This is a Performance Work Statement (PWS) for the modernization of an obsolete fire alarm system at Building 780 (Sustainment Bistro/KQuad DFAC) located at Schofield Barracks, Hawaii. The contractor must upgrade the existing EST2 fire alarm system to a new Edwards EST4 Networked Life Safety Platform, with performance spanning September 28, 2026, through July 28, 2027. The scope encompasses comprehensive field survey and design, removal of existing obsolete equipment, installation of a new UL-listed fully addressable fire alarm system, programming of all devices and system functions, 100% point-to-point testing with integrated systems testing, coordination of acceptance testing with the Authority Having Jurisdiction (AHJ), and complete system turnover including operator training, operation and maintenance manuals, as-built drawings, software backups, and access credentials. All work must comply with NFPA 72, NFPA 101, UFC 401-001 Anti-Terrorism/Force Protection requirements, and applicable codes and standards.
The contractor must provide all labor, supervision, materials, tools, equipment, permits, engineering, and programming necessary to deliver a fully functional and certified system. Key performance requirements maintain an Acceptable Quality Level (AQL) of 0% defective, meaning 90-100% compliance with no identified defects resulting in non-acceptance. Deliverables include an Existing Fire Alarm System Assessment Report, Fire Alarm Installation Documentation and Verification Report, Programming Verification Package, Testing Reports, Operation and Maintenance Manuals, Software Backup and Access Credentials, and proof of minimum one-year warranty. Work is performed at Schofield Barracks during standard government hours (7:30 a.m. to 4:00 p.m., Monday through Friday, excluding federal holidays), and the contractor must comply with extensive environmental, safety, anti-terrorism training, and installation access control requirements specific to U.S. Army Garrison Hawaii.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Modernization of Fire Alarm Systems – Sustainment Bistro, Schofield Barracks, Army Garison O’ahu, Hawaii
04/24/2026 07/22/2026
Performance Work Statement (PWS)
The objective of this Performance Work Statement is to provide all labor, supervision, materials, tools, equipment, transportation, permits, engineering, programming, testing, training, and warranty necessary to upgrade and migrate the existing obsolete EST2 fire alarm systems to the Edwards EST4 Networked Life Safety Platform at the Sustainment Bistro (K‑Quad DFAC), Building 780, located at 780 Menoher Road, Schofield Barracks, HI 96857; This work supports United States Army Garrison Hawaii on the Island of Oahu.
Vision Statement Provide services to support the mission and operations of United States Army Garrison Hawaii, ensuring a seamless transition, maintaining operational efficiency, fostering a reliable Hawaii military community, and enhancing Warfighter readiness and well‑being.
1.0 Scope of work
The contractor shall furnish all personnel, equipment, materials, and services required to deliver a complete, fully functional, certified, and accepted Edwards EST4 fire alarm system.
The scope of work includes:
• Conducting a full field survey and design effort to document existing conditions and develop the new EST4 system layout.
• Removing existing obsolete EST fire alarm system components as necessary.
• Installing a new UL‑listed, fully addressable, code‑compliant Edwards EST4 fire alarm system.
• Programming all system devices, messages, and functions in accordance with project requirements and applicable codes.
• Performing 100% point‑to‑point testing and full-integrated system testing with all connected systems.
• Coordinating acceptance testing with the Authority Having Jurisdiction (AHJ).
• Providing complete system turnover to the Government, including:
– Operator training
– Operation and maintenance manuals
– As‑built drawings
– Software backups
– Required access credentials
1.1 Period of Performance
28 September 2026 – 28 July 2027
2.0 General Requirements
This section describes the general requirements for this effort. The following sub-sections provide details of various considerations on this effort.
2.1 Non-Personal Services
The Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks. Under no circumstances shall the Government assign tasks to or prepare work schedules for individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall e the contractor's responsibility to notify the Contracting Officer (KO) immediately.
2.2 Business Relations
The Contractor will successfully integrate and coordinate all activities needed to execute the requirement. The Contractor shall manage the timeline, completeness, and quality of problem identification. The Contractor shall seek to ensure customer satisfaction and maintain the professional and ethical behavior of all contractor personnel.
2.3 Contract Administration and Management
The Contractor must maintain communication between the support operations at the Directorate of Public Works (DPW) Service Contract Branch, DPW Point of Contact and the Post Office Point of Contact. The Contractor shall respond to the Government's request for this contractual action promptly.
2.4 Subcontract Management
The Prime Contractors shall notify the Contracting Officer Representative (COR) if the Prime Contractor add any subcontractors necessary to integrate this work. The Prime Contractor shall be responsible for any Subcontract management and work performed on this requirement and shall be responsible and accountable for Subcontractor performance on this requirement. The prime Contractor will manage work distribution to ensure there are no Organizational Conflict of Interest (OCI) considerations. Cross teaming may or may not be permitted.
2.5 Contractor Personnel, Disciplines, and Specialties
The Contractor will accomplish the assigned work by employing and utilizing qualified personnel with appropriate combinations of education, training, and experience. The Contractor will provide the necessary resources and infrastructure to manage, perform, and administer the contract.
