About this file
This is a Questions and Answers log for federal contract opportunity W912CH-25-R-0176, last updated May 20, 2025. The solicitation seeks procurement of collapsible fuel tank assemblies in four sizes (3K, 20K, 50K, and 210K gallons) under a single firm-fixed-price, 5-year Indefinite Delivery Indefinite Quantity (IDIQ) Long Term Contract. The Government intends to award to one contractor for all tank sizes, with evaluation based on two factors: Past Performance (significantly more important) and Price. Products must comply with MIL-PRF-32233D performance specification, and offerors may propose materials and manufacturing methods that meet or exceed specification requirements. First Article Test and Report (FATR) costs are included in the total evaluated price for all four tank sizes. Delivery is FOB Destination to one or more of multiple specified locations based on estimated percentages outlined in the solicitation, with exact destinations to be identified on delivery orders. The contract is structured as firm-fixed-price with no provision for price adjustments due to material cost escalation, tariffs, or other unforeseen increases.
Many questions remain unanswered (marked TBD), including clarification on incumbent contractor information, specific testing requirements per MIL-PRF-32233D, acceptability of thermoset polymer bladders, allowable fuel type for testing, qualification of multiple material vendors and equipment sources, acceptability of representative bladder sizes for First Article Testing, and whether offerors may propose alternate integrated configurations. Additionally, unanswered questions address the number of past performance references required, acceptance of past performance for MIL-PRF-32233B (prior revision) tanks, whether relevant non-government test data may support First Article Waiver requests, and clarification on the total number of past performance references permissible (two or four). One answer provided clarifies that Special Packaging Instructions exist only for the 210K-IPDS tank, with 3K, 20K, and 50K tanks following standard packaging requirements in Section D and respective CLIN sections.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Last Updated: 20 May 2025 3:33 pm EST
W912CH-25-R-0176 - Q & A Log
Question: Is there an incumbent contractor? If so, can you please share the contact information?
Answer: TBD
Question: As per Para 5.4.3 - Table VI in MIL PRF 32233D, please confirm Seam Dead Load
Shear Resistance conformance test (para 4.5.2.9) is required per fabric material lot, not bladder production Inspection Lot (para 4.3.1).
Answer: TBD
Question: Historically, the Government has relied on Southwest Research Institute (SwRI) for bladder test data. Due to fuel storage capacity, SWRI is unable to perform a First Article Test on
Size V – 210K Bladders. Testing outside of SWRI may require awardee to test sequentially, where the typical timeline is greater than 90 days due to fuel delivery and cycling. If a bladder supplier utilizes the same materials and construction techniques for all bladder sizes, would the
Government consider a single bladder size that is most representative of all bladders for the First
Article Test? It is recognized that a typical Size III – 20K Bladder experiences all representative stresses while providing the most efficient and cost-effective option for the Government.
Answer: TBD
Question: Are thermoset polymer bladders acceptable under this solicitation effort?
Answer: TBD
Question: To be prepared for a robust supply chain, is it necessary for a First Article bladder to be constructed to qualify multiple equipment sources and qualify various material vendors to avoid iterative First Article testing beyond Table I and Table II qualification?
Answer: TBD
Question: Per Paragraph 4.5.1.6, will road diesel #2 be appropriate/acceptable for First Article
Testing? If not, please advise on Government approval method to acquire bulk JP-8.
Answer: TBD
Question: In the solicitation, the Government states that it intends to issue an award as a single
FFP Long Term Contract. Regarding M.3.5, if the Government chooses to enter into a negotiation round and it changes its intention to a multi-source supply award, how will this be communicated to the participants?
Answer: This Solicitation, W912CH-25-R-0176, is intended to result in the award of a single firm-fixed-price, 5-year, Indefinite Delivery Indefinite Quantity Long Term Contract for the procurement of all four tank sizes, 3K, 20K, 50K, and 210K. This RFP includes FAR 52.215-1
Instructions to Offerors Competitive Acquisition in Section L, which advises offerors that the
Government intends to make award without conducting negotiations/discussions. However, under FAR 52.215-1(f)(4), the Government reserves the right to hold negotiations/discussions, if necessary.
