AIT Complex, Phase 2, Dining Facility, Fort Sill, Oklahoma Federal contract opportunity
Solicitation number
W912BV21R0004
Issued by
Department of the Army Corps of Engineers Engineering District Tulsa

About this file

This document is a solicitation for the construction of an Advanced Individual Trainee Barracks Complex, Phase 2 Dining Facility at Fort Sill, Oklahoma. The solicitation is seeking a firm fixed-price contract awarded based on best value to the responsible offeror whose proposal conforms to the terms and conditions and offers the best overall value. Evaluation will consider past performance, management approach, performance capability, and price, with past performance and management approach being the most important factors. Offerors must submit separate technical and price proposals by the closing date. Key personnel requirements include a project manager with 10 years' experience and degrees, as well as qualified personnel to fill construction, quality control, safety, and superintendent roles.

View the file

Other files for this federal contract opportunity

Other files attached to AIT Complex, Phase 2, Dining Facility, Fort Sill, Oklahoma, newest first.
File Type Posted
W912BV21R0004_AM0007.pdf PDF
W912BV21R0004_AM0006.pdf PDF
W912BV21R0004_AM0005_Compiled.pdf PDF
W912BV21R0004_AM0004.pdf PDF
W912BV21R0004_AM0003.pdf PDF
AM0002 - Sheet - G-001 - COVER SHEET.pdf PDF
AM0002 - Sheet - IN601 - MATERIALS FINISH LEGEND.pdf PDF
Fort Sill Installation Design Standard.pdf PDF
AM0002 - Section 01 11 00 - Paragraph 1.3 Redacted.pdf PDF
DFAC Site Visit Location.jpg JPG image
W912BV21R0004_AM0001.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part2.pdf PDF
_Ft Sill DFAC - Specifications_Final.pdf PDF
Ft Sill DFAC - PLANS - VOL 1.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part4.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part1.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part7.pdf PDF
Ft Sill DFAC - PLANS - VOL 2.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part5.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part3.pdf PDF
Ft Sill DFAC - PLANS - VOL 3_Part6.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This Amendment is to provide edits to Section 00 22 11, Specification Section 01 11 00, and Finish Sheet IN601.

This Amendment also provides the most current Design Guide for Fort Sill.

The POC for this Amendment is the Contract Specialist: Tyler Godw in; tyler.l.godw in@usace.army.mil, 918-669-7281

1. CONTRACT ID CODE PAGE OF PAGES

1 28

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 15-Apr-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912BV21R0004

X 9B. DATED (SEE ITEM 11)

24-Mar-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Apr-2022

CODE

CONTRACTING DIV

US ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E. 81ST STREET

TULSA OK 74137-4290

W912BV 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912BV21R0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS

The following have been modified:

EVALUATION CRITERIA

SECTION 00 22 11

EVALUATION CRITERIA, BASIS OF AWARD

*AM0002

1. OVERVIEW

This is a competitive best value solicitation using trade off procedures for a construction contract for the Advanced Individual Trainee Barracks (AIT) 1300 persons Dining Facility (DFAC) project located at Fort Sill, Oklahoma. The Government will evaluate proposals in accordance with the criteria, described herein and award a firm fixed-price contract to the responsible firm whose proposal conforms to all the terms and conditions of the solicitation and is determined the overall best value to the Government.

General Description of Work: Construct the Advanced Individual Trainee Barracks Complex, Phase 2 Dining Facility located at Fort Sill, Oklahoma in accordance with the plans and specifications.

1.1 WHO CAN SUBMIT

a. Firms formally organized as small business construction contractors; firms associated specifically for this project as a small business. Associations may be as joint ventures, partnerships, or as key team subcontractors, or any other interested small business parties may submit proposals. Associations may be as joint ventures as a partnership in accordance with FAR 9.601, or as key team subcontractors. To qualify the requirements of paragraphs 5.1.2.a(3) and 7.1.1 (below) must be met.

b. Organization Conflicts of Interest (OCI) Disclosure: The Offeror shall provide a disclosure statement with its proposal which concisely describes all the relevant facts concerning past or present organizational conflicts of interest relating to work on this project. In the same statement, and if applicable, the Offeror shall provide information to assure the Government that the conflicts of interest have been mitigated and/or neutralized to the maximum extent possible. If a conflict of interest is discovered after award of this contract, the Contracting Officer will make a decision whether to terminate the contract.

2.0 BASIS OF AWARD

The Contracting Officer intends to award a firm fixed-price contract to the responsible Offeror whose proposal the Source Selection Authority determines conforms to the solicitation, is fair and reasonable, and offers the best overall value to the Government, considering all non-price factors described herein, and price. All evaluation factors, other than price, when combined, are considered significantly more important than price. The intent of this solicitation is to obtain the best proposal for the required work. The Government reserves the right to accept other than the lowest priced offer or to reject all offers. The Government will not award a contract if the proposal contains a deficiency, as defined in FAR 15.001. The Government reserves the right to reject any offer if the offer is not in the best interest of the Government.

