W912DR18R0021_AMD04_Final PWS_Amended Rev 1_3.12.20.pdf
PDF 1 MB Posted
- Solicitation number
- W912DR18R0021
About this file
This performance work statement outlines the requirements for decommissioning and disposal activities at the SM-1 Reactor Facility located at Fort Belvoir, Virginia. The work includes planning, engineering, demolition, and support services to decommission the deactivated SM-1 Nuclear Power Plant and related facilities. Key requirements include preparing required plans and reports; decommissioning, removing, and disposing of materials in accordance with permits and regulations; performing post-decommissioning radiological surveys; and coordinating with the Army and other regulatory agencies. The performance period is 60 months with work broken into elements such as project management, site preparation, building demolition, soil remediation, and reporting. Products and services must meet standards specified in documents provided by the Army including characterization reports, decommissioning plans, and environmental assessments.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DECOMMISSIONING AND DISPOSAL ACTIVITIES FOR THE
SM-1 REACTOR FACILITY LOCATED AT FORT BELVOIR, VA
FINAL PERFORMANCE WORK STATEMENT – AMENDED Rev 1 Amendments are noted in bold, italics [RFP Amendment 0004]
March 12, 2020
AMENDED, Rev 1 FINAL - Decommissioning and Disposal PWS for the SM-1Reactor Facility March 12, 2020
Page | 1
DECOMMISSIONING AND DISPOSAL ACTIVITIES FOR THE
SM-1 REACTOR FACILITY LOCATED AT FORT BELVOIR, VA
PERFORMANCE WORK STATEMENT
1.0 INTRODUCTION
The Department of the Army (DA) is authorized to build and operate nuclear reactors under Section 91.b. of the Atomic Energy Act of 1954. Section 91.b authorizes DOD to procure and utilize special nuclear material in the interest of national defense and to acquire utilization facilities, i.e., reactors for military purposes. Section 110.b of the Atomic Energy Act excludes such utilization facilities acquired by DOD from any of the licensing requirements of the Atomic Energy Act. As part of the Army Reactor Program, the United States Army Corps of Engineers (USACE) is responsible for nuclear reactor engineering and design, reactor construction, and decommissioning design and implementation.
2.0 GENERAL BACKGROUND
The SM-1 Deactivated Nuclear Power Plant is located on the western shore of the Potomac River within the boundaries of Fort Belvoir in Fairfax County, Virginia. It is approximately 17 miles south by southwest of the center of Washington D.C. Topographic and aerial maps showing the SM-1 site and surrounding areas are shown in Figure 1 (USGS 1983) and Figure 2 (GX 1994). These figures also show the area where the Sturgis (MH-1A) was berthed during decommissioning.
Figure 1: SM-1 and Surrounding Area Topographic Map (USGS)
Page | 2
Figure 2: SM-1 and Surrounding Area Aerial Photo (GX, 1994)
The construction of SM-1 at Fort Belvoir was completed in 1957, and it achieved its first criticality in April 1957. The SM-1 was a single-loop 10 megawatt-thermal (MWt) pressurized water reactor delivering a net 1,750 kilowatts of electrical power (KWe). It was the first nuclear power reactor to provide sustained electricity to a commercial power grid in the United States. The SM-1 Reactor operated from April 1957 to March 1973. Ft. Belvoir was home to the U.S. Army Engineer Reactors Group (USAERG) and the SM-1 was used for training the multi-service crews that would operate the various plants in the Program. The reactor was stationary with a medium power range (between 1000 and 10,000 KWe).
Deactivation was performed on the SM-1 Reactor in 1973-1974 in accordance with the SM-1 Decommissioning and Conversion Plan as approved by the Army Reactor Systems Health and Safety Review Committee (ARCHS). This consisted of removal of the nuclear fuel, minor decontamination, shipment of necessary radioactive waste, sealing the pressure vessel, and installing appropriate warning signs and monitoring devices.
After the completion of the facility deactivation and conversion, a third party radiological survey by the U. S. Army Environmental Hygiene Agency verified that known areas of radioactive contamination had been decontaminated to acceptable levels (based on the standards at the time of decommissioning) or were properly controlled. The Army Reactor Systems Health and Safety Review Committee (ARCHS) approved SM-1 Post-Decommissioning Environmental Monitoring Plan has been initiated to provide on-going surveillance of the decommissioned facility.
Additionally, in October of 1996, the U. S. Army Center for Health Promotion and Preventive Medicine (USACHPPM) took extensive surveys of the SM-1 and surrounding environment to determine the radiological status of the facility at that time.
Page | 3
2.1 PRIOR STUDIES
The decommissioning strategy that was developed in the 1970's recommended that the deactivated reactors be placed into a safe storage mode that would allow the shorter-lived radionuclides to decay.
It was expected that delaying decommissioning would reduce radioactive waste volumes and worker exposures. However, preliminary studies indicated that the levels of contamination present within the reactor building would not be reduced by decay sufficiently to allow for release of the facilities without significant decontamination being performed. Additionally, concern regarding the increasing cost and decreasing availability of radioactive waste disposal led the Army Reactor Office (ARO) to recommend that an assessment be performed of the SM-1 reactor to allow for a more accurate decommissioning cost estimate to be developed which addresses projected changes in disposal options.