2.6 Location and Hours of Work
The work for this requirement shall be performed at the following locations on Schofield Barracks, Hawaii:
• Sustainment Bistro (K‑Quad DFAC), Building 780 780 Menoher Road, Schofield Barracks, HI 96857 This contract shall be performed during the Government’s normal working hours, 7:30 a.m. – 4:00 p.m., Monday through Friday, excluding Federal Holidays. The Contractor shall not perform work outside normal working hours without prior written approval from the Contracting Officer (KO).
2.7 Federal holidays
The Contractor’s performance shall not be required on the Federal public holidays listed below. Holidays occurring on weekends will be observed as directed by the Federal calendar (5 U.S.C. 6103).
| New Year’s Day | Labor Day | |
| Martin Luther King Jr.’s Birthday | Columbus Day | |
| President’s Day | Veteran’s Day | |
| Memorial Day | Thanksgiving Day | |
| Independence Day | Christmas Day | |
| Juneteenth National Independence Day |
3.0 Performance Requirements
The following section specifies the Performance Objectives and Performance Elements for the contract.
3.1 Survey and Design
The contractor shall conduct a comprehensive field assessment of each facility’s existing fire alarm system to support the upgrade to the Edwards EST4 platform. The survey shall document all existing devices, wiring, circuits, panel locations, system capacities, and interface points, including kitchen hood suppression connections and gas or electrical shutdown tie‑ins. The contractor shall verify the facility’s occupancy type, hazard classification, and required notification coverage, and identify any deficiencies or non‑compliant conditions that must be corrected as part of the system upgrade.
Based on the results of the assessment, the contractor shall develop a complete engineered EST4 system design in accordance with NFPA 72, NFPA 101, and all AHJ‑specific requirements. The design package shall include device layout drawings, riser diagrams, equipment specifications, and required calculations such as battery, voltage‑drop, and load calculations. The contractor shall also prepare a detailed sequence of operations and submit all design documents for Government and AHJ review.
Throughout the survey and design process, the contractor shall coordinate closely with the Government COR and the Fire Marshal to ensure the system design meets all operational, installation, and life‑safety requirements.
Performance Standard:
The contractor shall assess the existing fire alarm system in each facility and document all devices, wiring, circuits, panel capacities, and interface points. The contractor shall identify any deficiencies or required corrections and provide all necessary calculations, including battery and voltage‑drop calculations, along with a detailed sequence of operations for Government and AHJ review. The contractor shall coordinate with the Government COR and the Fire Marshal throughout the survey and design process to ensure the replacement Edwards EST4 fire alarm system meets all operational, installation, and life‑safety requirements.
AQL: 0%
Deliverable:
A001 Existing Fire Alarm System Assessment Report
3.2 Remove the Existing System
The contractor shall safely remove the existing EST2 fire alarm system within the facility, including the fire alarm control panel, obsolete devices, damaged components, junction boxes, batteries, modules, annunciators, and all abandoned accessible wiring that will not be reused. All removal activities shall be performed in a manner that avoids disruption to facility operations and protects all building systems and infrastructure intended to remain in place.
If required by the Authority Having Jurisdiction (AHJ), the contractor shall provide and maintain a temporary fire watch during removal activities. The contractor shall handle, transport, and dispose of all removed equipment and materials in accordance with federal, state, and local regulations. Completion of removal shall fully prepare each facility for installation of the new Edwards EST4 fire alarm system.
Performance Standard The contractor shall fully and safely remove the existing fire alarm system without disrupting operations, protect all building systems that remain in service, maintain a fire watch when required, and dispose of all materials in compliance with applicable regulations.
AQL: 0%
3.3 Install the New Fire Alarm System
The contractor shall install a new UL‑listed, fully addressable Edwards EST4 fire alarm system to replace the existing obsolete equipment. Installation shall include mounting new smoke detectors, heat detectors, manual pull stations, audible and visual notification appliances, and all associated addressable devices. The contractor shall install the new fire alarm control panel, power supplies, batteries, communication modules, and all required wiring and circuits, ensuring all conductors are properly labeled and terminated.
The contractor shall provide full integration of the EST4 system with existing building safety interfaces, including kitchen hood suppression systems, gas shutoff controls, HVAC shutdown functions, and sprinkler flow and tamper switches. All installation work shall comply with manufacturer specifications, applicable codes and standards, UFC 4‑010‑01 Anti‑Terrorism/Force Protection requirements, and all other Government regulations to ensure a fully functional, reliable, and code‑compliant life‑safety system.
Performance Standard The contractor shall correctly install the new fire alarm system, including all devices, wiring, panels, power supplies, and required interfaces, ensuring all work is code‑compliant, properly labeled, fully integrated with building safety systems, and completed without damage to existing infrastructure.
AQL: 0%
Deliverables A002 – Fire Alarm Installation Documentation and Verification Report
3.4 Program the System
The contractor shall program the new Edwards EST4 fire alarm system so that all devices communicate correctly and all emergency functions operate as intended. Programming shall include assigning device addresses, applying Government‑approved custom labels, configuring alarm, supervisory, and trouble reporting, and establishing proper shutdown sequences for HVAC, gas, and kitchen hood systems. The contractor shall coordinate with base dispatch and the Fire Department to establish and verify the fire alarm monitoring connection. All programmed functions shall be validated to ensure full operational readiness and compliance with applicable requirements.