If awarded the contract, the Offeror shall construct the project in accordance with the plans and specifications.

3.0 PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

3.1 REQUIREMENT FOR SEPARATE PRICE AND TECHNICAL PROPOSALS

3.1.1 Each Offeror shall submit a Price Proposal and Technical Proposal. The Price Proposal and Technical Proposal must be submitted as separate files. Ensure that each file is clearly marked to indicate its contents, and the identity of the Offeror.

3.1.2 The Price Proposal and Technical Proposal must be received by the closing date and time set for receipt of proposals.

3.1.3 No dollar amounts from the Price Proposal are to be included in the Technical Proposal.

3.1.4 All information intended to be evaluated as part of the Technical Proposal must be submitted as part of the Technical Proposal (Volume 1). Do not merely cross-reference similar material in the Price Proposal, or vice versa.

Also, do not include links to websites in lieu of incorporating information into your proposal.

3.1.5 TAB A: Deviations, Exception and Assumptions

Deviations and exceptions to the terms and conditions of the solicitation in either the technical or price proposal are neither encouraged nor desired. Should the offer include any standard company terms and conditions that conflict with the terms and conditions of the solicitation, the offer may be determined “unacceptable” and, thus, ineligible for award. Should the Offeror have any questions related to specific terms and conditions, these must be resolved prior to submission of the offer. Notwithstanding the above, if deviations and exceptions are included with the offer, the Offeror shall list and describe in detail the deviations and/or exceptions under Tab A. All deviations and exceptions shall be fully supported with the Offeror’s rationale and shall fully explain the impact, if any, on the performance and/or specific requirement of the RFP. Deviations from the minimum standard of quality required by the RFP shall not be accepted unless identified by the offeror’s proposal and specifically approved by the Contracting Officer in writing. If unapproved, the Contractor must provide the RFP requirements without additional cost to the Government. If approved, the accepted deviation will take precedence as a provision of the solicitation.

The Offeror shall also clearly describe on the Tab B submitted with the Price Proposal any exception to the contractual and/or technical terms and include the monetary impact on the solicitation with the price proposal. If the offeror has no deviations, exceptions, or assumptions to the terms and conditions of the solicitation, they must submit a statement indicating this. This information will not be evaluated separately but may impact the evaluation of other factors.

Offerors are urged to read paragraph 2.0 and the definitions contained in paragraph 10.3 9.3 carefully. *AM0002

3.2 DISCUSSIONS

The Government does not intend to enter into discussions with offerors prior to making an award. Offerors are encouraged to present their best technical proposal and price proposal in their initial proposal submission. However, in accordance with FAR Part 15.306, should discussions become necessary, the Government reserves the right to hold them. If this occurs, a competitive range will be determined, and offerors notified. The competitive range may be limited for purposes of efficiency in accordance with (IAW) FAR Part 15.306(c)(2).

3.3 GENERAL INSTRUCTIONS

3.3.1 Submit only the electronic files specifically authorized and/or required elsewhere in this section. Do not submit excess information, to include audio-visual materials, electronic media, etc. All pages should be numbered and include working bookmarks.

3.3.2 Electronic copies of each volume shall be submitted through the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/ using the applicable solicitation number.

Proposals submitted by mail or hand-carried will not be evaluated. Proposals sent through proprietary or third-party File Transfer Protocol (FTP) sites or DoD SAFE will not be retrieved. It is the responsibility of the Offeror to confirm receipt of proposals. All proposals received after the exact time specified for receipt shall be treated as late submissions and will not be considered except under facts and circumstances allowed by the Federal Acquisition Regulation (FAR). For instructions on how to post an offer, please refer to the Posting Offer demo: https://pieetraining.eb.mil/wbt/sol/Posting_Offer.pdf.

It is the Offeror’s responsibility to obtain written confirmation of receipt of all electronic files of the full proposal by the DTRA Contracting office. In the event that the Solicitation Module is down, the alternate method for proposal submission is via email to: dtra.belvoir.al.mbx.fbo-notices@mail.mil ONLY. The Offeror must obtain prior approval from the Contracting Officer to use the alternate submission method. Offerors are responsible for ensuring electronic copies are virus-free and shall run an anti-virus scan before submission.

Electronic copies of each volume shall be compatible with the following software products: Adobe Acrobat Reader 11 and Microsoft Office Suite 2016. Narrative portions of the proposal shall be in Adobe Acrobat portable document file (pdf) searchable text format. Offerors shall not embed sound or video (e.g., MPEG) files into the proposal files.

Electronic files shall be clearly identified for each volume, section, and item. Proposals shall be tabbed and labeled in a manner to afford easy identification from a Table of Contents. Each page shall be identified with the appropriate page number centered at the bottom of the page.

