OPENED
25-Mar-21
Yes
No. 2
Maverick Construction 401 Greenwood Creek Lane Grasonville, MD
21638
Bid Bond 20%
MIG GOV, LLC 545 S.
Birdneck Road Ste 202H Virginia Beach, VA 23451
| 2021-03-29T09:30:02-0400 | |
| ALEXANDER.SHARON.LAGENIECE.1229366145 |
File details come from the government source that posted it. Updated .