Performance Standard The contractor shall fully and accurately program the fire alarm system, ensuring all devices report correctly, all shutdowns and system interfaces function properly, and the monitoring connection is verified with dispatch and the Fire Department.
AQL: 0%
Deliverable A003 – Programming Verification Package
3.5 Perform Testing and Commissioning
The contractor shall perform 100% point‑to‑point testing of the new Edwards EST4 fire alarm system, including all initiating devices, notification appliances, kitchen hood suppression interfaces, gas and electrical shutoff functions, and full integration with HVAC and other building control systems. The contractor shall conduct all required integrated systems testing, complete all battery load and functional tests, and correct any deficiencies at no additional cost to the Government. The contractor shall coordinate and schedule acceptance testing with the Authority Having Jurisdiction (AHJ) and shall demonstrate all alarm, supervisory, trouble, and shutdown functions to the satisfaction of the AHJ. The contractor shall provide complete test reports and documentation required for final Government and AHJ approval.
Performance Standard The contractor shall fully test all fire alarm functions, including all integrated shutdowns and system interfaces, and shall successfully demonstrate performance to the AHJ. All deficiencies shall be corrected, and the system shall meet all operational, code, and acceptance requirements.
AQL: 0%
Deliverable A004 – Testing Reports
3.6 Provide Training and Turnover
The contractor shall provide complete system training and turnover to ensure facility personnel can operate and maintain the new Edwards EST4 fire alarm system. Training shall include on‑site instruction for designated staff on panel operation, basic troubleshooting, system status recognition, and emergency procedures. The contractor shall deliver all required turnover documentation, including O&M manuals, software backups, access credentials, and system passwords. The contractor shall also provide all warranty documentation and ensure a minimum one‑year warranty is in place at the time of turnover.
Performance Standard The contractor shall provide complete system training and all required turnover documentation, ensuring facility staff can operate the system and that all final materials—including O&M manuals, software backups, access credentials, and warranty information—are accurate, complete, and fully delivered.
AQL: 0%
Deliverables:
A005 O&M manuals.
A006 Software backup and passwords A007 Warranty.
4.0 Definitions
Acceptable Quality Level (AQL). The AQL is the maximum percent defective (or the number of defects per hundred units) for the purposes of sampling inspection can be considered satisfactory.
The AQL for this contract is 0% defective, meaning all units and services must be 90-100% compliant with the requirements. For the purposes of sampling inspection, no defects or non-conformances are considered satisfactory, and any identified defect will result in non-acceptance.
5.0 Deliverables
| Identifier |
| Name |
| Description |
| Format |
| Frequency/Distribution |
| A001 |
| Existing Fire Alarm System Assessment Report |
| Contractor shall assess the existing fire alarm system, document all devices, wiring, circuits, panel capacities, and interface points, identify required corrections, and provide all necessary calculations and a detailed sequence of operations for Government and AHJ review. |
| Word, Excel or PDF |
| Submit to the KO/COR within ten (10) business days after contract award |
| A002 |
| Fire Alarm Installation Documentation and Verification Report |
| Installation report, labeled device/circuit documentation, as built updates, integration verification, manufacturer compliance certificates, and a completed installation QA checklist. |
| Word, Excel or PDF |
| Submit to the KO/COR within ten (10) business days after installation |
| A003 |
| Programing Verification Package |
| Package includes documented device addresses and labels, confirmation of all programmed alarm, supervisory, trouble, shutdown, and written confirmation that the monitoring connection has been successfully tested with dispatch and the fire department. |
| Word, Excel or PDF |
| Submit to the COR within ten (10) business days after programing |
| A004 |
| Testing Reports |
| A complete system testing and acceptance package that includes documented results of 100% device testing, integrated systems testing, battery load testing, AHJ‑witnessed acceptance testing, and all final test reports and corrections required for approval. |
| Word, Excel or PDF |
| Submit to the KO/COR within ten (10) business days of testing |
| A005 |
| O&M Manuals |
| Provide O&M manuals. |
| Word, Excel or PDF |
| Submit to the COR within ten (10) business days after project closeout, after successful system testing and AHJ approval, and prior to final acceptance by the Government. |
| A006 |
| Software Backup and Access Credentials |
| Provide software backup and passwords to Government. |
| Word, Excel or PDF |
| Submit to the COR at final system turnover. |
| A007 |
| Warranty |
| Provide a minimum 1-year warranty. |
| Word, Excel or PDF |
| Submit to the COR at final system turnover. |
6.0 Performance Requirement Summary (PRS)
| Required Services /Performance Object |
| PWS Paragraph Number |
| Performance Standards |
| Maximum Allowable Degree of Deviation from Requirement (AQL Level) |
| Incentive/Remedy |
Survey / Design
Para 3.1
The contractor shall assess the existing fire alarm system, document all devices, wiring, circuits, panel capacities, and interface points, identify required corrections, and provide all necessary calculations and a detailed sequence of operations for Government and AHJ review. The contractor shall coordinate with the Government COR and Fire Marshal throughout to ensure the replacement system meets all operational, installation, and life‑safety requirements.
AQL: 0%
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or additional time needed to accomplish this requirement at no additional cost to the Government.