Question: If there is a multiple award contract issued, will FAR 16.505(b)(1)(iii) - Simplified
Acquisition Threshold apply?
Answer: This Solicitation, W912CH-25-R-0176, is intended to result in the award of a single firm-fixed-price, 5-year, Indefinite Delivery Indefinite Quantity Long Term Contract for the procurement of all four tank sizes, 3K, 20K, 50K, and 210K.
Question: Will the Government reconsider delivered pricing vs First Destination Transport? As we are in a period of high fuel price volatility, which is a major driver of delivery costs, it would be prudent for vendors to estimate delivery costs based on current fuel pricing. The Government has a better view of fuel futures and buying power to ensure the most efficient delivery costs regardless of the economic situation at the time of shipment over the course of a 5-year contract.
Answer: TBD
Question: Section A and Section M state that the Government intends to award a single firm-fixed-price, 5-year IDIQ contract. Please confirm whether the Government intends to award one contract covering all four tank sizes, 3K, 20K, 50K, and 210K, or whether the Government may consider separate awards by tank size or another split-award structure among small businesses.
Answer: This Solicitation, W912CH-25-R-0176, is intended to result in the award of a single firm-fixed-price, 5-year, Indefinite Delivery Indefinite Quantity Long Term Contract for the procurement of all four tank sizes, 3K, 20K, 50K, and 210K.
Question: Section M identifies Past Performance and Price as the evaluation factors, with Past
Performance significantly more important than Price. Please confirm whether documented reliability, manufacturing controls, material performance, quality history, and relevant prior performance will be considered as part of the Past Performance confidence assessment when comparing proposals.
Answer: Please reference section M.4.1 Factor 1: Past Performance Factor for information on how Factor 1 will be evaluated and reference section L.4.1 Volume 1 Past Performance Factor for guidance on what should be submitted for Factor 1 evaluations.
Question: MIL-PRF-32233D is a performance specification. Please confirm whether an offeror may propose materials, manufacturing methods, and quality-control improvements that meet or exceed MIL-PRF-32233D and all solicitation requirements, without taking exception to the solicitation.
Answer: TBD
Question: For the 210K requirement, please confirm whether the Government requires the 210K-
IPDS exactly as identified under NSN 5430-01-546-3725 / P/N 210K-IPDS, or whether an alternate integrated configuration that provides equivalent or improved performance and total system capacity would be acceptable.
Answer: TBD
Question: If an offeror has relevant recent Government performance and test evidence for similar collapsible fuel tank systems, may that evidence be submitted as part of the Past Performance volume and/or a First Article Waiver request package for Government consideration?
Answer: TBD
Question: Section L.2.3.1 (page 93) references the proposal subject header as “Proposal
Submission W912CH-25-R-0175 (company name).” Since this solicitation is W912CH-25-R-
0176, please confirm the correct solicitation number to use in the email subject line.
Answer: The correct solicitation number is W912CH-25-R-0176. Please reference Amendment
0002 issued on 20 May 2026 for this correction.
Question: Please clarify total number of Past Performance references. It is unclear if offeror may provide two or four.
Answer: TBD
Question: Will the Government accept past performance references for collapsible fuel tanks fabricated to MIL-PRF-32233B, provided they meet the size, complexity, and production capacity requirements of the current solicitation? Because MIL-PRF-32233C/D is a relatively recent revision (2021/2022), allowing Revision B past performance ensures a robust pool of qualified, competent, and competitive fabricators while maintaining the identical core manufacturing relevancy required.
Answer: As mentioned in M.4.1.1, the Government will conduct a Performance Confidence
Assessment to establish a Confidence Assessment Rating for each offeror. The Confidence
Assessment Rating assigned will be based on the offeror's Recent and Relevant performance record and the expectation that the offeror will successfully perform the required effort based on the criteria consideration described in L.4.1.2. The past performance relevancy rating and performance confidence assessment methods are found in the DoD Source Selection Procedures date August 20, 2022. It is recommended that each offeror review these procedures/ratings when determining what to submit for the past performance factor as it relates to the criteria considerations in L.4.1.2.