3.3.3 Sheet size of the proposal contents shall be 8-1/2 inches x 11 inches where sheets are prepared specifically for this proposal, unless another paper size is specifically authorized elsewhere in this section for a particular submission. Do not use alternative paper sizes (e.g., 11” x 14” or 11” x 17” sheets) unless specifically authorized in this section for a particular submission. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. All page margins must be at least 1 inch wide but may include headers and footers. Proposals shall not exceed page limitations as defined in the individual Factor limitations noted in the paragraphs below, excluding the cover sheet and Table of Contents. A page is defined as text or information on one side of the paper. The Government will not evaluate any information beyond the total page limitations noted in the individual Factor limitations noted in the paragraphs below. The Government will not review any information submitted in an appendix or attachment to the proposal. The Offeror shall not submit verbatim sections of this solicitation as part of their proposal. Offers that do not meet these requirements may be subject to rejection.

3.3.4 “Confidential” projects cannot be submitted to demonstrate capability unless all of the information required for evaluation as specified herein can be provided to the Government as part of the Offeror’s technical proposal.

Proposals containing information that is not to be disclosed to the public for any purpose, or used by the Government except for evaluation purposes, must be clearly marked in accordance with the instructions at FAR 52.215-1, “Instructions to Offerors— Competitive Acquisition,” paragraph (e), “Restriction on disclosure and use of data.”

3.3.5 For submissions with page limitations: Where authorized, fold-out pages (11" x 14" or 11" x 17") will count as one page. Tables of content, proposal cover letters, and tabs between proposal information do not count toward any page limitations in the proposal.

3.3.6 Proposal revisions shall be submitted as page replacements with revised text readily identifiable, e.g., bold face print or underlining. The source of the revision, e.g., Error, Omission, Clarification, or amendment shall be included and be annotated for each revision. Proposal replacement pages shall: be numbered; be clearly marked “REVISED;” show the date of revision.

A revised copy of the entire proposal in .pdf format shall be provided via the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/or via email to tyler.l.godwin@usace.army.mil and copy julie.s.hill@usace.army.mil.

3.4 SPECIFIC INSTRUCTIONS FOR THE TECHNICAL PROPOSAL (VOLUME 1)

3.4.1 Technical Proposal. Proposals shall contain the entire proposal in .pdf format using Adobe Acrobat software to print to a .pdf file; do NOT scan the document(s) into a .pdf file. The text portion of the complete proposal shall be contained as a single .pdf file. Sections of the proposal shall be bookmarked (linked to the index) in logical order.

3.4.2 Format and Contents of the Technical Proposal and List of Tabs. The technical proposal will be appropriately organized using the tabs specified in the chart below. The proposals shall contain a detailed table of contents. A cover sheet identifying the Offeror (name, address, point of contact), project description, and solicitation number shall be provided. The second sheet shall be a Table of Contents. Offers that violate these rules unnecessarily delay the evaluation process and may be rejected by the Government after the initial evaluation without receiving any further consideration. The Government will not evaluate any information beyond the page limitation noted.

3.4.3 Page Limitations. The following page limitations are established for each factor and subfactor:

Factor 1 – Past Performance – No overall page limitation.

Each project submitted shall be limited to two (2) pages per project.

Factor 2 - Management Approach:

Sub-factor 1, Technical Approach – Limited to 12 pages Sub-factor 2, Organization– Limited to 5 pages Sub-factor 3, Key Personnel – Limited to 2 pages for each resume provided

Factor 3 - Performance Capability Sub-factor 1, Proposed Contract Duration and Summary Schedule – No page limit may be (11" x 14" or 11" x 17"). Schedule narrative is limited to 5 pages.

Sub-factor 2, Specialized Experience Key Subcontractors – No page limitation. Each project submitted shall be limited to one (1) page per project

3.5 SPECIFIC INSTRUCTIONS FOR THE PRICE PROPOSAL (VOLUME 2)

3.5.1 Price Proposal. Submit the Price Proposal in read only PDF files.

3.5.2 Size Restrictions and Page Limits. The following are established for Factor 4 – Section 00 11 00 Pricing Schedule: no page limit.

Proposal materials shall be submitted in PDF file. Do not use a font size smaller than 10, an unusual font style such as script, or condensed print for any submission. Each page shall be identified with the appropriate page number centered at the bottom of the page. Sheet size of the proposal contents shall be 8-1/2 inches x 11 inches. There are no page limits set for the Price Proposal. However, limit your response to information required by this solicitation.

Excess information will not be considered in the Government’s evaluation.

3.5.3 Format and Contents of the Price Proposal and List of Tabs.

The Price Proposal shall be tabbed and labeled in a manner to afford easy identification from a Table of Contents, as indicated in the following chart. Note: If the Offeror is not required to submit any information under a listed Tab (such as a JV Agreement) in accordance with the instructions below, that tab can be omitted. However, do not renumber the subsequent tabs.