USACE developed a management plan for conducting an All Hazards Assessment (AHA), which contained provisions for four phases of work to be performed. Phase I included a Historical Records Review and Disposal Alternatives Investigation. Phase II, included performing a characterization survey and developing a decommissioning cost estimate. Phases III deal with decommissioning planning, design, and execution. Phase IV is reactor permit termination. The AHA process supplies information to support the decommissioning study process outlined in Army Regulation 50-7. This process was performed by USACE, at the direction of the Army Reactor Office, to better define decommissioning activity costs.
Phase I - Review SM-1 historical design, operations, decommissioning, and surveillance related documents in order to prepare: Data Quality Objectives for a hazards assessment/characterization survey of the SM-1 Reactor Facility; initial waste classification of large components based on an activation analysis to estimate radionuclide concentrations; and identify those areas of the SM-1 site that are impacted by residual radioactive contamination and those that may contain other hazardous materials (to include areas where the MH-1A may have been impacted due to defueling and decontamination activities at Fort Belvoir).
Phase II - Conduct radiological and non-radiological sampling and analysis, hazards assessment, disposal alternatives evaluation, and cost estimates for the decommissioning and disposal of the SM-1.
Phase III - Develop detailed plans and execute the selected approach for hazards reduction, facility decommissioning, and waste disposal options.
Phase IV - Terminate the nuclear reactor decommissioning permit.
The results of the USACHPPM surveys and other historical records were utilized to prepare a Historical Site Assessment (HSA) in 2005. Characterization surveys and the AHA were completed in 2010/2011 and reported in a 2013 Characterization Survey Report. Objectives of these activities were as follows:
Quantified the inventory and distribution of radionuclides present in impacted areas of the SM- 1 Reactor Facility as required for decommissioning alternative assessment and waste management planning.
Quantified the radiation fields and fixed/removable contamination from accessible surfaces, equipment and structures in impacted areas of the SM-1 Reactor Facility as required for decommissioning worker dose projections and waste management planning.
Confirmed the presence of hazardous or toxic substances that have the potential to significantly affect the decommissioning alternative assessment and waste management planning.
Completed an initial cost estimate to assist with planning purposes and funding requests associated with decommissioning.
Page | 4
Supplemental collection of specific information to address data gaps identified by the Characterization Survey Report review were completed and are presented as supplemental Technical Memorandums.
The Technical Memorandums for SM-1 will be included as appendices to the Decommissioning Plan.
Objectives for the planning efforts that will be completed by early 2020 include obtaining the necessary information to support the application for a decommissioning permit in accordance with Table 2-1 of AR 50-7 Army Reactor Program. The following information is needed to support the permit application:
Approved environmental impact statement or environmental assessment.
Historical site assessment.
Coordination documents with State Historical Preservation Office.
Compliance agreements/consent decrees, and so forth, that involve other regulators and stakeholders in the decommissioning.
Proposed classification of areas for cleanup.
Any applicable agreements between responsible commander and garrison organizations to be in place during decommissioning.
Safety and health framework, identifying how personnel and radiation safety will be managed.
Waste management and disposal plan.
Final decommissioning plan.
2.2 OBJECTIVES
For the purposes of this Performance Work Statement (PWS) the scope of services include the following activities related to the decommissioning and disposal of the SM-1 Deactivated Nuclear Power Plant. This includes byproduct materials produced as a result of SM-1 operations at locations where facility equipment or materials were utilized within Fort Belvoir, VA:
1) Prepare plans that will support the decommissioning of the SM-1 Reactor Facility in accordance with this PWS and the ARO Decommissioning Permit;
2) Decommission/dispose of materials in accordance with final plans, decommissioning permits, and relevant Federal and State requirements;
3) Perform and document the necessary post-decommissioning radiological surveys to demonstrate all affected areas of Fort Belvoir are suitable for unrestricted release; and
4) Adherence to U.S. Nuclear Regulatory Commission (NRC) and Army, as well as other relevant Federal/State permits, standards, and guidance.
To assist in meeting the objectives of the PWS, the Government is providing the following documents:
Historical Site Assessment, SM-1 Reactor Facility, Fort Belvoir, Virginia; May 2005 (includes SM-1 Reactor Vessel Activation Analysis as Appendix F) (Enclosure 1 and 2)
Gamma Walk-over Characterization Report, SM-1 Deactivated Nuclear Power Plant, Ft Belvoir, VA; December 2009 (Enclosure 3)
Final (Rev 1) Characterization Survey Report for the All Hazards Analysis of the SM-1 Reactor Facility, Fort Belvoir, Virginia; Feb 2013 (Enclosure 4)
Phase II and Phase III – Cost Estimate to Support the Alternative Analysis for the All Hazards Assessment of the SM-1 Reactor Facility at Fort Belvoir, April 2018.[Not for distribution, for
Page | 5 purposes of this procurement only; this document is procurement sensitive.] (Enclosure 5
– five files total)
Pre-Final SM-1 Decommissioning Plan for the SM-1 Reactor Facility, March 2020.