Remove the Existing System
Para 3.2
The contractor shall fully and safely remove the existing fire alarm system without disrupting operations, protect all building systems that remain, maintain a fire watch when required, and dispose of all materials in compliance with applicable regulations.
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or additional time needed to accomplish this requirement at no additional cost to the Government.
| Install the New Fire Alarm |
| Para 3.3 |
The contractor shall correctly install all new fire alarm, including devices, wiring, panels, power supplies, and required interfaces, ensuring all work is code‑compliant, properly labeled, fully integrated with building safety systems, and installed without damage to existing infrastructure.
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or additional time needed to accomplish this requirement at no additional cost to the Government.
| Program the System |
| Para 3.4 |
The contractor shall fully and accurately program all fire alarm functions, ensuring all devices report correctly, all messages and tones operate as required, all shutdowns and interfaces function properly, and the monitoring connection is verified with dispatch and the fire department.
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or
Perform Testing and Commissioning
Para 3.5
The contractor shall fully test all fire alarm and functions, including integrated shutdowns and interfaces, and shall successfully demonstrate system performance to the AHJ. All deficiencies shall be corrected and the system shall meet all operational, code, and acceptance requirements.
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or
Provide Training and Turnover
Para. 3.6
The contractor shall provide complete system training and all required turnover documentation, ensuring facility staff can operate the system and all final materials—including O&M manuals, software backups, access credentials, and warranty information—are accurate and fully delivered.
Trends of less-than-acceptable performance could result in non-conforming reports issued to the Contractor or
7.0 OTHER INFORMATION
7.1 GENERAL ENVIRONMENTAL STANDARDS
(a) The contractor will comply with the Government directives, permit conditions, installation policies and plans as administered by the Government. The Contractor will be held liable to pay for any environmental fines resulting from his operations, waste generated or other operational environmental requirements. As applicable, the Contractor will obtain environmental permits required for wastewater pretreatment, underground tanks, hazardous waste identification numbers, and air pollution permit for temporary sources, storm water permits or other pertinent environmental permits.
(b) The contractor will review and comply with applicable policies, program documents and regulatory requirements as stipulated under each environmental program media below.
(1) Environmental program documents include, but are not limited to; the Installation Hazardous Waste Management Plan – USAG-HI Regulation 200-4, Asbestos Management Plan, Lead-based Paint Management Plan, Installation Spill Prevention, Control, and Countermeasures (SPCC) Plan, Integrated Natural Resources Management Plan, Integrated Cultural Resources Management Plan, Pollution Prevention Plan, and the Storm Water Pollution Prevention Plan available at the DPW Environmental Division. Environmental program documents can be downloaded from the installation sustainability and environmental management website at: https://home.army.mil/hawaii/garrison/dpw/environmental-division
(2) Installation policies include but are not limited to; the Environmental Compliance and Protection Program Policy Memorandum USAG-HI-4; Spill Kit Requirements USAG-HI-33; Solid Waste Management and Recycling USAG-HI-11; Open Burn Policy Memorandum USAG-HI-27; Illicit Discharge Detection and Elimination Policy Memorandum USAG-HI-30. Installation Policy Memorandums are available for download at: https://home.army.mil/hawaii/about/command-pubs
(c) The Contractor shall at all times keep the work area, including storage areas used by him, free from accumulations of waste material or rubbish and prior to completion of the work remove any rubbish from the premises and all tools, scaffolding, equipment and materials not the property of the Government. Upon completion of the work, the Contractor shall leave the work and premises in a clean, neat and workmanlike condition satisfactory to the Contracting Officer. If debris is not disposed of properly or the site is not left clean, the Government will clean the site at the expense of the contractor. The Contractor will also be held liable for damages done to the environment as a result of disposal and/or cleanup.
(d) The Contractor may be subject to unannounced Environmental Compliance Inspections by the DPW Environmental Division.
(e) Environmental and Safety Noncompliance Fees. The Contractor shall be solely responsible for remedying all Federal, State and local environmental and safety violations or noncompliance and any payment of fines, penalties and fees levied as a result of the violations or noncompliance. The Government reserves the right to withhold payment in the amount of the fines, penalties and fees levied if not paid by the contractor.
7.2 EMERGENCY PLANNING COMMUNITY RIGHT TO KNOW ACT (EPCRA) HAZARDOUS SUBSTANCES (HS)
(a) Contractors using EPCRA HS in the performance of any work while on USAG-HI installations are responsible for complying with the provisions of EPCRA regulations and submitting applicable reports (TIER II/TRI) to Federal and State regulatory agencies as applicable.
(b) Copies of reports for substances used in connection with work performed on USAG-HI installations shall be provided to the DPW Environmental Division, Attention: EPCRA Program Manager, STOP 253, 3rd Floor, 948 Santos Dumont Ave., Wheeler Army Airfield, phone 808-656-3106.
(c) Chemicals regulated under EPCRA HS are defined in EPA document EPA 550-B-98-017, Title III List of List, Consolidated List of Chemicals Subject to the Emergency Planning and Community Right to Know Act and Section 112(r) of the Clean Air Act Amended.
(d) The Contractor is responsible for knowing which chemicals it uses or transports that are contained on the list. For convenience, the Contractor may review a copy of the EPA document at the Directorate of Public Works (DPW) Environmental Division.