4.0 PROPOSAL CONTENTS AND RELATED EVALUATION FACTORS

VOLUME 1 – TECHNICAL PROPOSAL

Factor/ Subfactor/ Element

LOCATION DESCRIPTION RELATIVE IMPORTANCE

N/A Vol 1 TAB A DEVIATIONS, EXCEPTIONS, AND ASSUMPTIONS

Not rated but may impact the evaluation of factors

FACTOR 1 Vol 1 TAB B PAST PERFORMANCE Most Important Factor

FACTOR 2 MANAGEMENT APPROACH 2nd Most Important Factor

Subfactor 1

Vol 1 TAB C Technical Approach Most Important Sub-factor

Subfactor 2 Vol 1 TAB D Organization 2nd Most Important Subfactor

Subfactor 3 Vol 1 Tab E Key Personnel 3rd Most Important Subfactor

FACTOR 3 PERFORMANCE

CAPABILITY

3rd Most Important Factor

Subfactor 1 Vol 1 Tab F Proposed Contract Duration And Summary Schedule

Most Important Subfactor

Subfactor 2 Vol 1 Tab G Specialized Experience Key Subcontractors

2nd Most Important Subfactor

VOLUME 2 – PRICE PROPOSAL

Factor/ Subfactor/ Element

LOCATION

DESCRIPTION

RELATIVE IMPORTANCE

N/A Vol 2 Tab A Proposal Cover Sheet Not Rated

N/A Vol 2 Tab B Signed Letter Responding to RFP, SF1442 and Acknowledgement of Amendments

Not Rated

FACTOR 4 Vol 2 Tab C SECTION 00 11 00, PRICING

SCHEDULE

5th Most Important Factor All technical factors, when combined, are significantly more important than price N/A Vol 2 Tab D Bid Guarantee (Bid Bond) Not Rated

N/A Vol 2 Tab E Representations & Certifications Not Rated

N/A Vol 2 Tab F JV Agreement (if applicable) Not Rated

5.0 VOLUME 1 TAB B – FACTOR 1 PAST PERFORMANCE

There are two aspects to the performance confidence evaluation: relevancy and quality of past performance. In accordance with FAR 15.305(a)(2), the currency and relevance of the information, source of the information, context of the data, and general trends in contractor's performance shall be considered. Relevance and quality of performance will be combined to establish one performance confidence assessment rating for each Offeror.

5.1 RELEVANCY OF PAST EXPERIENCE

5.1.1 These projects must be of relevant scope and complexity to the solicited project. The Offeror shall submit information on up to five (5), but no more than five (5), completed projects demonstrating the Offeror's recent and relevant experience using the Company – Specialized Experience form – (Attachment 1) at the end of the section. If any of the information required is not included in these forms, the Offeror will be considered non-responsive and evaluated as unacceptable. Each project submitted shall be limited to two (2) page per project. Projects must be one hundred percent (100%) complete or meet the Beneficial Occupancy Date (BOD) requirement.

All projects must have a construction completion date or BOD no earlier than seven (7) years preceding the original date of issuance of this solicitation. BOD is the point at which the customer determines the facility or area can be occupied from both a regulatory and work function standpoint.

5.1.2 To determine relevance, the agency will evaluate the following. This list is not all-inclusive. The offeror may submit other types of projects but must explain the relevancy of those projects to the project that is being solicited in this RFP. However, the more items that are included in a project the more relevant the experience and the more credit will be given:

i. A project with a value of $15M.

ii. A project that involved the construction of a dining facility or the construction of a large restaurant or cafeteria with an industrial kitchen.

iii. A Design-Bid-Build project.

iv. A project constructed on Military installation or other restricted access sites.

v. Projects that demonstrate experience with High Performance and Sustainable Building (HPSB) Guiding

Principles certification per UFC 1‐200‐02, LEED certification or, other third-party sustainability certifications.

5.1.3 The Offeror shall submit the requested information to demonstrate a record of recent, related experience, for the facility types. Offerors may identify state and local government and private contracts that are similar to the Government’s requirements as outlined in the Summary of Work Section 01 11 00.

5.1.4 If the Offeror is a joint venture or teaming arrangement, each firm shall provide information, demonstrating experience relevant to their role on this project. Offeror shall provide a copy of the joint venture agreement or letters of commitment for all teaming contractors, agreements and letters of commitment will not count towards the page limitations, failure to provide the joint venture agreement or letters of commitment will result in the proposal being evaluated as unacceptable. If any firm has multiple functions or divisions, limit the project examples to those performed by the division or unit submitting the offer or by the team member. Joint Venture partners or teaming partners should each demonstrate experience commensurate with their role on this project. If any of the information required is not included in the forms (Attachment 1), then the Contractor will be considered non-responsive and evaluated as unacceptable.