(Enclosure 6) [ This is an updated version of the previously provided document]
All associated NEPA documentation (i.e., Draft Final Environmental Assessment, FNSI, etc.) (Enclosure 7 – 5 files total) [ This is an updated version of the previously provided document]
Phase I Archeological Report for SM-1 Reactor Facility, U.S. Garrison Fort Belvoir, Fairfax County, VA, April 2016. (Enclosure 8)
TPP and meeting minutes (multiple TPPs). (Enclosure 9 – six files total) Final Value Engineering (VE) Study Report for the SM-1 Deactivated Nuclear Reactor Site
(Enclosure 10) Limited Set of as built drawings for SM-1 associated buildings, to include 3-D modeling
(Enclosure 11 – two files total) Enriched Uranium as a Soil Contaminant at the SM-1 Reactor Facility, dated December
2019 (Enclosure 12) [provided in amendment 0002] SM-1 Engineering Tech Memo, Rev 01, dated 14 April 2016 (Enclosure 13) [provided in amendment 0002] Evaluation of Field Activities – Geotechnical Investigation, dated March 2018 (Enclosure
14) [provided in amendment 0002] Evaluation of Field Activities – Lead Soil Sampling, dated April 2019 (Enclosure 15)
[provided in amendment 0002] PST IP1 Components Container (Enclosure 16) [provided in amendment 0002] Plutonium as a Soil Contaminant at the SM-1 Reactor Facility, dated December 2019
(Enclosure 17) [provided in amendment 0002] Rad Swipe Sampling Tech Memo with Attachments Draft 8-2-17 (Enclosure 18) [provided in amendment 0002] Secondary Systems Analysis with Attachments Final 6-20-16 (Enclosure 19) [provided in amendment 0002] SM-1 Army Power Package Reactor Design FOUO (Enclosure 20) [provided in amendment 0002] SM-1 Design Construction and Operation Report FOUO (Enclosure 21) [provided in amendment 0002] SM-1 Restricted Area Photo Walkthrough FOUO (Enclosure 22) [provided in amendment
0002] SM-1 DOPAA to Client 6-19-19 (Enclosure 23) [provided in amendment 0002] Sturgis Government Property Revised Expend and Non Expend Final 7-22-19 ( 2 Files)
(Enclosure 24) [provided in amendment 0002] Waste Transportation Assessment FOUO 12-11-18 (Enclosure 25) [provided in amendment
0002] SM-1 Waste Management Plan Pre-Final FOUO (Enclosure 26) [provided in amendment
0002] SM-1 Utility Drawings to USACE (Enclosure 27) [provided in amendment 0003] SM-1 Improvements 1964 (Enclosure 28) [provided in amendment 0003] SM-1 Limited As Builts Site Plans, Modifications, Support Facilities (Enclosure 29)
[provided in amendment 0003] SM-1 Limited As Builts 1 (Enclosure 30) [provided in amendment 0003]
Page | 6
SM-1 Limited As Builts 2 (Enclosure 31) [provided in amendment 0003] SM-1 Limited As Builts 3 (Enclosure 32) [provided in amendment 0003] SM-1 Limited As Builts 4 (Enclosure 33) [provided in amendment 0003] SM-1 Limited As Builts 5 (Enclosure 34) [provided in amendment 0003] SM-1 Limited As Builts 6 (Enclosure 35) [provided in amendment 0003] Technical Memorandum Assessment Of Solid Waste Management Unit (SWMU) N-07
Building 358, Fort Belvoir, VA, dated October 2019 (2 Files ) (Enclosure 36) [ new document being provided with this amendment 0004]
Memorandum Of Agreement Among The U.S. Army Corps Of Engineers – Baltimore District, The Virginia State Historic Preservation Office, U.S. Army Garrison Fort Belvoir And The Advisory Council On Historic Preservation Regarding The Decommissioning Of The Stationary Medium Power Plant Number 1 (Sm-1), Fort Belvoir, Fairfax County, Virginia, dated March 2020 (Enclosure 37) [ new document being provided with this amendment 0004]
Some of the Decommissioning Planning documents are still under development. The most current version of the documents are being provided with the amended Request for Proposal. Final versions will be provided as we progress with the solicitation, including the Decommissioning Permit.
The Government provided documents will be provided via DoD (Department of Defense) SAFE site https://safe.apps.mil/ or the ARL SAFE site https://safe.arl.army.mil/ approved file sharing site for USACE. The documents will be loaded to the site and you will receive an email notification from the site with instructions on how to access and download the documents. The documents will only be available for 7 days from the date of the Request for Proposal. All bidders will need to sign a Non- Disclosure Agreement prior to the release of any documents for bidding purposes. All documents provided by the Government must be protected from distribution and destroyed after the proposal process. (Please send the Contract Specialist email addresses for the points of contact to receive this information.)
The selected Contractor will execute the decommissioning and disposal activities in accordance with the selected alternative identified in the Environmental Assessment (EA) and in accordance with the Decommissioning Permit and Decommissioning Plan.
3.0 WORK STATEMENT
The Contractor shall conduct all activities in compliance with applicable federal, state, and local laws, regulations, and guidance. The Contractor shall comply with the provisions of the basic contract, this PWS, and other Government provided documentation.