(e) The Contractor must maintain copies of Safety Data Sheets (SDS’s) of all chemicals used in the performance of any work while on USAG-HI installations. SDSs must be readily available at the site location where the work is being performed.
(f) The Contractor can request the list and locations of EPCRA HS currently utilized on USAG-HI installations by contacting the DPW Environmental Division EPCRA Program Manager. The Contractor must provide name, company, contract number, date the contract was awarded and provide a description of the contract. A database of locations of chemicals will then be forwarded upon review and approval of request. Contractors working on USAG-HI installations are encouraged to review this database, which will provide information where potentially hazardous chemicals are stored.
(g) All spills of substances containing EPCRA HS will be immediately reported to the Directorate of Public Works Spill Response line at 808-656-1111 or 808-656-3279 (after hours). The Contracting Officer must be notified during the first business hour immediately after. All waste generated from EPCRA HS being utilized will be immediately reported to the DPW Environmental Office, phone: 808-656-3106.
(h) All Contractors utilizing substances containing EPCRA HS will perform the following prior to contract start.
(1) Review the Installation Spill Prevention, Control, and Countermeasures (SPCC) Plan available upon request from the DPW Environmental Division.
(2) Provide a listing and SDS copies of oil and Hazardous Substance (HS) products projected to be utilized in the performance of any work while on USAG-HI installations to the DPW Environmental Division. The estimated average and maximum quantities of each material anticipated to be on-site at any given time shall also be provided to the DPW Environmental Division EPCRA Program Manager, STOP 253, 3rd Floor, 948 Santos Dumont Ave., Wheeler Army Airfield, phone 808-656-3106 and to building 6040 East Range for material to be bar-coded. The contractor must ensure the product listing is current and updated as frequently as necessary and/or at a minimum, on an annual basis by 1 January of each year.
(3) Provide the name, office phone number, and cellular phone number of a company spill response point of contact. The point of contact must be trained in spill response.
(4) Provide a copy of an agreement with a hazardous materials spill response company in the event of a spill.
(5) Provide copies of employees training certificates on environmental and spill response training.
(6) Appoint a primary and alternate Environmental Compliance Officer in writing.
(7) Develop a notification procedure in the event of a spill to include phone numbers of response personnel, support agencies, National Response Center, State Hazard Evaluation Emergency Response Office and Civil Defense.
(8) Accomplish all spill notifications as required by the U.S. Environmental Protection Agency and State of Hawaii to the Hazard Evaluation Emergency Response Office, Local Emergency Response Commission and National Response Center. Copies of written spill notifications shall be provided to the DPW Environmental Division.
(9) All spills caused by the contractor will be cleaned up under supervision of the contractor and a qualified hazardous materials spill response company, at no cost to the government, in accordance with all applicable laws and regulations and to the satisfaction of the DPW Environmental Division.
(10) The contractor shall pay for disposal cost of all contaminated materials to include but not limited to soil, sorbent materials, disposable equipment and other materials contaminated by the spill. Ensure all disposals are in accordance with all applicable laws and regulations at authorized disposal facilities.
7.3 SPILLS OF PETROLEUM/OIL/LUBRICANTS OR HAZARDOUS MATERIALS/HAZARDOUS WASTE
(a) The Contractor will prepare and maintain a site-specific spill plan, including notification procedures for spills/releases. The spill plan will include phone numbers of response personnel, support agencies, National Response Center, State Hazard Evaluation Emergency Response Office and Civil Defense. The Contractor will provide a copy of the spill plan to DPW Environmental Division upon request.
(b) The Contractor shall provide immediate response to stop, contain, and clean-up all spills of oil and other hazardous substances that result from his performance under this contract.
(c) The Contractor must report all spills immediately to the DPW Spill Response line at (808) 656-1111 in accordance with the Installation SPCC Plan. Additionally, the Contractor shall notify the COR of the incident during normal business hour or the first business hour following the incident.
(d) The Contractor will accomplish all spill notifications and written spill reports as required by the U.S. Environmental Protection Agency, State of Hawaii Hazardous Evaluation Response Office, Local Emergency Planning Commission and National Response Center, in accordance with applicable laws and regulations.
(e) The Contractor will provide a copy of spill notifications and written reports to the DPW Environmental Division.
(f) All spills caused by the Contractor will be cleaned up under the supervision of the Contractor and/or a qualified hazardous waste/materials spill response company, at no cost to the USAG-HI, in accordance with all applicable laws and regulations and to the satisfaction of the DPW Environmental Division. If cleanup is not accomplished in a timely fashion, or to the satisfaction of the DPW Environmental Division, the Government will assist with the final cleanup, and the Contractor will provide appropriate reimbursement of cleanup costs.
(g) The Contractor will pay for all clean up, management, and disposal cost of all contaminated materials to include but not limited to soil, sorbent materials, disposable equipment and other materials contaminated by the spill. The Contractor will ensure waste disposal is accomplished in accordance with all applicable laws and regulations and at an authorized/permitted treatment and disposal facilities.
(h) The Contractor will pay any fines or penalty charges associated with a citation issued by federal, state or local officials as a result of the accident.