5.1.5 To receive credit for extent (amount) of experience, the Offeror shall demonstrate a history of recent, relevant experience. A firm will not receive credit under this factor for the relevant experience of key personnel proposed for this project. If Offeror represents the combining of two or more companies for the purpose of this RFP, the proposal shall clearly identify the contractual responsibilities of each firm and the work to be performed by each;

describe the nature of the association; indicate whether the firms have experience working together in construction ventures, including how long and how many projects. In addition, each company, including joint ventures, shall list their Government contract experience. Provide a copy of the commitment letter of the firms (see Attachment 5) or the Joint Venture Agreement. A copy of the teaming or joint venture agreement(s) must be appended to the plan under Factor 2 Sub-factor 1 (not included in the page limitation). If the letter of commitment is not included for a teaming subcontractor, the contractor will not receive credit for teaming subcontractor’s experience under this factor and the submitted projects will not be reviewed. Each member of the team must provide one (1) to two (2) "recent", "relevant" projects performed by the team member that reflect the team member's experience commensurate with their role on this project or how their experience qualifies them for their role on this project. In such instances the combined experience projects, submitted by each member of the team, shall not exceed the maximum number of projects stated in paragraph 5.1.1.

5.1.6 The Government will consider extent of recent experience, degree of relationship of such experience to this project, demonstrated familiarity with applicable codes and local conditions. Some examples of relevancy to this project may include, but not be limited to:

i. Number, size, type work, complexity, location

ii. Dates completed no more than seven (7) years preceding date of Solicitation

iii. Firm's role and extent of work self-performed (brokering out all work and simply “placing the sidewalks” on a cited project are examples of less relevant experience)

5.1.7 The Government may consider previous recent teaming experience among the team members, JV partners or key teaming subcontractors, as value added, even if on different type design and/or construction projects than this project. The more relevant the experience, the more credit will be given.

5.2 PERFORMANCE ASSESSMENT

5.2.1 For each of the projects submitted, provide a copy of the Contractor Performance Assessment Reporting System (CPARS) report. If CPARS does not exist, please provide a Past Performance Questionnaire (PPQ) (Attachment 2) to a representative of the owner. The Past Performance Questionnaire included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1, Past Performance. Ensure correct phone numbers and email addresses are provided for the client point of contact. Completed Past Performance Questionnaires should be submitted with your proposal. If the offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the offeror should complete and submit with the proposal the first page of the PPQ (Attachment 2), which will provide contract and client information for the respective project(s). Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Tyler Godwin via email Tyler.L.Godwin@usace.army.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.

However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Form PPQ-0 at Attachment 2 shall be utilized and offerors shall submit the PPQ with their proposal submission to the Contracting Office designated proposal submission location. The contract specialist or Contracting Officer will not require the PPQ to be sent directly from the client. If you have questions regarding the attached questionnaire, or require assistance, please contact the Contract Specialist at (918) 669-7281.

5.2.2 The Government reserves the right to verify the experience record of cited projects or other recent projects by reviewing Past Performance Information Retrieval System (PPIRS), Contractor Performance Assessment Reporting System (CPARS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), other databases; or interviews with Program Managers, Contracting Officers, and Fee Determining Officials; and the Defense Contract Management Agency or to interview owners or references. The Government may check any or all cited references to verify supplied information. The information obtained from these sources will be evaluated supplementary to the past performance questionnaires. In reference to the contracts pulled from these sources, the relevancy of the projects, completion dates, ratings and comments in the individual categories and overall ratings will be considered in making the overall confidence assessment.

5.2.3 While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror. The offeror is responsible for ensuring that the completed questionnaires are submitted by the closing date.

*AM0002

5.2.4 No additional information may be submitted under this factor, unless the Offeror is submitting proposals as a Joint Venture in which case the offeror shall provide the brief narrative as described in paragraph 5.2.9.d 5.3.d below. Inclusion of additional information will result in the contractor being found unacceptable and may result in the contractor being removed from further consideration.

5.2.5 The Government will evaluate the responses from the customers from which Past Performance Questionnaires have been received. The Government may contact and interview points of contact on the Past

Performance Questionnaires. The Government reserves the right to interview other individuals acting for the listed references if the listed reference is not available. In addition to the above, the Government may review any other sources of information for evaluating past performance.

5.2.6 To improve accuracy of database searches, the offeror will also provide the CAGE Codes for the prime contractor and all teaming partners, i.e., design firms, key subcontractors, Joint Venture Partners, whose experience is being relied on.

5.2.7 The Government may contact references, for information regarding the Offeror’s past performance on the project and for the purposes of assessing and verifying Section 00 22 11 the scope of the work performed. Offerors should provide accurate, current, and complete contact information for references provided in the project descriptions.