Question: Completion of the FATR for each tank size represents a significant cost for the Offeror and potentially an unfair advantage to a very limited number of offerors. To allow for more competition and fairness will the Government exclude the FATR cost entered by each Offeror from the total evaluated price?
Answer: No, the Total Evaluated Price equals the sum of the following: the total proposed price as calculated in the "Summary" Worksheet of Attachment 0001 - Pricing Workbook and if applicable, any other price adjustments, for evaluation purposes only, that are required in accordance with the FAR, DFARS, or RFP (to include RFP Attachments). This includes, but is not limited to, the pricing for all CLINs, including the FATR CLINs.
Question: How does the government view uncertain raw material cost escalation due to factors out of Offerors’ control such as USG tariffs and increased costs of aluminum, polyurethane coated fabrics, and nylon. Would the Government allow awardee to renegotiate CLIN pricing in the event of such unforeseen increases?
Answer: No, this solicitation is intended to result in a 5-Year Firm-Fixed-Price (FFP) Indefinite
Delivery Indefinite Quantity (IDIQ) Contract. As stated in RFO FAR 16.202-1, A firm-fixed-price contract provides for a price that is not subject to any adjustment on the basis of the contractor’s experience in performing the contract.
Question: The contract number referenced appears to be an error. Should the proposal submission instructions indicate the solicitation number: W912CH-25-R-0176 instead?
Answer: Yes, the correct solicitation number is W912CH-25-R-0176. Please reference
Amendment 0002 issued on 20 May 2026 for this correction.
Question: The attachment SPI_AK15463725_Revision_E.pdf was provided in the original solicitation documents. This SPI is for the 210k IPDS tank. Will the government provide the SPI for the other tanks in this solicitation?
Answer: There are no Special Packaging Instructions for the 3K, 20K, or 50K tank sizes.
Packaging requirements are in accordance with Section D - PACKAGING AND MARKING.
Additionally, please reference the Packaging and Marking Section under each CLIN in Section
B.
Narrative D.1. PACKAGING REQUIREMENTS (SPECIFICATIONS/STANDARDS)-
APPLICABLE TO PART NUMBER: 3KFUELASSY applies to CLINS 0010-0015.
Narrative D.2. PACKAGING REQUIREMENTS (SPECIFICATIONS/STANDARDS)-
APPLICABLE TO PART NUMBERS: 20KFUELASSY AND 50KFUELASSY applies to
CLINS 0020-0025 and CLINS 0030-0035.
Narrative D.3. PACKAGING REQUIREMENTS (SPECIAL PACKAGING INSTRUCTIONS)-
APPLICABLE TO PART NUMBER: 210K-IPDS applies to CLINS 0040-0045.
Question: Government provides percentages of tanks to be shipped to two locations while also providing three ship to locations and implying additional ship to locations. The Government states in each CLIN that an offeror is to price FOB Origin. Does the Government want us to price with shipping? How will it be evaluated?
Answer: FOB is Destination. For the purpose of offerors compiling FOB Destination offers, the final destination for the supplies will be one or more of the following destinations; in the following estimated percentages as listed in F.2. (for Part Number: 3KFUELASSY (CLINS
0011-0015)), F.3. (for Part Number: 20KFUELASSY (CLINS 0021-0025)), F.4. (Part Number:
50KFUELASSY (CLINS 0031-0035)), and F.5. (for Part Number: 210K-IPDS (CLINS 0041-
0045)). Exact ship to locations will be listed on any delivery order placed off of a contract awarded as a result of this solicitation.
Please reference L.4.2 Volume 2: Price Factor for information on the price factor and reference
M.4.2 Factor 2: Price Factor for how the price factor will be evaluated.
File details come from the government source that posted it. Updated .