(i) Contractors handling bulk fuel must be trained to do so, and mobile fuel operations must be approved by the DPW Environmental Division.
(j) Off-Post Spills. The Contractor shall be responsible for and pay for cleanup of off-post spills in accordance with directions received from appropriate local authorities (e.g., Honolulu Fire Department, State Civil Defense, etc.). Off-post spills in connection with work performed under this contract shall also be reported to the DPW Spill Response line at (808) 656-1111 and the COR.
(k) Discovery of other than Contractor-caused spills. The Contractor shall report any spills of hazardous materials to the DPW Spill Response line at (808) 656-1111 and the COR upon discovery.
7.4 HAZARDOUS WASTE (HW), Universal Waste (UW), and NON-REGULATED WASTE (NRW).
(a) The Contractor will comply with all applicable Federal and State regulations for the characterization, storage, management, and disposal of all solid waste, HW, UW, and NRW.
(b) The Contractor will determine, based on analytical testing, the regulatory status of all waste generated. Any waste awaiting testing must be stored in compliance with all applicable regulations. The Contractor will provide a copy of the analytical results and waste determination to the DPW Environmental Division as soon as they are completed. If the waste is determined to be HW, the Contractor must coordinate an inspection of the waste with the DPW Environmental Division Transfer and Accumulation Point (TAP) Manager at 808-656-0866. A copy of the Draft Hazardous Waste Manifest must be furnished to the TAP Manager prior to scheduled disposal. HW disposal must be coordinated with the TAP Manager who must be present to sign the HW Manifest at the time it is picked up for transportation for disposal. If the waste is determined to be NRW, the Contractor may sign the Non-Hazardous Waste Manifest for the transportation and disposal of the NRW but they must furnish a copy of the Non-Hazardous Waste Manifest to the TAP Manager. All costs associated with HW and NRW disposal are borne by the Contractor.
7.5 RECYCLING PROGRAM
(a) The Contractor will comply with USAG-HI Policy Memorandum11, Solid Waste Management and Recycling and with Army Regulation 200-1(10-2): Environmental Protection and Enhancement, requiring diversion of solid waste through reduction, green procurement, and recycling to support the Army’s waste management objectives. More information can be found on the installation sustainability and environmental management website at: https://home.army.mil/hawaii/garrison/dpw/swrp#qt0:3
(b) Identify a recycling POC to DPW Environmental Division to include name, phone number and email address.
(c) Report monthly quantities of refuse disposed and recycled to DPW Environmental Division as part of the work performed under this contract as applicable, utilizing the Summary of Solid Waste Disposal and Diversion Form Revised on 12/14/2023.
7.6 NATURAL AND CULTURAL RESOURCES PROGRAM
(a) The Contractor will comply with USAG-HI Range Standard Operating Procedures (SOPs). All personnel who use the ranges must complete a mandatory pre-brief covering issues associated with Natural and Cultural Resources.
(b) The Contractor must be cognizant of the potential environmental impact and liability their actions could have, if specified procedures are not followed on Army lands. The Contractor must be aware that USAG-HI manages more than 100 threatened and endangered species including plants, snails, birds, bats, insects and their critical habitat and over 1,300 prehistoric archaeological sites, including temple structures, stone markers, fishing shrines, habitation sites, caves, rock shelters, mounds, burial platforms, earth ovens, stone walls and enclosures, agricultural terraces, irrigation canals, petroglyphs and trails.
(c) The Contractor must only allow smoking in designated areas to minimize potential for starting wildfires.
(d) The Contractor must follow all recommendations and guidelines in the garrison and DPW policies that provide protection for natural resources, specifically the following:
(i) DPW-HI-01 Avoidance of Little Fire Ant Introduction. All new landscaping projects must be sourced from nurseries free of little fire ants.
(ii) DPW-HI-02 Tree Cutting Moratorium. There shall be no cutting or trimming of any tree over 15 feet tall during the Hawaiian hoary bat pupping season, 1 June to 15 September.
(iii) DPW-HI-03 Landscaping with Native Plants. All new construction and land management projects must use native Hawaiian plant species for landscaping to the extent practical.
(iv) USARHAW Washrack Utilization Policy to Control Invasive Species. Clean, wash, and inspect vehicles and equipment prior to movement to/from off-island locations, prior to movement from Kahuku Training Area, and prior to movement from Schofield Barracks East Range to minimize potential spread of invasive species.
(v) USAG-HI-13Animal Control Policy. Do not feed feral or free-roaming animals, including pigs, dogs, cats, chickens, mongoose, etc.
(vi) USAG-HI-35 Wildlife Friendly Lighting and Dark Skies. Minimize the potential impacts on wildlife from man-made light sources through design and use guidance. Use lights only when needed, only light the area that needs it, do not use lights brighter than necessary, minimize blue light emissions, and shield lights so they are pointed downward – the extent feasible.
(vii) USAG-HI-50 Green Waste Policy. To minimize the spread and breeding of coconut rhinoceros beetle, any work that generates green waste must follow the handling, transportation, and disposal guidelines outlined in the policy.
(e) The Contractor will stay out of areas marked with Seibert Stakes. Seibert stakes are placed along roads and within vegetated areas to advise personnel of unsafe or hazardous range or training conditions and/or environmentally sensitive off-limit areas.