5.3 JOINT VENTURE SUBMISSION REQUIREMENTS

a. Offerors submitting proposals as a Joint Venture (JV) shall obtain a DUNS number and be registered in the CCR as the offering Joint Venture. The Offeror must provide three (3) to five (5) "recent", "relevant" projects performed by the JV that reflect the JV's ability to perform the work required in this.

b. If the Offeror cannot provide a sufficient number of projects as the JV to meet the minimum requirement, the Offeror must provide those "recent", "relevant" projects that it has performed as the JV, and then supplement the record with additional "recent", "relevant" projects performed by each JV member in their individual capacities. In such instance, each JV member must satisfy a minimum requirement of two (2) projects, to include any performed as the JV.

c. If the JV has no "recent", "relevant" projects performed by the JV, then each member of the JV must provide two (2) to three (3) "recent", "relevant" projects performed by the JV member that reflect the JV member's experience commensurate with their role on this project or how their experience qualifies them for their role on this project as required. In such instances the combined experience projects, submitted by each member of the JV, shall not exceed the maximum number of projects stated in paragraph 5.1.1

d. In addition to the examples of "Company Specialized Experience" and "Past Performance Surveys", the Joint Venture shall provide a brief narrative not to exceed five (5) pages stating the roles that each partner of the Joint Venture will perform on this project and how the presented projects demonstrate the JV member's experience commensurate with their role on this project or how their experience qualifies them for their role on this project.

The attached “Specialized Experience" and "Past Performance Survey" forms shall be used by the Joint Venture or the JV partners. Explain how the JV is structured.

e. Verification: The Government reserves the right to verify the experience record of cited projects or other recent projects not submitted by reviewing the Past Performance Information Retrieval System (PPIRS), or other Government appraisal systems or to interview owner or references. The Government may check any or all cited references to verify supplied information. An Offeror will be afforded the opportunity to reply to or explain adverse performance information to which the Offeror has not previously had an opportunity to address.

5.4 RATING METHODS

5.4.1 Each submitted project will be assigned one of the levels of relevancy shown in Table 1.

Table 1. Past Performance Relevancy Rating Method

Adjectival Rating Definition Very Relevant Present/past performance effort involved essentially the same scope and magnitude of effort and complexities this solicitation requires.

Relevant Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

Somewhat Relevant Present/past performance effort involved some of the scope and magnitude of effort and complexities this solicitation requires.

Not Relevant Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

5.4.2 In reviewing each past performance effort by the Offeror, the Source Selection Evaluation Board (SSEB) will then evaluate the overall quality of the Offeror's past performance (see FAR 15 .304(c)(2)) to determine the performance confidence assessment rating. The past performance evaluation conducted in support of a current source selection does not establish, create, or change the existing record and history of the Offeror's past performance on past contracts; rather, the past performance evaluation process gathers information from customers on how well the Offeror performed those past contracts.

5.4.3 The Government will consider the currency and relevance of the information, source of the information, context of the data, and general trends in contractor performance. With respect to relevancy, past performance on projects with more relevance will typically be a stronger predictor of future success and have more influence on the past performance confidence assessment rating than past performance on projects of lesser relevance.

Owners/references may be asked to comment on items such as quality of design or construction, timeliness, management of the work, subcontractor management, including timely payment to subs or suppliers, safety, relations between owner and designer or contractor, level of support for such things as as-built documentation, O&M manuals, training, correcting design or construction errors, warranty work, etc. The Government will target areas covered in the requirements of this proposal including records of confirming quality, schedule, cost control, customer satisfaction, level of support for such things as as-built documentation, O&M Manuals, training, problem resolution for design or construction errors, warranty work, and safety. The Government will not release the Interview Forms to the Offeror at any time, in order for the Government to solicit candid, unbiased interview comments. The Government also places a higher value on projects which document successful outcomes and are supported by outside source confirmation, for example, but not limited to telephone databases, Offeror-furnished references, or personal knowledge. The Government also places a higher value on projects, which provided particularly difficult or unique challenges and the innovative methods the contractor used to resolve problems successfully. (see Table 2 below).

5.4.4 The past performance confidence assessment rating is based on the Offeror's overall record of recency, relevancy, and quality of performance. At the conclusion of the assessment, the Offeror shall be assigned one of the ratings in Table 2.

Table 2. Performance Confidence Assessment Adjectival Rating Definition Substantial Confidence Based on the Offeror’s recent/relevant performance record, the Government has a high expectation that the Offeror will successfully perform the required effort.

Satisfactory Confidence Based on the Offeror’s recent/relevant performance record, the Government has a reasonable expectation that the Offeror will successfully perform the required effort.

Limited Confidence Based on the Offeror’s recent/relevant performance record, the Government has a low expectation that the Offeror will successfully perform the required effort.

No Confidence Based on the Offeror’s recent/relevant performance record, the Government has no expectation that the Offeror will successfully perform the required effort.

Unknown Confidence (Neutral)

No recent/relevant performance record is available, or the Offeror’s performance record is so sparse that no meaningful confidence assessment rating can be reasonably assigned.

5.4.5 Each entity (firm) will be rated on its own performance or that of its predecessor, as defined in FAR 52.204-20, if relevant. An entity may not establish past performance based on the past performance of its proposed key personnel, apart from that of the entity. If the Government does not obtain past performance information for the projects identified by the Offeror and cannot establish a past performance record for the Offeror through other sources, past performance will be rated neither favorably nor unfavorably. The performance confidence assessment will be considered “Unknown Confidence”.