The Government team will utilize Technical Direction (TD) letters to control the release of project funding for the duration of the contract. The Contractor will work with the Project Manager and COR to develop a draft of the TD letter and the Government will finalize the letter and authorize spending accordingly. Typically, the Government will authorize the funds needed to support the project efforts on a quarterly basis. This approach will be utilized by the team to ensure project funds are being properly executed.
Page | 7
The work breakdown structure (WBS) and Work Elements (WE) for this project is as follows:
WE 1 Project Management and Support Services
Project Management (PM for WE1 only) Work Plan
WE 1A - Travel and Per Diem WE 2 Site Preparation
Site Prep Engineering Obtain Required Permits Tree Removal Prep/Mob Trailer/Office Area Fence/Gate Modifications Construction Waste Storage Pad Establishment of Exterior Control Area Boundary and Radiation Control Points Remove Exterior ASTs Remove Exterior Electrical Equipment and Fence Waste T&D for WE 2 Bldg. 358 Sampling
WE 3 Mobilization Personnel Training Equipment and Material Services
WE 4 Bldg. 372 Disposition Infrastructure Upgrades Asbestos Abatement (including disposal) Unrestricted Area and HP MOD Room Materials and Equipment (M&E) Removal and Decontamination Restricted Area M&E Removal and Decontamination VC M&E Removal and Disposal Unrestricted & HP Mod Demolition Restricted area demolition Vapor Container (VC) Demolition Upper Site Soil Remediation Upper Site Restoration
WE 5 Other Structural Demolition Demolition Engineering Bldg. 350/399 Demolition Intake pier demolition Bldg. 349 demolition Lower site remediation/restoration
WE 6 Demobilization Demobilization Crew Travel Site office/equipment demobilization Utilities demobilization
WE 7 Reporting
Page | 8
3.1 Project Constraints:
The following are government required project constraints:
1) Decommissioning and reporting work must be completed by 30 September 2026.
2) Onsite work days are assumed to be Monday through Friday with a maximum of 10 hours per day. Work outside of the normal hours listed above may be authorized as needed to support specific project tasks. All work outside of the normal working hours and/or over 50 hours per week must be authorized by USACE at least 48 hours prior to the proposed additional hours.
3) Contractors will manage and utilize personnel dosimetry from the Army Dosimetry System (Redstone Arsenal).
4) The Government intends to award the following Work Elements under the Base contract. All items/task/subtasks associated with the following WE are Firm Fixed Price or Cost Reimbursable.
WE 1- Project Management and Work Plan Preparation (Section 3.2) – Firm Fixed Price WE 1A - Travel and Per Diem (Section 3.2) – Cost Reimbursable (no fee) WE 2 - Site Preparation (Section 3.3) – Firm Fixed Price WE 3 - Mobilization (Section 3.4) – Firm Fixed Price WE 6 - Demobilization (Section 3.7) – Firm Fixed Price WE 7 - Reporting (Section 3.8) – Firm Fixed Price
It is the intent of the Government to award the base contract plus CPIF subtask up to the funds available in FY20. Remaining CPIF WEs will be identified in the contract award as optional items to be exercised in the subsequent year of funding. As such, the Base contract may include some of the following subtasks from the following WE as Cost Plus Incentive Fee task items:
WE 4 subtasks – Cost Plus Incentive Fee:
Infrastructure Upgrades (Section 3.5.1) Asbestos Abatement (including disposal) (Section 3.5.2) Unrestricted Area and HP MOD Room M&E Removal and Decontamination (Section 3.5.3) Restricted Area M&E Removal and Decontamination (Section 3.5.4) Vessel Containment M&E Removal and Disposal (Section 3.5.5) Unrestricted & HP MOD Demolition (Section 3.5.6) Restricted Area Demolition (Section 3.5.7) Vessel Containment Demolition (Section 3.5.8) Soil Remediation Upper Site (Section 3.5.9) Upper site restoration (Section 3.5.10)
WE 5 subtasks - Cost Plus Incentive Fee:
Engineering Demo (Section 3.6.1) Building 350/399 (Lift Station) Demolition (Section 3.6.2) Intake Pier Demolition (Section 3.6.3) Building 349 (Warehouse) Demolition (Section 3.6.4) Lower Site Remediation (Section 3.6.5)
Page | 9
3.2 Project Management and Support Services for Work Plan Development (WE 1) (Firm Fixed Price):
The Contractor shall provide project management support as necessary to perform the activities detailed in WE 1. It is assumed that this task will provide the overall project management and support services for the preparation of the work plans. The Contractor shall provide technical, public relations, and management support to meetings required to fulfill the objectives of this WE. The Contractor shall prepare minutes of the review conferences, conference calls, and meetings conducted for this WE. The minutes for each meeting shall be prepared and submitted by email to USACE, initially in draft form for review and comment, and shall be finalized based on review comments received. The final minutes shall be submitted by email to each meeting attendee.