(f) All contracts must comply with applicable historic preservation requirements including but not limited NHPA, NAGPRA, & ARPA including any requirements specified in the NEPA documentation. Contractors must ensure they follow all historic preservation requirements and may face civil or criminal prosecution for violating those requirements. No archaeological activity may occur under any contract with a permit from the U.S. Army Garrison Hawaii Cultural Resources Office.
(g) The Contractor will refer to the installation sustainability and environmental management website at: https://home.army.mil/hawaii/garrison/dpw/natural-resources and https://home.army.mil/hawaii/garrison/dpw/cultural-resources for additional information.
7.7 NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)
As applicable, and upon request by the Government, the Contractor will comply with the NEPA process, notify the DPW Environmental Division and complete a Record of Environmental Consideration (REC) for actions such as, but not limited to:
(1) Actions that could impact historic structures, cultural and natural resources
(2) Minor renovation or new construction
(3) Actions that introduce new training vehicles, maneuvers, and weapons
(4) Replacing or removing floor tiles, ceiling tiles, sound proofing material, lighting fixtures, carpet, serving line equipment, natural gas unit
(5) Installing interior doors, windows, partitions, security cameras, rerouting ductwork
7.8 ENERGY AND WATER CONSERVATION
(a) Upon request by the Government, the Contractor will appoint a Unit Energy Conservation Officer (UECO) and Building Energy Monitor (BEM) and fully participate in the Garrison's energy and water conservation program.
(b) Appointed BEM and UECO must attend the training class provided by the DPW Engineering Branch.
(c) The appointed UECOs and BEMs are responsible for ensuring energy-saving measures are being enforced in each building and to provide regular reports to DPW Engineering Branch showing how well the contractor is doing at conserving energy.
(d) More information can be found on the installation sustainability and environmental management website at: http://www.garrison.hawaii.army.mil/sustainability/Energy.aspx
479 PRECAUTIONS FOR THE PROTECTION OF EXISTING UTILITIES (INCLUDES COMMUNICATIONS) AND FACILITIES.
(a) Contractors are required to ensure necessary precautions and obtain required permits to protect government utilities and facilities. Contracts involving dredging, excavating, blasting and grading operations, demolition of structure and the moving of heavy and/or bulky equipment shall be subject to the following procedures and conditions:
(1) The Contractor shall obtain a written concurrence of the existing conditions and locations of utilities for his operations from the COR prior to beginning work and request the best information available on the location of Engineer facilities. Contractor shall verify locations of all utilities identified by the Government which affect his work.
(2) The Contractor shall be required to obtain a written clearance for his operations prior to beginning work and shall have locations of signal underground facilities staked out in the field from the 30th Signal Battalion/Network Enterprise Center-Hawaii (NEC-HI), EMC, IMG (Army Telephone, Data/LAN): Bldg. 600, Room 157, 148 Curtis Loop, Wheeler Army Airfield. Mr. Eugene Brown, (Primary AO) (808) 656-6656; Marion F. Robinson, Jr., (808) 656-1765 (Alt AO). Business Hours: Mon - Fri. 0830-1700.
(3) If any cable/conduit is uncovered or damaged during excavation process, immediately contact:
(i) the JHITS trouble desk, (808) 659-1444
(ii) the NEC-HI RNOSC, (808) 655-2999, with detailed information on situation, and
(iii) the NEC-HI POCs (above) with reported dates, times and details.
(4) The Contractor shall also obtain a written clearance for gas line for these operations from The Gas Company (Tel: 594-5575) prior to beginning work and shall have locations for underground facilities staked out in the field by Gas Company personnel.
(5) Additional Digging Information: At least five days prior to digging please call the number below. Government Agency and Contact Person: Hawaii One Call Center Phone Number: 1- 866-423-7287.
(b) The Contractor shall be liable for damages resulting from his failure to comply with (1), (2), (3) or (4) above.
7.10 AMC-LEVEL PROTEST PROGRAM
(a) If you have complaints about this procurement, it is preferable that you first attempt to resolve those concerns with the responsible Contracting Officer. However, you can also protest to Headquarters, AMC.
(b) The HQ, AMC-Level Protest Program is intended to encourage interested parties to seek resolution of their concerns within AMC as an Alternative Dispute Resolution forum, rather than filing a protest with the Government Accountability Office or other external forum. Contract award or performance is suspended during the protest to the same extent, and within the same time periods, as if filed at the GAO.
(c) The AMC protest decision goal is to resolve protests within 20 working days from filing. To be timely, protests must be filed within the periods specified in FAR 33.103. Send protests (other than protests to the Contracting Officer) to:
Headquarters U.S. Army Materiel Command Office of Command Counsel 4400 Martin Road Rm: A6SE040.001 Redstone Arsenal, AL 35898-5000
Fax: (256)450-8840
(d) The AMC-level protest procedures are found at: http://www.amc.army.mil/amc/commandcounsel.html. If Internet access is not available, contact the Contracting Officer or HQ, AMC, to obtain the AMC-Level Protest Procedures.