6.0 VOLUME 1 - FACTOR 2 - MANAGEMENT APPROACH

6.1 VOLUME 1, TAB C: SUBFACTOR 1 - TECHNICAL APPROACH

6.1.1 Submission Requirements:

6.1.1.1 Provide information that describes the offeror’s intended technical approach to executing the construction contract per the detailed requirements herein. Limit the information to 12 pages or less concisely describe the technical approach to project management and execution.

6.1.1.2 Offeror’s Understanding: Describe challenges, risk, and constraints associated with the project and how the offeror intends to address each with means and methods, resources, or internal organizational processes.

6.1.1.3 Technical Approach for Construction: Describe the technical approach to construction for the facility.

Describe any proposed phasing plan for construction of the Advanced Individual Trainee Barracks (AIT) Complex, Phase II Dining Facility (DFAC). Describe interactions within the team and with the Corps of Engineers during construction.

6.1.14 Subcontractor Approach and Management: Describe how subcontractors are managed by the contractor.

Discuss how subcontract relationships are structured to assure proper balance and flow-down of contract requirements, duties, responsibilities, and properly balanced and proportioned risk management. Discuss how non-performance by subcontractors is handled by the general contractor. Discuss the types of relationships the general contractor has with local small business subcontractors and how the general contractor promotes the development of small business subcontractors to include training, development, and mentoring. The Government wants to understand that the general contractor places emphasis on strong business relationships with subcontractors to maximize the number of quotes the general contractor obtains during proposal preparations that demonstrates market competition and the best valued prices are being provided to the Government. General Contractors that do not maintain solid business practices with small business subcontractors increase business costs to the Government.

6.1.15 Planning and Scheduling: Describe the time control capabilities and systems to be used and how the schedule will be used to manage construction. Discuss internal procedures for handling delays to minimize time growth.

6.1.1.6 Self-Performed Work: Generally, describe the items the Offeror will self-perform to comply with the requirements in FAR Clause 52.236-1 for self-performed work. All other items not self-performed will be assumed by the Government to be subcontracted. It is the position of the government that self-performance of items allows the general contractor greater control of the work and yields in cost savings to the government as the amount of subcontracted markups are reduced and provide a cost savings to the government and government customers.

6.1.1.7 Quality Control: Describe the team’s quality control approach, corporate systems and capabilities to maintain quality control of the construction. Describe the proposed quality control organization, including the proposed staffing plan. Provide information on how you will handle internal and external requests for information, shop drawings, progress meetings, site visits, contract completion, closeout, as-built, and completion documentation;

failure to address these areas at a minimum within the Quality Control section will be considered non-responsive and evaluated as unacceptable. There is no need to submit a quality control plan as the successful offeror will provide that after award. Describe how the team will meet USACE three phase quality control requirements, and how the three phase inspections will be integrated and documented within RMS.

6.1.1.8 Safety Plan: Describe the team’s safety approach, corporate systems and capabilities to maintain safety requirements during construction. Describe the proposed safety organization, including the proposed staffing plan.

The intent is to provide enough detail to demonstrate the Offeror’s understanding Section 00 22 11 of the project;

however, it is not the intent for the Offeror to provide the amount of detail that will be required in the pre-work submittals contained in Division 01 of this RFP.

6.1.2 Evaluation Criteria:

6.1.2.1 The Government will evaluate the strengths, weaknesses and any deficiencies in the plan. The Government will evaluate the firm’s understanding of the requirements described in the Division 01 requirements and the plans and technical specifications of the Solicitation and the capability to execute the project. Some additional specific evaluation considerations are listed below. This list is not all inclusive.

6.1.2.2 Offeror’s Understanding: The Government will evaluate the offeror’s understanding of the challenges and risks associated with this project and the specific methods, resources, or internal processes that will be employed to mitigate those challenges and risks.

6.1.2.3 Technical Approach for Construction: The Government places a higher value on an offer that provides proposed methods to streamline construction, manage labor and other resource constraints in an effort to reduce costs and support aggressive schedules while upholding strict safety standards. In addition, clear and concise proposed phasing plans for construction of the Advanced Individual Trainee Barracks (AIT) Complex, Phase II Dining Facility (DFAC) will be viewed more favorably. The Government will also consider whether the approach reduces on-site craft labor and susceptibility to inclement weather delays.

6.1.2.4 Subcontractor Approach and Management: The government will evaluate the general contractor’s ability to develop and maintain strong subcontractor and small business relationships. The Government will evaluate the general contractor’s subcontractor management model and processes.

6.1.2.5 Planning and Scheduling: The Government will evaluate the offeror’s scheduling capabilities to manage construction of the Advanced Individual Trainee Barracks (AIT) Complex, Phase II Dining Facility (DFAC) to include processes that will be employed to handle delays and minimize time growth.

6.1.2.6 Self-Performed Work: The Government will evaluate the Offeror’s proposal to ensure that the self-performed work complies with the requirements of Clause 52.236-1 for self-performed work.