As part of the management plans for the project, planning documents must address administrative procedures to be followed throughout the project (to include but not limited to the following: control of government property, documentation of communications, project controls [scheduling, invoicing, earned value management, change management, risk management], periodic status reporting/monthly reports, and other planning documents required to implement the project). Additionally, a SharePoint site must be established by the Contractor to allow for team collaboration, document sharing and as a file repository for the project files during the implementation of the project. The site must be accessible by DoD computers, must be password controlled, and have the ability to store all project data (no issues with files sizes, files with “For Official Use Only” information, files with “Personally Identifiable Information” etc.).
3.2.1 Project Kick-Off Meeting
A kick-off meeting will be scheduled after award. The purpose of this meeting will be to answer questions and provide approach to the overall project and planned activities for SM-1. Assume one (1) 4-hour meeting with six (6) individuals from the contractor attending. Assume the meeting will be held in Baltimore, MD at the USACE District Office.
3.2.2 Progress/Review Conferences And Reports
Following receipt of review comments on a deliverable, the contractor shall prepare and distribute draft responses. A review conference will be held with USACE to discuss the comments and responses.
Based on the agreements reached during the review conferences, the contractor shall prepare and distribute a set of responses for the comments.
The contractor shall prepare and submit reports (format to be agreed upon after award) and monthly progress reports for the duration of the contract and submit to the Project Manager. The reports shall include details concerning the project management and fieldwork activities conducted, deliverables submitted, cost information/tracking, invoice status, communications initiated and received, and meetings attended. Additional information may be added by the parties after award and throughout implementation.
The contractor shall host at least one weekly overall project team progress meeting with USACE for the duration of the project. This will be done via conference call and/or on-site. The contractor will prepare the weekly agenda, with input from USACE, host the meeting and prepare all necessary minutes as described above. A management team meeting will also be implemented on a weekly basis as needed.
Page | 10
3.2.3 SharePoint Site
The contractor shall set up and maintain a project SharePoint site for all team members to utilize. All meeting minutes, correspondence, invoicing, project deliverables, and so forth share be stored on the project SharePoint site. The site will be maintained throughout the duration of the project then provided to the Government at the end of the project.
3.2.4 Public Meeting
The contractor shall prepare for and assist USACE in hosting up to four public meetings with community members to discuss the SM-1 Decommissioning and Disposal project at or near Fort Belvoir, VA. The contractor shall identify and contact community groups and advertising venues and shall secure a meeting location near the project location. The contractor shall assume a four hour meeting with four (4) professional staff in attendance at the meeting. The contractor shall also assist USACE with preparation of presentation materials, to include the compilation of a fact sheet summarizing the implementation process for the decommissioning/disposal effort. For this public meetings, a transcript will be required. The contractor shall document the discussions of the meeting, and prepare a meeting transcript that will be submitted to the Project Manager. Draft transcript shall be submitted within ten days after the meeting, and shall be revised within seven (7) days after the receipt of comments from USACE- Baltimore.
3.2.5 Work Plans
The Contractor shall prepare all management plans for the project. Planning documents must address administrative procedures to be followed throughout the project (to include but not limited to the following: control of government property, documentation of communications, project controls [scheduling, invoicing, earned value management, change management], periodic status reporting/monthly reports, and other planning documents required to implement the project). The Contractor shall prepare all required work plans necessary to support decommissioning activities as described in the permit and this PWS. Work plans will be required by the Decommissioning Plan and/or Permit (additional plans may be required):
Decommissioning Work Plan (an overarching plan describing how specific engineering plans will be developed to support the implementation of specific tasks)
Quality Assurance Project Plan Contractor Quality Control Plan Accident Prevention Plan o Site Health and Safety Plan o Air Monitoring Plan o Radiation Protection Plan o Lead Compliance Plan o Asbestos Hazard Control Plan o Critical Lift Plans o Emergency Response Plan
Hazardous Material Work Plan o Hazardous Material Abatement Plan
Environmental Monitoring Plan Material Categorization, Survey, and Release Plan Final Status Survey Plan
Page | 11
Waste Management Plan (site-specific) Waste Transportation and Disposal Plan
3.2.6 Security Plan: The plan shall sufficiently describe security protocols which conform to USACE requirements. A physical security plan will be developed in accordance with AR-190-13 and the Decommissioning Plan and the Decommissioning Permit. The minimum requirements of the security plan include:
Access and General Protection/Security Policy and Procedures. This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area. Contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.
iWATCH and/or CorpsWatch Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 15 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award and/or NLT 30 calendar days after the completion of training for new employees.
For Contracts that Require AT Awareness and OPSEC Training. All Contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training and Level I OPSEC Awareness training (for contracts that require OPSEC Training per AR530-1 Operations Security) within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The Contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the POC or to the contracting officer, if a POC is not assigned, within 5 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website:
http://jko.jten.mil. Level I OPSEC awareness training is available at the following website:
http://cdse.edu/catalog/elearning/GS130.html.
All Contractor personnel will be escorted in areas where they may be exposed to classified and/or sensitive materials. All contractor employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials. The contractor will coordinate with the COR and/or the facility security office for access when required. (Use when security clearances are not required, i.e. facility repair or construction).
NCIC and terrorist threat data base screening required. All contractor employees, including subcontractor employees who are not in possession of a current Common Access Card (CAC) will be vetted by the installation, facility local security office to determine fitness
Page | 12 and eligibility for access IAW DTM 09-012, paragraph 2.b(4) to include but not limited to an NCIC and Terrorist Database screening. The Contractor will ensure that the Government has sufficient biographical information to conduct said screening including, but not limited to the person's name, date of birth, and social security number.
