H01 Contract Phase Sequencing.docx

DOCX document 37 KB Posted

Attached to
MDC 3289 Revetment Barges FY25
Solicitation number
w912bu25ba004
Issued by

About this file

The document H01 Contract Phase Sequencing.docx details the contract phase timeline for a project involving revetment barge construction. The contract is structured with three sequential phases: Phase II (Construct, Test, and Deliver) spans 430 calendar days, with a 15-calendar day receipt period, followed by Phase III (Delivery) which is allocated 30 calendar days. This phased approach allows for systematic progression and government review between each stage of the project.

The phase sequencing aligns with the associated Federal Contract Opportunity (Solicitation w912bu25ba004) for the U.S. Army Corps of Engineers, which requires the construction of four welded steel revetment barges. Each barge will be 160' long, 36' wide, with 11' depth, designed to support the Mat Sinking Unit. The total project completion timeline is 490 calendar days after the Notice to Proceed, including 15 calendar days between phases for government review. The project falls under NAICS Code 336611 (Ship Building and Repairing) with a small business size standard of 1,300 employees, and solicitation documents will be exclusively available on SAM.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECEIPT BY CONTRACTOR OF PSN PHASE II (CONSTRUCT, TEST AND DELIVER) 15 Calendar Days.

CD

CONTRACT PHASE SEQUENCING

Phase II 430 Calendar Days Calendar Days

CONSTRUCT, AND TEST

CD

Phase III 30 Calendar Days Calendar Days

DELIVER