6.1.2.7 Quality Control. The Government will evaluate the Offeror’s capabilities and understanding of the contractually required quality control processes for construction. The Government will evaluate the adequacy of the staffing plan to cover all required tasks and responsibilities.

6.1.2.8 Safety Plan: The Government will evaluate the narrative for realism, logic, and understanding of the contractual requirements in regard to the safety plan.

6.2 VOLUME 1 -TAB D: SUBFACTOR 2- ORGANIZATION

6.2.1 Submission Requirements:

6.2.1.1 Provide information that describes the offeror’s organization. Limit the information to 5 pages or less to include the required organization charts; clearly but concisely describe the organization the 5-page limit does not include unequivocal letters of commitment submitted for key personnel, unequivocal letters of commitment for teaming subcontractors, or the joint venture agreement.

6.2.1.2 Organization: Describe what firms, their resources and how their resources will be utilized, their roles and responsibilities and any contractual arrangements that have been established. Clearly describe any teaming or joint venture arrangements, including a clear description of each firm’s roles and responsibilities on the project. A copy of the teaming or joint venture agreement(s) shall be appended to the plan (not included in the page limitation). Include a simple organizational chart, illustrating the organization, including the proposed quality control group(s). Present a matrix of responsibilities for each firm in executing the key work breakdown structure activities of the project, including construction activities for each major feature. Identify the firms chosen for the project, if not to be self-performed, Offerors will be required to identify the specific firm(s) chosen for Electrical, Mechanical, Structural, and Fire Protection work. The Offeror shall be required to obtain the Contracting Officer’s approval for any substitution of firms listed. Describe the proposed management structure for the team, describing how the construction process will be managed and the authorities and the delegations of authority within the team. Include a key personnel organization chart that clearly depicts the key positions and the names of the personnel, their firm affiliations and their job locations, their job/position title within the organization. The key personnel organization chart shall be consistent with the corporate organization chart, with the matrix of responsibilities assigned to the firms, and with the list of key personnel.

Provide any joint venture agreements or letters of commitment, will not count towards the page limitations.

6.2.2 Evaluation Criteria:

6.2.2.1 Organization. The Government will evaluate the clarity and strength of the overall organization and how well it is organized, structured and staffed to execute the entire scope of work. If applicable, joint venture participants’/teaming subcontractor’s contribution to the organization should be commensurate with their skills and background.

6.3 VOLUME 1 – TAB E: SUBFACTOR 3 - KEY PERSONNEL

6.3.1 Submission Requirements

6.3.1.1 Offeror shall provide resumes for key personnel; including team members, which demonstrate the qualifications necessary for this project, which includes proposed role, relevant education and training; and previous relevant experience in similar type work, to manage, control and perform construction. Resumes shall include detailed experience in proposed role, relevant education & training, total relevant experience. Clearly indicate whether individual has had a significant role in any of the cited project examples from Factor 1. If re-assignment of personnel is considered possible, provide alternate professionals in each assignment (if multiple individuals are proposed for the key positions identified – the least qualified will be the basis of the evaluation).

For each person provide a brief resume, using the Key Personnel Resume forms (Attachment 3) at the end of this section, minimum years of experience must be verifiable, with example projects from the present back the minimum number of years, to include dates of work performed. Limit each resume to not more than two

(2) pages. Key personnel shall at a minimum include on site Project Manager responsible for construction, site safety manager (SSHO), the on-site Quality Control manager (CQC System Manager), and construction Site Superintendent. Provide unequivocal letters of commitment from all proposed key personnel not currently employed by the prime contractor. Use the form letter (Attachment 4) at the end of this section.

6.3.1.2 Minimum qualifications of Key Personnel include:

6.3.1.2.1 On Site Project Manager – reference Section 01 45 00.00 15, Paragraph 3.5. The Project Manager shall have a minimum of a bachelor’s degree and 10 years construction experience

6.3.1.2.2 Construction Quality Control Systems Manager (CQCSM) – reference RFP Section 01 45 00.00 15, Paragraph 3.4.2. Meets the qualifications of any of (A), (B), or (C): (A) Licensed Professional Engineer with 3 years’ construction experience -OR- (B) Bachelor’s degree of Engineering or Construction Management (or equivalent) with 5 years’ construction experience -OR- (C) 10 years relevant construction experience. Relevant construction experience includes any work requiring oversight of construction quality and adherence to plans and specifications this includes work as a crew foreman, QCM, Assistant QC, Superintendent, or combination thereof to meet the 10-year requirement. In the event that the QCM will fill a role of one of the specialists listed below – the resume shall specifically indicate those specialist roles that will be accomplished by the QCM. The resume shall clearly demonstrate that the proposed QCM meets the qualifications of the QC specialist listed in paragraph 3.4.3 “Experience Matrix” table.

a. Electrical QC Specialist – reference RFP Section 01 45 00.00 15, Paragraph 3.4.3

b. Mechanical QC Specialist –…