Pre-screen candidates using E-Verify Program. The Contractor must pre-screen Candidates using the E-verify Program (http://www.dhs.gov/E-Verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award.
Access to the 300 Area is strictly controlled. The contractor’s key personnel will be issued permanent badges to the 300 Area (pending security approval based on a background check).
The remainder of the project team and crew will be issued weekly temporary badges for access to the project site.
Security of site: The 300 Area security staff will monitor the site for security purposes throughout the duration of the contract. The security perimeter roads must be maintained for their roving patrols. The security perimeter roads will be impacted by some of the project work;
these impacts must be coordinated with the Government team and the 300 Area staff. The perimeter security fence must be maintained at all times. If short sections of fence must be removed to implement key features of work, the perimeter fencing must be reestablished at the close of business everyday so that the site is secured.
Parking: On site parking at SM-1 will be very limited. Project parking will be limited to 50 vehicles and will be provided at the former location of Bldg. 361 in the 300 Area. Additional crew vehicles will need to park at the 300 Area Visitor’s Center or other designated location and then be shuttled to the site in passenger vans as needed.
WE 1A – Travel and Per diem (Cost Reimbursable)
All project related travel and per diem should be included with this WE. Travel and Per Diem will be a Cost Reimbursable CLIN. The contractor shall utilize methods to minimize project costs associated with travel (local trades/craft if possible, use/hire local staff, move staff vs. long term temporary duty, etc.). For any personnel on long term travel, the costs to the project shall not exceed 55% of the per diem rates authorized in the JTR. All travel assumptions to/from the site must be clearly outlined in the proposal costs, to include costs for personnel on long term travel to mobilize, demobilize and travel home throughout the project. The project will only allow the costs to travel home on a quarterly basis. Costs to travel home on a more frequent basis will not be applied to the project costs.
Calculate and present all travel associated with all work elements described in the PWS. A breakdown of the travel cost per WE should be provided for evaluation purposes. A cumulative total costs for travel shall be provided in the Price Schedule for WE 1A. Travel costs will be cost reimbursable. All travel costs will be billed under WE 1A.
3.3 Site Preparation (WE 2) (Firm Fixed Price):
The Contractor shall implement the Site preparation work at Fort Belvoir, VA in accordance with the approved work plans, Decommissioning Plan (DP), Decommissioning Permit, and any Ft Belvoir permits necessary to complete activities. The Contractor is reposible for obtaining any necessary permits, including but not limited to CAA, RCRA, TSCA, CWA, etc. All permitting efforts will be coordinated with USACE and Fort Belvoir staff. The Contractor shall provide all necessary equipment, personnel and engineering support in order to prepare the site for decommissioning and
Page | 13 disposal operations. Government Furnished Equipment (GFE) will be provided to the contractor to support the project. All GFE provided will be managed by the contractor as part of equipment management program. Site preparation may include the travel of management and labor staff, project-specific training, and acquisition and delivery of required equipment for DP tasks. The decommissioning contractor management staff will establish a site office, laydown areas, and waste storage areas in a location acceptable to the USACE Project Manager.
3.3.1 Site Prep Engineering
The Contractor shall provide Task-level engineering and planning required for all Site Preparation work as part of the decommissioning and disposal operations.
3.3.2 Tree Removal
As part of the site preparation, brush and trees in the upper and lower portions of the site will need to be removed. The initial tree removal will be nonintrusive and all stumps will remain until the project soils are addressed. The tree removal requires additional permitting and therefore may not necessarily take place at the same time as other site preparation activities. Per Ft. Belvoir requirements, clearing of trees larger than 3 inches in diameter at breast height would take place between September 15 and April 15 in accordance with Ft Belvoir and U.S. FWS policy regarding critical bat habitat. Approximately 30 or more trees (up to 36-inches in diameter) will need to be removed. The Contractor shall conduct field surveys to identify specific trees that require removal.
The Contractor shall assume that all tree and brush debris is removed from the site and that tree removal will not generate low-level radioactive waste (LLRW). Contractor should be advised that the site is subject to soil saturation during periods of substantial precipitation. This should be taken into account for scheduling and planning purposes during site preparation and throughout implementation.
3.3.3 Project Offices
The Contractor may establish a small office area of about 50 feet by 50 feet to be used as the SM-1 Site Office area for the duration of the project. This may require the Contractor to perform rough grading and site preparation for the placement of the temporary site office trailer(s) There is a small area outside of the fenced site area (adjacent to the entrance gate) that may be utilized for this small office area. There are utilities available for this area, to include, sewer, water, and electric.
The main project site office may be established at the former Building 361 location on Burbeck Road. Fort Belvoir and the 300 Area have cleared the area and and reserved it for use by the SM-1 project team. This location has utility capabilities available and stubbed up for immediate hookup.
It will accomidate up to 8 single wide trailers, parking for up to 50 vehicles, an area for the waste storage pad and additional space for laydown purposes.
