This is a Questions and Answers document for a roof repairs, inspections, and maintenance contract at Fort Buchanan, Puerto Rico.

Core diagnostic testing including roofing core sampling, moisture contamination inspections using infrared equipment, and thermogram documentation are required as part of the base contract per Contract Specification Section 01 11 00. Contractors should not assume the presence of hazardous materials such as asbestos or lead unless identified by the Government; however, the Government will direct and compensate testing when hazardous materials are suspected or required to be verified in accordance with the applicable line item in the Schedule of Prices. If unexpected asbestos or lead is discovered, contractors must immediately notify the Contracting Officer and stop work in the affected area, then follow procedures outlined in Section 02 82 00 and the Operations and Maintenance Plans Technical Exhibits 3 and 4. The roof square footage provided in Technical Exhibit 1 represents estimated quantities for bidding purposes only; contractors must verify actual dimensions and site conditions during task order execution, as quantities may vary based on field measurements and existing conditions. The Government will coordinate facility access on a task-order-by-task-order basis for any ongoing or planned construction, renovation, or maintenance projects that may impact the roofing work.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof Repairs, Inspections and Maintenance at Fort Buchanan, Puerto Rico

Questions received from Vendors

1. Is the contractor required to perform core cuts, moisture scans, or any additional diagnostic testing as part of the base contract, or will such testing be directed only under specific task orders?

As per Contract Specification Section 01 11 00 paragraph 3.3, Item c and Item d: (c) Roofing cores sampling and location within the roof, and testing to determine system components, and roofing system type. (d) Inspection for subsurface moisture contamination with Infrared Equipment, provide thermograms and exact location within the As-Built roof plan drawing.

2. Should contractors assume the presence of hazardous materials (e.g., asbestos, lead) within existing roof assemblies, or will the Government provide any known hazardous materials reports for the facilities?

Contractors shall not assume the presence of hazardous materials within existing roof assemblies unless otherwise identified by the Government.

Where hazardous materials such as asbestos are suspected or required to be verified, the Government will direct sampling and laboratory testing in accordance with Section 01 11 00 Part 3.3 e. Testing will be performed and compensated under the applicable line item in the Schedule of Prices.

If an unexpected discovery of Asbestos or Lead occurs, refer to Section 02 82 00 Part

1.3.2 and the Operations and Maintenance Plans Technical Exhibits 3 and 4. Notify the Contracting Officer if any previously untested building components suspected to contain asbestos are impacted by the work. Contractors should stop working in the affected area immediately after notification.

Although all known history of asbestos located on roof structures has been resolved to date, the asbestos plan should be taken into consideration for all task orders and put into action if any signs of asbestos are identified

3. Are the roof square footages listed in Attachment 3 considered final and Government-verified, or should contractors expect variations based on field measurements?

The roof square footage provided in Technical Exhibit 1 is estimated quantities for bidding purposes.

After award, contractors shall verify the dimensions and site conditions in the field in accordance with the task order issue at the time. Actual quantities may vary based on field measurements and existing conditions.

4. Is the Government aware of any ongoing or planned construction, renovation, or maintenance projects that may overlap with or restrict access to buildings included in this roofing requirement?

All facility access coordination will be performed by the Government on a task order by task order basis.

5. What buildings are considered to have Asbestos on the roof?

Refer to answer in question 2.