7.11 ACCESS TO ARMY INSTALLATIONS – PERSONNEL and VEHICLES.
The Government recognizes the important roles companies like you play in our day-to-day operations. That is why USAG-Hawaii is enhancing the current access control solution called the Automated Installation Entry (AIE) Program. This program supports the security requirements while offering a streamlined access procedure for vendors, contractors, sub-contractors, suppliers and service providers. This program is available to new and existing personnel who require access to USAG Hawaii and are not authorized to receive a Department of Defense CAC and desire a streamlined entry into the installation. Sponsorship and participation at each USAG Hawaii location (e.g., Schofield Barracks, Wheeler Army Airfield, Fort Shafter, Tripler Army Medical Center, Pililaau Army Recreation Center and Pohakuloa Training Area) is required.
AIE Credential holders may access the installation through any of the USAG-Hawaii Gates that size allows and will only be subject to random inspections.
Companies that choose not to participate in the AIE Program will have limited access through the Schofield Barracks Lyman gate, Fort Shafter’s Buckner Gate and Tripler Army Medical Center Main Gate. All employees will be required to go through the inspection area and will be subject to the standard access control procedures, security screenings, and/or vehicle inspections.
*Access control changes can occur at any time due to security requirements
Companies that service USAG Hawaii facilities may initiate enrollment in the AIE Program by contacting the Contracting Officer’s Representative (COR).
If you have questions regarding the AIE Program at USAG Hawaii, please contact Security Branch Operations, at 808-656-0232.
· AIE Program Enrollment Process for Background Check and Process to obtain AIE Badge
Enroll your company by contacting the COR who will be the Sponsor. The COR will provide the excel spreadsheet for the list of contractor employee information. The following information is required from the contractor: last name, first name, date of birth, status, social security number, company name, and contract number. The COR will complete the Sponsor information and provide the list to the Directorate of Emergency Services (DES) Access Control Division. The DES will conduct the background check to vet personnel prior to arrival to pick up their AIE Badge and will ensure a more efficient process while saving time.
The AIE Program performs background screening and credentialing.
DES will contact the COR (Sponsor) once the background checks have been validated to schedule a time for the contractor employees to go to one of the registration locations and complete the process to obtain the AIE Badge.
Contractor employees should bring an acceptable form of identification (see List A and List B) to the appointment. Upon arrival, a photo will be taken to complete the process. Employees will be issued their AIE Badge, which they will use for access to the installation.
Forms of Acceptable Identification for picking up your credential:
List A - One (1) needed
U.S. Passport (unexpired)
Permanent Resident Card or Alien Registration Receipt Card (Form I-551)
Unexpired foreign passport, with I-551 stamp or attached Form I-94 indicating unexpired employment authorization
Unexpired Employment Authorization Document that contains a photograph (Form I-766, I-688, I688A, I-688B)
List B – Two (2) needed
Driver’s license or ID card issued by a state
ID Card issued by federal, state or local government agencies or entities
School ID card with a photograph
Voter’s registration card
U.S. Military card or draft record
Military Dependent’s ID card
U.S. Coast Guard Merchant Mariner Card
Native American tribal document
Driver’s license issued by a Canadian government authority
U.S. Social Security card issued by the Social Security Administration
Certification of Birth Abroad issued by the Department of State (Form FS-545 or Form DS-1350)
Original or certified copy of a birth certificate issued by a state, county, municipal authority or outlying possession of the United States bearing an official seal
U.S. Citizen ID Card (Form I-197)
ID Card for use of Resident Citizen in the United States (Form I-179)
Unexpired employment authorization document issued by DHS (other than those listed under List A)
7.12 ANTITERRORISM (AT) STANDARDS
Pursuant to Department of Defense Instruction Number 2000, “DoD Antiterrorism (AT) Standards,” dated October 2, 2006, each contractor employee requiring access to a Federally-controlled installation, facility and/or Federally-controlled information system(s) shall complete Level I AT Awareness Training on an annual basis and receive a certificate of completion.
Standard Contract Language Provision/Contract Clause Applicability and/or additional SOW language. Detailed information on each of these items are stated below. Applicable items to this contract are indicated below.
___X__1. AT level I Training (general)
| __ X__ 2. Access and general protection policy and procedures. |
| ______2a. For contractor requiring Common Access Card (CAC) |
| __X__ 2b. For contractor not eligible for CAC, bur requires access to DoD facility |
or installation _____ 3. AT Awareness training for US Based contractor personnel traveling overseas.
| __X__ 4. iWatch training |
| _____ 5. Army Training Certificate Tracking System (ACTS) registration for |
contractors.
| _____ 6. For contracts that require a formal OPSEC program |
| __X__ 7. Requirement for OPSEC training |
| _____ 8. Information assurance/information technology training |
| _____ 9. Information assurance/information technology certification |
| _____ 10. Contract authorized to accompany the force clause |
| _____ 11. Contract requiring performance or delivery in a foreign county. |
| _____ 12. Handling/Access to classified information. |
| __X__13. Threat Awareness Reporting Program |
1. AT Level I training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I Awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I Awareness training is available at the following website: http://jko.jten.mil.
2. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contract or Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
2a. For Contractors requiring CAC access to a DoD facility or installation. N/A
2b. For Contractors that do not require CAC but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations .
3. Anti-Terrorism (AT) Level 1 Awareness Training. This standard language is for contractor employees with an area of performance within an Army controlled installation,…