3.3.4 Construct Waste Storage Pad
For bidding purposes, the Contractor shall assume the need to establish designated areas on the SM-1 reactor facility site in order to package and store industrial, radiological, hazardous, TSCA and RCRA waste. The Contractor shall be responsible for the construction of a concrete pad with an area up to 5,000 square foot for storing waste containers. The former Building 361 location has an area for the primary waste storage pad. If an additional pad area is needed, the Contractor can contruct it at the SM-1 site. The additional waste storage area may be inside the SM-1 perimeter fence or may be located near Ponton Basin. If the pad is constructed near Ponton Basin, additional security may be required.
3.3.5 Establish Exterior Controlled Area Boundary and Radiological Control Points
Page | 14
A Support Zone will be proposed and established to serve as a clean equipment staging area and administrative area. The support zone can be moved as the project progresses through the decommissioning. The Support Zone will include controlled access points/radiological control points into and from the Contamination Reduction Zone (CRZ). The CRZ is a buffer area between the Support Zone and the Radiological Controlled Area (RCA) which will include active decontamination and radioactive M&E removals. The CRZ will include personnel decontamination areas, areas to don and doff PPE, and areas for personnel to ‘frisk’ prior to exiting the CRZ. The CRZ may be used for placement of temporary exhaust ventilation fans and high efficiency particulate air (HEPA) filters and for staging trailers for the storage and donning of protection clothing.
3.3.6 Removal of Exterior ASTs
Site preparation will also include the removal of exterior interferences from around Building 372. The Distilled Water Tank (TK-2) and Service Water Tank (TK-3) should be removed from the southwest side of Building 372. These items are not considered contaminated, the assumption should be confirmed, and the tanks treated as non-radiological waste.
3.3.7 Remove Exterior Electrical Equipment, other interferences The removal of a few exterior interferences from around Building 372, including the electrical substation from the northwest corner of Building 372 is also included in the Site Preparation. These items are not considered contaminated and should be treated as non-radiological waste. These materials should be assessed to ensure there are no additional hazardous waste or toxic substance control act requirements for disposal.
3.3.8 Waste Transportation and Disposal (T&D) for WE 2
Waste generated from performing site preparation includes the two exterior tanks (TK-2 and TK-3) and the exterior substation equipment. These items are assumed to be free of radiological contamination (confirmation radiological surveys should be implemented) and other hazardous materials and available for local non-radiological disposal or recycling. No additional waste/debris from tree removal is assumed as part of the site preparation Waste T&D. None of these site preparation items are considered contaminated and will be managed as clean waste; however, radiation surveys and other requirements to meet disposal/recycle facility criteria will be required.
3.3.9 Building 358 Sampling
The contractor shall use the USACE-provided work plan, which was approved by VDEQ, to allow closeout of an underground storage tank (UST) for B358. This plan contains requirements for a minimum of six soil samples; samples will be collected from depth intervals of 0 to ½ foot below the bottom of the vaults and 2 to 2 ½ feet below the vault bottoms. USACE believes the top of the vault is located 5 ft below grade, and the vault bottom is located approximately 10 ft below grade.
The top of the vault is currently covered/partially covered with concrete structures (i.e. disability ramps). The samples collected shall be analyzed for metals (arsenic, barium, cadmium, chromium, lead, mercury, selenium, and silver), Volatile Organic Compounds and Semi-Volatile Organic Compounds.
The analytical results shall be evaluated to determine if a release of concern has occurred. A release of concern would consist of unacceptable concentrations of a hazardous waste or hazardous constituent as defined by federal, state, and local regulations. If results indicate that a release of concern has occurred, a detailed investigation shall be performed to determine the extent of impacted soil and whether groundwater has been impacted. Based on the detailed
Page | 15 investigation, a remedial action plan will be developed, if required, and implemented to mitigate environmental impacts.
A final closure report specific to the B358 USTs will be required to be developed by the contractor and approved by all stakeholders.
3.4 MOBILIZATION (WE 3) (Firm Fixed Price):
Initial mobilization of decommissioning contractor personnel may include the project-specific training, and acquisition and delivery of required equipment for the Decommissioning Plan (DP) tasks. The decommissioning contractor management staff will establish a site office, laydown areas, and waste storage areas in a location acceptable to the USACE Project Manager as indicated in WE 2 above.
Each individual performing decommissioning work, oversight, or supervision must attend site specific training in accordance with approved procedures. Safety training will be provided by the decommissioning contractor’s safety and radiological professionals. Additionally, all workers must attend a safety and securities briefing provided by USACE personnel and, if applicable, site owner/contractor personnel, regarding site-specific items.
Mobilization also includes delivery and setup of the field trailers, de-energizing the existing reactor power system, and installing new temporary power services. The contractor shall provide USACE staff with 800 square feet of office space to support up to six (6) USACE staff for the duration of the project. The USACE facilities shall include indoor restrooms, break area, and conference room.
This office space should be at the former Bldg. 361 location. It should be co-located with the office space for the contractor’s management team.
All facilities and services needed to implement the DP shall be in place prior to commencement of any DP Tasks.
3.4.1 Personnel
The PWS assumes 15 to 20 on-site contractor personnel for the entire duration of decommissioning.
The PWS also assumes increases and/or decreases in on-site contractor personnel depending on current DP tasks being executed.
3.4.2 Training
All personnel working on SM-1 conducting decommissioning activities are required to be trained in regard to the type and magnitude of the radiological, chemical, and physical hazards onsite. This training will be conducted by the decommissioning contractor personnel.
Project personnel who will work in radiological controlled areas are required to undergo Radiation Worker Training. Contractor Radiation Worker Training should include the following topics at a minimum:
Radioactivity and radioactive decay.
Characteristics of ionizing radiation.
Manmade radiation sources.
Effects of exposure to radiation.
Page | 16
Risks associated with occupational radiation exposures.
Special considerations with respect to exposure of women of reproductive age.
Dose-equivalent limits.
Modes of exposure (internal and external).
Dose-equivalent determinations.
Basic protective measures (time, distance, and shielding).
Specific procedures for maintaining exposures ALARA.
Radiation survey instrumentation (calibration, use, and limitations).
Radiation monitoring programs and procedures.
Contamination control, including protective clothing, equipment, and workplace design.
Personnel decontamination.
Emergency procedures.
Warning signs, labels, and alarms.
Responsibilities of employees and management.
Contractor personnel may also be required to take additional site-specific training required by Fort Belvoir as part of their Safety and Security requirements.
Additionally, a tailgate safety meeting will be conducted by the Site Safety and Health Officer or designee, at the beginning of each work shift, whenever significant changes in job scope are made, whenever significant changes in site conditions (physical or radiological) occur, or whenever new personnel arrive at the job site. Health and safety procedures and issues for the day, any unique hazards associated with an activity, and a review of any significant topics from previous activities will be presented at this meeting. The information discussed will be recorded, which will serve as confirmation that the information was presented to those persons whose signatures are on the form.
There will be at least one signed form for each work shift. Tailgate safety training forms will be incorporated into the decommissioning records. The Accident Prevention Plan (APP) shall describe the tailgate safety meetings and required documentation.
3.4.3 Equipment and Materials
The Contractor shall furnish all necessary equipment and materials necessary to execute the required DP Tasks. This equipment would likely include a crane capable of the heavy lifts, skid loaders, forklifts, boom lifts, etc. USACE will require proof of appropriate training and certification for all equipment operators.
All equipment and supplies needed to complete the project should arrive at the site as needed. These materials generally will consist of office, health and safety, and health physics equipment and materials.
USACE currently has 5 - 20 foot conex containers with government property used to support the MH-1A STURGIS Decommissioning Project. This equipment will be transferred to the Contractor, Page | 17 inventoried, and tracked/maintained as government equipment. Attachment 1 is the list of government equipment. Additionally, there is a waste container that will be utilized by the Contractor and will be maintained as government equipment.
3.4.4 Services
The Contractor shall be responsible for working with Ft. Belvoir and USACE in order to provide needed services to the site for the duration of the project. These will include existing or temporary facilities allowing for office space, laboratory, break room, rest room, and equipment storage for the decommissioning contractor. Additional space will be needed for USACE oversight personnel as outlined above.
Electrical service, internet, and phone connections will be installed in the office and laboratory locations as needed. Other facilities may only require electricity connections for work completion.
Water hook-ups may be needed for restrooms, depending on the proposed facilities.
Mobilization also includes delivery and setup of the field trailers, de-energizing the existing reactor power system, and installing new temporary power services. Utilities are available to the Contractor for the site needs. Electrical power for the site can be coordinated with Dominion Energy (POC is Kenneth Wilkins); sewer and water, if needed, will be provided by American Water (POC is Jason Nash). Costs associated with the utilities needed for the project should be included with this WE.
3.5 BUILDING 372 DISPOSITION (WE 4) (Cost Plus Incentive Fee)
All activities should be in accordance with the requirements detailed in the Decommissioning Plan/ Permit and the Contractor prepared Decommissioning Work Plan and associated work plans for the project. Decommissioning the SM-1 reactor facility will generate a variety of unwanted materials or wastes. A majority of these materials are currently, or will be, free of any radioactive contaminants and may be disposed of through well-established construction demolition methods. There are, however, a number of SM-1 components that are known to be activated and/or contaminated from past reactor operations and the contractor should review the government provided documents to better understand the radiological source term at the facility.
3.5.1 Infrastructure upgrades
It may be necessary for the Contractor to provide upgrades to the existing road(s) within the 300 Area to support heavy loads and a steady stream of trucks and equipment for project execution. The Government will repair the roadways necessary for access to the project site prior to the implementation of the project.
For bidding purposes, the Contractor shall assume that trucks would travel Totten Road from the lower 300 Area (near the SM-1 Reactor Facility) to the upper 300 Area (near the main 300 Area gate). The infrastructure upgrade to repave Totten Road would cover approximately 4,000 square yards of paved surface and approximately 1,430 cubic yards (CY) of material would need to be hauled in to complete these upgrades. Other roadways on the route to leave the installation may also require upgrades.
Contractor should bid all anticipated repairs accordingly. The Government team has committed to inspect and repair the roadways at the middle of the project schedule and completion of the work.
These repairs should be priced if repairs are…